US5066896A
Expired / Lapsed
US
⏱️ 0.0 years remaining
Electric lighting and power controllers therefor
Assignee: Strand Lighting Ltd
•
Filing: 1989-12-12
•
Granted: 1991-11-19
•
Expires: 2009-12-12
Abstract
Abstract In a lighting power controller having a controllable switch (such as a thyristor), in order to compensate for perturbations in the mains supply waveform, the waveform is analyzed and a table is set up of thyristor firing angle against output RMS voltage. To obtain a desired output RMS voltage, the thyristor is fired at the angle indicated by the table.
Inventors
- 👤 David R. Bertenshaw
- 👤 Richard Williamson
- 👤 John Wright
Bibliographic Details
Application Number
—
Jurisdiction
US
Data Source
google_patents
Last Synchronized
2026-10-28 00:25
CPC Classifications
H; H05; H05B; H05B39/00; H05B39/04; H05B39/08; G; G05; G05F; G05F1/00; G05F1/10; G05F1/12; G05F1/40; G05F1/44; G05F1/45; G05F1/455; H02; H02M; H02M5/00; H02M5/02; H02M5/04; H02M5/22; H02M5/25; H02M5/257; H02M5/2573; H02M5/2576
Claims Analysis
Total Claims: 12
Claim 1
Independent Claim
99 words
A method of controlling power supplied from an AC supply to a lighting load by a circuit including a controllable switch, the method comprising the steps of: measuring the supply voltage a multiplicity of times over a half-wave cycle of the supply; producing from the measured voltages a table indicating how the switch should be operated to obtain any of a multiplicity of RMS output voltages; receiving a signal indicative of a desired RMS output voltage; determining from the table the switch operation required for the desired RMS output voltage; and operating the controllable switch in the determined manner.
Claim 2
Independent Claim
99 words
A method of controlling power supplied from an AC supply to a lighting load by a circuit including a controllable switch, the method comprising the steps of: measuring the supply voltage a multiplicity of times over a half-wave cycle of the supply; producing from the measured voltages a table indicating how the switch should be operated to obtain any of a multiplicity of RMS output voltages; receiving a signal indicative of a desired RMS output voltage; determining from the table the switch operation required for the desired RMS output voltage; and operating the controllable switch in the determined manner.
Claim 3
Dependent Claim
160 words
A controller for an electric lighting load, comprising: a controllable switch for connecting an AC power supply to a lighting load; and means for controlling the switch to conduct during a halfwave cycle of the AC supply for a conduction period less than or equal to the half-cycle supply period to produce a desired switched output RMS voltage, the controlling means comprising: means to measure the AC supply voltage at a multiplicity of sampling times over a half-cycle period; means to calculate from the measured voltages for each of a plurality of sampling times the RMS voltage which would be obtained by causing the switch to operate in accordance with that sampling time; means to receive a signal indicative of the desired switched output RMS voltage; means to determine the sampling time for which the calculated RMS voltage corresponds to the desired RMS voltage; and means for operating the switch in accordance with the determined time in a half-cycle period.
Claim 4
Dependent Claim
160 words
A controller for an electric lighting load, comprising: a controllable switch for connecting an AC power supply to a lighting load; and means for controlling the switch to conduct during a halfwave cycle of the AC supply for a conduction period less than or equal to the half-cycle supply period to produce a desired switched output RMS voltage, the controlling means comprising: means to measure the AC supply voltage at a multiplicity of sampling times over a half-cycle period; means to calculate from the measured voltages for each of a plurality of sampling times the RMS voltage which would be obtained by causing the switch to operate in accordance with that sampling time; means to receive a signal indicative of the desired switched output RMS voltage; means to determine the sampling time for which the calculated RMS voltage corresponds to the desired RMS voltage; and means for operating the switch in accordance with the determined time in a half-cycle period.
Claim 5
Dependent Claim
26 words
A controller as claimed in claim 2, further comprising a low pass filter for filtering the measured AC supply voltage to remove high frequency interference therefrom.
Claim 6
Dependent Claim
24 words
A controller as claimed in claim 2, wherein the measuring means includes an analog-to-digital converter, the digital voltage values being stored in a memory.
Claim 7
Dependent Claim
68 words
A controller as claimed in claim 4, wherein the calculating means is operable to calculate for each of the sampling times a value representing the sum of the squares of the voltage values for each of the sampling times from that sampling time to the end of the half-cycle, and to store the calculated values as a table in a memory with addresses corresponding to the sampling times.
