Method of optimizing a vehicle assembly line build sequence

Assignee: GM Global Technology Operations LLC
•
Filing: 1989-11-08
•
Granted: 1990-06-05
•
Expires: 2009-11-08
📄 Original PDF 🌐 Google Patents 🔄 Sync Now

Abstract

Abstract A method of scheduling the building sequence of a plurality of objects on an assembly line in order to minimze the cost of building the objects is disclosed. Each object has a plurality of attributes, which together with the position of the object in the sequence, affects the overall cost of the build sequence. A computer is provided with a representation of the object, its attributes, and a procedure for calculating the cost associated with any arrangement of the attributes. An initial build sequence is generated using the representation which has a minimal cost associated with the arrangement of at least one of the attributes. A final build sequence is generated in accordance with a simulated annealing algorithm which utilizes a scoring function that includes the costs defined by the procedure, those costs associated with the attributes being independently weighted in accordance with a temperature varying function. A representation of the final build sequence usable for construction of the object is then provided.

Inventors

  • 👤 Roy Richter
  • 👤 Jackson G. Gay
  • 👤 Robert P. Kromer

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-10-26 09:21
CPC Classifications
G; G06; G06Q; G06Q10/00; G06Q10/06; G05; G05B; G05B19/00; G05B19/02; G05B19/418; G05B19/41805; G06F; G06F30/00; G06F30/10; G06F30/15; G06F30/18; Y; Y02; Y02P; Y02P90/00; Y02P90/02

