Automatic machining scheduling method based on an expert system

Assignee: Fanuc Corp
•
Filing: 1988-09-02
•
Granted: 1991-02-19
•
Expires: 2008-09-02
📄 Original PDF 🌐 Google Patents 🔄 Sync Now

Abstract

Abstract An automatic machining scheduling method based on an expert system is provided, which can optimize and facilitate the assignment of processes in a large-scale production system to individual machine tools, based on expert experience accumulated as a database, thereby enabling effective operation of the production system. When requested quantities for respective machine models to be produced are input (S1), the machining time of each jig involved in a respective machine model and the usage form of each jig are read from the related files, and the former is multiplied by the latter, to obtain the total machining time for each of the machine tools (S2, S3). A day or week production matrix is created based on the ratio of the calculated time of each of the machine tools to the operating time thereof per day (S4-S7). It is determined whether a machining schedule including a pattern identical to the machining pattern of the matrix is registered (S10, S11). If the machining schedule is registered in the file, the registered schedule is used (S12-S15).

Inventors

  • 👤 Bong J. Lee
  • 👤 Ryoji Yokomori

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-10-28 07:15
CPC Classifications
B; B23; B23Q; B23Q41/00; B23Q41/08; G; G05; G05B; G05B19/00; G05B19/02; G05B19/418; G05B19/41865; G05B2219/00; G05B2219/30; G05B2219/32; G05B2219/32252; G05B2219/32288; G05B2219/32397; Y; Y02; Y02P; Y02P90/00; Y02P90/02; Y10; Y10S; Y10S706/00; Y10S706/902; Y10S706/903; Y10S706/904

Claims Analysis

Total Claims: 7
Claim 1
Independent Claim 181 words
An automatic machining scheduling method based on an expert system, comprising the steps of: (a) obtaining a total machining time required for each of a plurality of machine tools to machine various component parts of machines to be produced, based on requested quantities of respective machine models; (b) comparing the required total machining time of each of the machine tools, obtained in said step (a), with a predetermined operating time for the corresponding machine tool per a first predetermined period, and determining whether the first predetermined period or a second predetermined period longer than the first predetermined period should be used as a unit time for creating a machining schedule; (c) creating a production matrix in accordance with the unit time determined in said step (b) and based on the requested quantities of respective machine models; (d) retrieving a machining pattern coinciding with the production matrix created in said step (c), from among various machining patterns registered previously; and (e) retrieving a machining schedule corresponding to the machining pattern retrieved in said step (d), from among various machining schedules registered previously.
Claim 2
Dependent Claim 181 words
An automatic machining scheduling method based on an expert system, comprising the steps of: (a) obtaining a total machining time required for each of a plurality of machine tools to machine various component parts of machines to be produced, based on requested quantities of respective machine models; (b) comparing the required total machining time of each of the machine tools, obtained in said step (a), with a predetermined operating time for the corresponding machine tool per a first predetermined period, and determining whether the first predetermined period or a second predetermined period longer than the first predetermined period should be used as a unit time for creating a machining schedule; (c) creating a production matrix in accordance with the unit time determined in said step (b) and based on the requested quantities of respective machine models; (d) retrieving a machining pattern coinciding with the production matrix created in said step (c), from among various machining patterns registered previously; and (e) retrieving a machining schedule corresponding to the machining pattern retrieved in said step (d), from among various machining schedules registered previously.
Claim 3
Dependent Claim 25 words
An automatic machining scheduling method according to claim 1, wherein the first and second predetermined periods are set respectively to one day and one week.
Claim 4
Dependent Claim 89 words
An automatic machining scheduling method according to claim 1, wherein usages of various jigs for respective machine tools used for executing patterns representing quantities of respective machine models to be produced are previously registered in relation to the respective patterns, a machining time for each of the jigs used for producing respective machine models is registered previously and wherein said step (a) comprises obtaining the required total machining time for the respective machine tool based on the usage forms of the various jigs and the machining times registered previously.
Claim 5
Dependent Claim 89 words
An automatic machining scheduling method according to claim 2, wherein usages of various jigs for respective machine tools used for executing patterns representing quantities of respective machine models to be produced are previously registered in relation to the respective patterns, a machining time for each of the jigs used for producing respective machine models is registered previously and wherein said step (a) comprises obtaining the required total machining time for the respective machine tool based on the usage forms of the various jigs and the machining times registered previously.
Claim 6
Dependent Claim 172 words
An automatic machining scheduling method, comprising the steps of: (a) registering a plurality of machining patterns; (b) registering a plurality of machining schedules corresponding to the machining patterns; (c) determining a total machining time required for each of a plurality of machine tools to manufacture a requested quantity of machines having respective machine models; (d) comparing the total machining time of each of the machine tools determined in said step (c) with a predetermined operating time for the corresponding machine tool to determine whether a first predetermined period or second predetermined period which is longer than the first predetermined period, should be used as a unit time for creating a machining schedule; (e) creating a production matrix based on the requested quantities of respective machine models and the unit time determined in said step (d); (f) retrieving one of the registered machining patterns corresponding to the production matrix created in said step (e); and (g) retrieving one of the registered machining schedules corresponding to the machining pattern retrieved in said step (f).
Claim 7
Dependent Claim 172 words
An automatic machining scheduling method, comprising the steps of: (a) registering a plurality of machining patterns; (b) registering a plurality of machining schedules corresponding to the machining patterns; (c) determining a total machining time required for each of a plurality of machine tools to manufacture a requested quantity of machines having respective machine models; (d) comparing the total machining time of each of the machine tools determined in said step (c) with a predetermined operating time for the corresponding machine tool to determine whether a first predetermined period or second predetermined period which is longer than the first predetermined period, should be used as a unit time for creating a machining schedule; (e) creating a production matrix based on the requested quantities of respective machine models and the unit time determined in said step (d); (f) retrieving one of the registered machining patterns corresponding to the production matrix created in said step (e); and (g) retrieving one of the registered machining schedules corresponding to the machining pattern retrieved in said step (f).

References Cited (Backward Citations)

US4473883A Cited
US4472783A Cited
US4583280A Cited
US4661912A Cited
US4896269A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1994-02-18 1994-08-20 1995-02-19 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1998-02-18 1998-08-20 1999-02-19 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 2002-02-18 2002-08-20 2003-02-19 $7700.00 Window Closed / Lapsed

Assigned Categories & Tags

No categories assigned to this patent yet.

Assign Category Tag