← Back to Patent Explorer
US5278750A Expired / Lapsed US ⏱️ 0.0 years remaining

Production schedule making method

Assignee: Toyota Motor Corp
•
Filing: 1991-08-19
•
Granted: 1994-01-11
•
Expires: 2011-08-19
📄 Original PDF 🌐 Google Patents 🔄 Sync Now

Abstract

Abstract A method for making a production schedule of an instant process which produces a plurality types of products and supplies the products to a plurality of following processes by trucks. A truck delivery schedule including a number of truck deliveries and times is taken into account when the production schedule of the instant process is made. On the production schedule, a production order of the products is determined, and a stocking schedule also is made on the production order schedule.

Inventors

  • 👤 Kuniya Kaneko
  • 👤 Harumichi Wakiyama
  • 👤 Tadasi Naito

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-11-03 16:20
CPC Classifications
G; G06; G06Q; G06Q10/00; G06Q10/06; G06Q10/063; G06Q10/0631; G06Q10/0633; G06Q10/0639; G06Q10/06395; Y; Y02; Y02P; Y02P90/00; Y02P90/02

Claims Analysis

Total Claims: 13
Claim 1
Independent Claim 192 words
A method for making a production schedule for an instant process that produces a plurality of types of products and supplies the products to a plurality of second processes by trucks, the method comprising the steps of: recording a second process schedule which includes numbers of products needed by the second process with respect to respective product types and respective days; recording a truck delivery schedule from the instant process to the second process and information included in a card called a KANBAN which is carried by each truck between the instant process and the second processes and which includes information about delivery types; determining a product shipment schedule of the instant process based on the second process schedule, the truck delivery schedule, and the KANBAN information; recording a working condition and a production condition of the instant process; determining a production schedule of the instant process based on the product shipment schedule, the working condition of the instant process, and the production condition of the instant process; and determining a production order of the products to be produced at the instant process based on the production schedule of the instant process.
Claim 2
Independent Claim 192 words
A method for making a production schedule for an instant process that produces a plurality of types of products and supplies the products to a plurality of second processes by trucks, the method comprising the steps of: recording a second process schedule which includes numbers of products needed by the second process with respect to respective product types and respective days; recording a truck delivery schedule from the instant process to the second process and information included in a card called a KANBAN which is carried by each truck between the instant process and the second processes and which includes information about delivery types; determining a product shipment schedule of the instant process based on the second process schedule, the truck delivery schedule, and the KANBAN information; recording a working condition and a production condition of the instant process; determining a production schedule of the instant process based on the product shipment schedule, the working condition of the instant process, and the production condition of the instant process; and determining a production order of the products to be produced at the instant process based on the production schedule of the instant process.
Claim 3
Dependent Claim 59 words
A method according to claim 1, wherein each of the second processes comprises a process including a normal working condition in which no work is scheduled on a weekend or holiday, and the KANBAN comprises an ordinary KANBAN in which there is a time lag between delivery of the KANBAN and delivery of the products corresponding to the KANBAN.
Claim 4
Dependent Claim 60 words
A method according to claim 1, wherein at least one of the second processes comprises a process including an extra working condition in which work is scheduled on a weekend or holiday, and the KANBAN comprises an ordinary KANBAN in which there is a time lag between delivery of the KANBAN and delivery of the products corresponding to the KANBAN.
Claim 5
Dependent Claim 60 words
A method according to claim 1, wherein at least one of the second processes comprises a process including an extra working condition in which work is scheduled on a weekend or holiday, and the KANBAN comprises an special KANBAN in which there is no time lag between delivery of the KANBAN and delivery of the products corresponding to the KANBAN.
Claim 6
Independent Claim 51 words
A method according to any one of claims 3 and 4, wherein the following process schedule comprises a schedule in which the numbers of products needed by the second process are modified so as to include also a number of products needed by the following process on the extra working day.
Claim 7
Independent Claim 43 words
A method according to any one of claims 1, 2, 3, and 4, and further comprising a step of making a stocking schedule of the instant process based on the determined production order of the products to be produced at the instant process.
Claim 8
Independent Claim 30 words
A method according to any one of claims 1, 2, 3, and 4, wherein the truck delivery schedule comprises a schedule specifying times when the trucks reach the second processes.
Claim 9
Independent Claim 45 words
A method according to any one of claims 1, 2, 3, and 4, wherein the KANBAN comprises a KANBAN specifying a number of truck deliveries per day and a time lag between delivery of the KANBAN and delivery of the products corresponding to the KANBAN.
Claim 10
Independent Claim 83 words
A method according to any one of claims 1, 2, 3, and 4, wherein the step of determining a product shipment schedule of the instant process includes steps of: dividing the numbers of the plurality of types of products needed by the second processes specified in the following process schedule by the number of truck deliveries specified in the KANBAN and distributing the divided numbers over the respective truck deliveries; and advancing the distributed numbers by the time lag specified in the KANBAN.
Claim 11
Independent Claim 54 words
A method according to any one of claims 1, 2, 3, and 4, wherein the step of determining a production schedule of the instant process includes a step of distributing the numbers of products specified in the product delivery schedule of the instant process over actual working periods of time as evenly as possible.
Claim 12
Independent Claim 74 words
A method according to any one of claims 1, 2, 3, and 4, wherein the step of determining a production order of products to be produced at the instant process includes steps of: calculating desired production magnitudes with respect to respective types of products and respective actual working times; and determining a product type having a maximum desired production magnitude at an actual working time as the product to be produced at the time.
Claim 13
Dependent Claim 130 words
A method according to claim 6, wherein the step of making a stocking schedule of the instant process comprises step of: determining an inspection order of products based on the production order of products; determining cumulative numbers of inspected products with respect to respective times and respective types of products; determining cumulative numbers of delivered products with respect to respective times and respective types of products based on the product shipment schedule; subtracting the cumulative numbers of delivered products from the cumulative numbers of inspected products to obtain numbers of products stocked at the instant process with respect to respective types of products and respective times; and adjusting initial stock numbers of products at the instant process so that the numbers of stocked products at respective times are not negative.

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1997-01-10 1997-07-12 1998-01-11 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 2001-01-10 2001-07-12 2002-01-11 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 2005-01-10 2005-07-12 2006-01-11 $7700.00 Window Closed / Lapsed

Assigned Categories & Tags

No categories assigned to this patent yet.

Assign Category Tag