US5050108A Expired / Lapsed US ⏱️ 0.0 years remaining

Method for extending the useful life of boiler tubes

Assignee: Aptech Engineering Services Inc
•
Filing: 1989-11-30
•
Granted: 1991-09-17
•
Expires: 2009-11-30
📄 Original PDF 🌐 Google Patents 🔄 Sync Now

Abstract

Abstract A method for increasing the reliability and remaining useful life of a system of boiler tubes. The present condition of boiler tubes is ascertained and a temperature profile is developed. Additional operating parameters are obtained and used to model the tube system. The model is manipulated to predict a modification which will cause increased tube system life and reliability. The tubes are modified according to the model.

Inventors

  • 👤 Kimble J. Clark
  • 👤 Kevin G. Hara
  • 👤 Clayton Q. Lee
  • 👤 Richard S. Moser
  • 👤 Terry W. Rettig

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-10-28 13:10
CPC Classifications
F; F22; F22B; F22B35/00; F22B35/18; Y; Y10; Y10S; Y10S122/00; Y10S122/13

Claims Analysis

Total Claims: 17
Claim 1
Independent Claim 63 words
A method of increasing the reliability and remaining useful life of a system of boiler tubes, comprising: (a) evaluating the current condition of the tubes; (b) obtaining the operating temperatures of the tubes; (c) determining the flow redistribution which would be required in the tubes in order to optimize operating temperature profile; and (d) modifying the tubes to achieve said required flow distribution.
Claim 2
Independent Claim 63 words
A method of increasing the reliability and remaining useful life of a system of boiler tubes, comprising: (a) evaluating the current condition of the tubes; (b) obtaining the operating temperatures of the tubes; (c) determining the flow redistribution which would be required in the tubes in order to optimize operating temperature profile; and (d) modifying the tubes to achieve said required flow distribution.
Claim 3
Dependent Claim 45 words
The method of claim 1, wherein the evaluating step comprises: (a) examining the tubes in order to obtain measurements of oxide scale thickness and wall thickness; (b) collecting design and operating data for the system; and (b) calculating the remaining useful life for said tubes.
Claim 4
Dependent Claim 18 words
The method of claim 2, wherein the evaluating step further comprises collecting a failure history of the system.
Claim 5
Dependent Claim 33 words
The method of claim 2, wherein the evaluating step further comprises making a visual inspection of the system to check for alignment and surface condition, including overheating damage, deposits, erosion, corrosion, and cracks.
Claim 6
Dependent Claim 31 words
The method of claim 1, wherein the evaluating step further comprises analyzing the economic benefit which can be derived by increasing the reliability and remaining useful life of said boiler tubes.
Claim 7
Dependent Claim 23 words
The method of claim 2, wherein said examining step comprises a non-destructive tube sampling technique, whereby certain of said measurements are obtained therefrom;
Claim 8
Dependent Claim 34 words
The method of claim 2, wherein said examining step comprises a destructive tube sampling technique, wherein a second plurality of boiler tubes are physically removed from the boiler and said measurements are taken therefrom.
Claim 9
Dependent Claim 49 words
The method of claim 2, wherein said examining step comprises: (a) a non-destructive tube sampling technique, whereby certain of said measurements are obtained therefrom; and (b) a destructive tube sampling technique, wherein a first plurality of tubes are physically removed from the boiler and said measurements are taken therefrom.
Claim 10
Independent Claim 32 words
The method of claims 6 or 8, wherein said non-destructive tube sampling technique comprises ultrasonic examination of a second plurality of boiler tubes, and whereby certain of said measurements are obtained therefrom.
Claim 11
Dependent Claim 80 words
The method of claim 2, wherein said calculating step comprises: (a) calculating a stress value as a function of current wall thickness, estimated original wall thickness, tube pressure, and tube outside diameter; (b) determining a current creep condition as a function of the stress value and internal oxide thickness; (c) determining a projected creep condition as a function of oxide growth and wall thinning rates; and (d) comparing the projected creep condition to failure conditions for the selected tube material.
Claim 12
Dependent Claim 34 words
The method of claim 1, wherein said obtaining step comprises connecting a plurality of thermocouples to various points in the tubes and taking temperature readings therefrom, and recording the temperatures for use in calculations.
Claim 13
Dependent Claim 19 words
The method of claim 1, wherein said obtaining step comprises inferring tube operating temperature from measured oxide scale thickness.
Claim 14
Dependent Claim 45 words
The method of claim 1, wherein said obtaining step comprises: connecting a plurality of thermocouples to various points in the tubes and taking temperature readings therefrom, and recording the temperatures for use in calculations; and (b) inferring tube operating temperature from measured oxide scale thickness.
Claim 15
Dependent Claim 97 words
The method of claim 1, wherein said determining step comprises: (a) calculating an initial tube metal temperature from enthalpy and heat flow relationships; (b) calculating tube metal temperature, scale temperature, stress, scale thickness, and creep damage for incremental increases in time; (c) incrementing the parameters of step (b) until failure is predicted; (d) calculating changes in future tube temperatures necessary to obtain a specified failure time; (e) projecting steam temperature at the tube outlet based on said failure time; and (f) select optimal tube temperature profile based on steam temperature to obtain a minimum increase in pressure.
Claim 16
Dependent Claim 15 words
The method of claim 1, wherein said tubes. modifying step includes replacing certain of said
Claim 17
Dependent Claim 18 words
The method of claim 1, wherein said modifying step includes inserting a controller within certain of said tubes.

References Cited (Backward Citations)

US4231419A Cited
US4505232A Cited
US4792912A Cited
US4628870A Cited
US4713870A Cited
US4685334A Cited
US4669310A Cited
US4716767A Cited
US4908775A Cited
US4941512A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1994-09-16 1995-03-18 1995-09-17 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1998-09-16 1999-03-18 1999-09-17 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 2002-09-16 2003-03-18 2003-09-17 $7700.00 Window Closed / Lapsed