Abstract

Abstract A method and an arrangement for manufacturing hot-rolled steel strip from continuously cast initial materials in continuously successive work steps, wherein the continuously cast initial material is cut after solidifying to a certain length, is heated in a soaking furnace to rolling temperature and is introduced into a finishing rolling mill train for rolling out. The continuously cast initial material is introduced after being heated to a multiple-stand, reversible finishing rolling mill train and a coilbox connected downstream to the finishing rolling mill train.

Inventors

  • 👤 Jurgen Seidel
  • 👤 Wolfgang Rohde

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-11-06 04:09
CPC Classifications
B; B21; B21B; B21B1/00; B21B1/22; B21B1/24; B21B1/26; B21B1/30; B21B1/32; B21B1/34; B21B1/46; B21B1/466; B21B35/00; B21B35/12; B21B45/00; B21B45/02; B21B45/0203; B21B45/0209; B21B45/0215; B21B45/0218; B21B45/04; B21B45/06; Y; Y10; Y10T; Y10T29/00; Y10T29/49; Y10T29/4998; Y10T29/49988; Y10T29/49989; Y10T29/49991; Y10T29/51; Y10T29/5184; Y10T29/5197; Y10T29/5198

Claims Analysis

Total Claims: 11
Claim 1
Independent Claim 184 words
In a method for manufacturing hot-rolled steel strip from continuously cast initial material having a thickness of more than 50 mm in continuously successive work steps, including cutting the continuously cast initial material after solidifying into billets having a certain length, heating the billets in a soaking furnace to rolling temperature and introducing the billets to a finishing rolling mill train for rolling the billets into the desired size, wherein the improvement comprises introducing each billet after being heated into a finishing rolling mill train having a plurality of reversible rolling mill stands arranged one behind the other, rolling each billet in the finishing rolling mill train in a forward movement with a direct sequence of several rolling passes with relatively high moment and low rolling speed and in a reversing movement with a direct sequence of several rolling passes with relatively low moment and high rolling speed, and adjusting a ratio of rate of rotation between drive motors and work rolls of the rolling mill stands between the forward movement and the reversing movement by changing gear transmission of the rolling mill stands.
Claim 2
Dependent Claim 184 words
In a method for manufacturing hot-rolled steel strip from continuously cast initial material having a thickness of more than 50 mm in continuously successive work steps, including cutting the continuously cast initial material after solidifying into billets having a certain length, heating the billets in a soaking furnace to rolling temperature and introducing the billets to a finishing rolling mill train for rolling the billets into the desired size, wherein the improvement comprises introducing each billet after being heated into a finishing rolling mill train having a plurality of reversible rolling mill stands arranged one behind the other, rolling each billet in the finishing rolling mill train in a forward movement with a direct sequence of several rolling passes with relatively high moment and low rolling speed and in a reversing movement with a direct sequence of several rolling passes with relatively low moment and high rolling speed, and adjusting a ratio of rate of rotation between drive motors and work rolls of the rolling mill stands between the forward movement and the reversing movement by changing gear transmission of the rolling mill stands.
Claim 3
Dependent Claim 18 words
The method according to claim 1, wherein the initial material has a thickness of more than 65 mm.
Claim 4
Dependent Claim 39 words
The method according to claim 1, comprising descaling the roller material by means of a descaling unit arranged within the finishing rolling mill train, descaling being performed between successive rolling passes during the forward movement and/or the reversing movement.
Claim 5
Dependent Claim 174 words
In an arrangement for manufacturing hot-rolled steel strip from continuously cast initial material having a thickness of more than 50 mm in continuously successive work steps, including means for cutting the continuously cast initial material after solidifying into billets having a certain length, a soaking furnace for heating the billets to rolling temperature, and means for introducing the billets into a finishing rolling mill train for rolling the billets into the desired size, the improvement comprising a casting plant for producing at least one billet, a soaking furnace arranged downstream of the casting plant, a cutting machine arranged between the casting plant and the soaking furnace, a finishing rolling mill train arranged downstream of the soaking furnace, the finishing rolling mill train including a plurality of rolling mill stands arranged one behind the other, a coil box arranged downstream of the finishing rolling mill train wherein at least one of the finishing rolling mill stands is a principal load-applying stand, the at least one principal load-applying stand being connected to a change-over gear unit.
Claim 6
Dependent Claim 174 words
In an arrangement for manufacturing hot-rolled steel strip from continuously cast initial material having a thickness of more than 50 mm in continuously successive work steps, including means for cutting the continuously cast initial material after solidifying into billets having a certain length, a soaking furnace for heating the billets to rolling temperature, and means for introducing the billets into a finishing rolling mill train for rolling the billets into the desired size, the improvement comprising a casting plant for producing at least one billet, a soaking furnace arranged downstream of the casting plant, a cutting machine arranged between the casting plant and the soaking furnace, a finishing rolling mill train arranged downstream of the soaking furnace, the finishing rolling mill train including a plurality of rolling mill stands arranged one behind the other, a coil box arranged downstream of the finishing rolling mill train wherein at least one of the finishing rolling mill stands is a principal load-applying stand, the at least one principal load-applying stand being connected to a change-over gear unit.
Claim 7
Dependent Claim 15 words
The arrangement according to claim 4, wherein the finishing rolling mill train comprises three stands.
Claim 8
Dependent Claim 15 words
The arrangement according to claim 4, wherein the finishing rolling mill train comprises four stands.
Claim 9
Dependent Claim 18 words
The arrangement according to claim 4, wherein the initial material has a thickness of more than 65 mm.
Claim 10
Dependent Claim 16 words
The arrangement according to claim 4, comprising the descaling unit arranged between the rolling mill stands.
Claim 11
Dependent Claim 21 words
The arrangement according to claim 4, comprising a descaling unit arranged between the last rolling mill stand and the coil box.

References Cited (Backward Citations)

US3777533A Cited
JPS58100903A Cited
US4503697A Cited
US4658363A Cited
US4688897A Cited
JPS6238704A Cited
US4675974A Cited
US4782683A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1994-03-11 1994-09-10 1995-03-12 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1998-03-11 1998-09-10 1999-03-12 $3760.00 Window Closed / Lapsed