Claims Analysis

Total Claims: 10
Claim 1
Independent Claim 173 words
A method of scheduling the build sequence of a plurality of objects on an assembly line in order to minimize the cost of building the objects, each object having a plurality of attributes, which together with the position of the object in the sequence, affect the overall cost of the build sequence: comprising the steps of; (a) providing a computer with a representation of the object, its attributes, and a procedure for calculating the cost associated with any arrangement of the attributes, (b) generating an initial build sequence using the representation of step (a) which has a miminal cost associated with the arrangement of at least one of said attributes, (c) generating a final build sequence in accordance with a simulated annealing algorithm which utilizes a scoring function that includes the costs defined by the procedure of step (a), those costs associated with the attributes of step (b) being independently weighted in accordance with a temperature varying function, (d) providing a representation of the final build sequence usable for construction of the objects.
Claim 2
Independent Claim 173 words
A method of scheduling the build sequence of a plurality of objects on an assembly line in order to minimize the cost of building the objects, each object having a plurality of attributes, which together with the position of the object in the sequence, affect the overall cost of the build sequence: comprising the steps of; (a) providing a computer with a representation of the object, its attributes, and a procedure for calculating the cost associated with any arrangement of the attributes, (b) generating an initial build sequence using the representation of step (a) which has a miminal cost associated with the arrangement of at least one of said attributes, (c) generating a final build sequence in accordance with a simulated annealing algorithm which utilizes a scoring function that includes the costs defined by the procedure of step (a), those costs associated with the attributes of step (b) being independently weighted in accordance with a temperature varying function, (d) providing a representation of the final build sequence usable for construction of the objects.
Claim 3
Independent Claim 173 words
A method of scheduling the build sequence of a plurality of vehicles on an assembly line in order to minimize the cost of building the vehicles, each vehicle having a plurality of attributes, which together with the position of the vehicle in the sequence, affect the overall cost of the build sequence: comprising the steps of; (a) providing a computer with a representation of the vehicle, its attributes, and a procedure for calculating the cost associated with any arrangement of the attributes, (b) generating an initial build sequence using the representation of step (a) which has a miminal cost associated with the arrangement of at least one of said attributes, (c) generating a final build sequence in accordance with a simulated annealing algorithm which utilizes a scoring function that includes the costs defined by the procedure of step (a), those costs associated with the attributes of step (b) being independently weighted in accordance with a temperature varying function, (d) providing a representation of the final build sequence usable for construction of the vehicles.
Claim 4
Independent Claim 173 words
A method of scheduling the build sequence of a plurality of vehicles on an assembly line in order to minimize the cost of building the vehicles, each vehicle having a plurality of attributes, which together with the position of the vehicle in the sequence, affect the overall cost of the build sequence: comprising the steps of; (a) providing a computer with a representation of the vehicle, its attributes, and a procedure for calculating the cost associated with any arrangement of the attributes, (b) generating an initial build sequence using the representation of step (a) which has a miminal cost associated with the arrangement of at least one of said attributes, (c) generating a final build sequence in accordance with a simulated annealing algorithm which utilizes a scoring function that includes the costs defined by the procedure of step (a), those costs associated with the attributes of step (b) being independently weighted in accordance with a temperature varying function, (d) providing a representation of the final build sequence usable for construction of the vehicles.
Claim 5
Independent Claim 171 words
A method of scheduling the build sequence of a plurality of vehicles on an assembly line in order to minimize the cost of building the vehicles, each vehicle having a plurality of attributes, one of which is color, which together with the position of the vehicle in the sequence, affect the overall cost of the build sequence: comprising the steps of; (a) providing a computer with a representation of the vehicle, its attributes, and a procedure for calculating the cost associated with any arrangement of the attributes, (b) generating an initial build sequence using the representation of step (a) which has a miminal cost associated with placing the color attribute, (c) generating a final build sequence in accordance with a simulated annealing algorithm which utilizes a scoring function that includes the costs defined by the procedure of step (a), those costs associated with the attribute color being independently weighted in accordance with a temperature varying function, (d) providing a representation of the final build sequence usable for construction of the vehicles.
Claim 6
Independent Claim 171 words
A method of scheduling the build sequence of a plurality of vehicles on an assembly line in order to minimize the cost of building the vehicles, each vehicle having a plurality of attributes, one of which is color, which together with the position of the vehicle in the sequence, affect the overall cost of the build sequence: comprising the steps of; (a) providing a computer with a representation of the vehicle, its attributes, and a procedure for calculating the cost associated with any arrangement of the attributes, (b) generating an initial build sequence using the representation of step (a) which has a miminal cost associated with placing the color attribute, (c) generating a final build sequence in accordance with a simulated annealing algorithm which utilizes a scoring function that includes the costs defined by the procedure of step (a), those costs associated with the attribute color being independently weighted in accordance with a temperature varying function, (d) providing a representation of the final build sequence usable for construction of the vehicles.
Claim 7
Independent Claim 170 words
A method of scheduling the build sequence of a plurality of objects in order to minimize the cost of building the objects, each object having a plurality of attributes, which together with the position of the object in the sequence, affect the overall cost of the build sequence: comprising the steps of; (a) providing a computer with a representation of the object including its attributes, and a procedure for calculating the cost associated with any arrangement of the attributes, (b) generating an initial build sequence using the representation of step (a) which has a minimal cost associated with the arrangement of at least one of said attributes, (c) generating a final build sequence in accordance with a simulated annealing algorithm which utilizes a scoring function that includes the costs defined by the procedure of step (a), those costs associated with the attributes of step (b) being independently weighted in accordance with a temperature varying function, (d) providing a representation of the final build sequence usable for construction of the objects.
Claim 8
Independent Claim 170 words
A method of scheduling the build sequence of a plurality of objects in order to minimize the cost of building the objects, each object having a plurality of attributes, which together with the position of the object in the sequence, affect the overall cost of the build sequence: comprising the steps of; (a) providing a computer with a representation of the object including its attributes, and a procedure for calculating the cost associated with any arrangement of the attributes, (b) generating an initial build sequence using the representation of step (a) which has a minimal cost associated with the arrangement of at least one of said attributes, (c) generating a final build sequence in accordance with a simulated annealing algorithm which utilizes a scoring function that includes the costs defined by the procedure of step (a), those costs associated with the attributes of step (b) being independently weighted in accordance with a temperature varying function, (d) providing a representation of the final build sequence usable for construction of the objects.
Claim 9
Independent Claim 174 words
A method of scheduling the build route of a plurality of components in an assembly plant in order to minimize the cost of building the components, each component having a plurality of attributes, which together with the position of the component in the route, affect the overall cost of the build route: comprising the steps of; (a) providing a computer with a representation of the component including its attributes, and a procedure for calculating the cost associated with any arrangement of the attributes, (b) generating an initial build route using the representation of step (a) which has a minimal cost associated with the arrangement of at least one of said attributes, (c) generating a final build route in accordance with a simulated annealing algorithm which utilizes a scoring function that includes the costs defined by the procedure of step (a), those costs associated with the attributes of step (b) being independently weighted in accordance with a temperature varying function, (d) providing a representation of the final build route usable for construction of the components.
Claim 10
Independent Claim 174 words
A method of scheduling the build route of a plurality of components in an assembly plant in order to minimize the cost of building the components, each component having a plurality of attributes, which together with the position of the component in the route, affect the overall cost of the build route: comprising the steps of; (a) providing a computer with a representation of the component including its attributes, and a procedure for calculating the cost associated with any arrangement of the attributes, (b) generating an initial build route using the representation of step (a) which has a minimal cost associated with the arrangement of at least one of said attributes, (c) generating a final build route in accordance with a simulated annealing algorithm which utilizes a scoring function that includes the costs defined by the procedure of step (a), those costs associated with the attributes of step (b) being independently weighted in accordance with a temperature varying function, (d) providing a representation of the final build route usable for construction of the components.

References Cited (Backward Citations)

US4495559A Cited
US4593360A Cited
US4745549A Cited
US4688178A Cited
US4745555A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1993-06-04 1993-12-04 1994-06-05 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1997-06-04 1997-12-04 1998-06-05 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 2001-06-04 2001-12-04 2002-06-05 $7700.00 Window Closed / Lapsed

Assigned Categories & Tags

No categories assigned to this patent yet.

Assign Category Tag