Claim 8
Dependent Claim
58 words
A controller as claimed in claim 5, further comprising means for forming in a memory an inverse of said table having values corresponding to the sampling times stored at addresses corresponding to RMS voltage values, the determining means being operable to address the inverse table memory according to the desired RMS voltage to determine the triggering time therefrom.
Claim 9
Dependent Claim
19 words
A controller as claimed in claim 5, further comprising means to transmit the table data to a further memory.
Claim 10
Dependent Claim
339 words
A controller for an electric lighting load, comprising: a controllable switch for connecting an AC power supply to alighting load: and means for controlling the switch to conduct during a halfwave cycle of the AC supply for a conduction period less than or equal to the half-cycle supply period to produce a desired switched output RMS voltage, the controlling means comprising: means to measure the AC supply voltage at a multiplicity of sampling items over a half-cycle period, said means including an analog-to-digital converter, the digital voltage values being stored in a memory; means to calculate from the measured voltages for each of a plurality of sampling times the RMS voltage which would be obtained by causing the switch to operate in accordance with that sampling time, said means being operable to calculate for each of the sampling times a value representing the sum of the squares of the voltage values for each of the sampling times from that sampling time to the end of the half-cycle, and to store the calculated values as a table in a memory with addresses corresponding to the sampling times; means to receive a signal indicative of the desired switched output RMS voltage; means to determine the sampling time for which the calculated RMS voltage corresponds to the desired RMS voltage; means for operating the switch in accordance with the determined time in a half-cycle period; a low pass filter for filtering the measured AC supply voltage to remove high frequency interference therefrom; means for forming in a memory an inverse of said table having values corresponding to the sampling times stored at addresses corresponding to RMS voltage values, the determining means being operable to address the inverse table memory according to the desired RMS voltage to determine the triggering times therefrom; means to transmit the table data to a further memory; and means for digitally filtering the data to produce a lesser number of data items for transmission, and means to re-construct the table of data in the further memory by interpolation.
Claim 11
Dependent Claim
339 words
A controller for an electric lighting load, comprising: a controllable switch for connecting an AC power supply to alighting load: and means for controlling the switch to conduct during a halfwave cycle of the AC supply for a conduction period less than or equal to the half-cycle supply period to produce a desired switched output RMS voltage, the controlling means comprising: means to measure the AC supply voltage at a multiplicity of sampling items over a half-cycle period, said means including an analog-to-digital converter, the digital voltage values being stored in a memory; means to calculate from the measured voltages for each of a plurality of sampling times the RMS voltage which would be obtained by causing the switch to operate in accordance with that sampling time, said means being operable to calculate for each of the sampling times a value representing the sum of the squares of the voltage values for each of the sampling times from that sampling time to the end of the half-cycle, and to store the calculated values as a table in a memory with addresses corresponding to the sampling times; means to receive a signal indicative of the desired switched output RMS voltage; means to determine the sampling time for which the calculated RMS voltage corresponds to the desired RMS voltage; means for operating the switch in accordance with the determined time in a half-cycle period; a low pass filter for filtering the measured AC supply voltage to remove high frequency interference therefrom; means for forming in a memory an inverse of said table having values corresponding to the sampling times stored at addresses corresponding to RMS voltage values, the determining means being operable to address the inverse table memory according to the desired RMS voltage to determine the triggering times therefrom; means to transmit the table data to a further memory; and means for digitally filtering the data to produce a lesser number of data items for transmission, and means to re-construct the table of data in the further memory by interpolation.
Claim 12
Dependent Claim
18 words
A controller as claimed in claim 8, further comprising means for differentially processing the data items for transmission.
References Cited (Backward Citations)
US4004214A
Cited
US4241295A
Cited
US4359670A
Cited
US4380730A
Cited
GB2115240A
Cited
DE3316761A1
Cited
GB2150323A
Cited
US4661765A
Cited
EP0237733A2
Cited
US4839566A
Cited
US4689548A
Cited
US4804916A
Cited
USPTO Annuity & Maintenance Windows
| Annuity Stage | Window Opens | Payment Deadline | Surcharge Period Until | Estimated Fee | Status |
|---|---|---|---|---|---|
| 3.5 Years (Year 4) | 1994-11-18 | 1995-05-20 | 1995-11-19 | $2000.00 | Window Closed / Lapsed |
| 7.5 Years (Year 8) | 1998-11-18 | 1999-05-20 | 1999-11-19 | $3760.00 | Window Closed / Lapsed |
| 11.5 Years (Year 12) | 2002-11-18 | 2003-05-20 | 2003-11-19 | $7700.00 | Window Closed / Lapsed |