US4850310A
Expired / Lapsed
US
⏱️ 0.0 years remaining
Boiler control having reduced number of boiler sequences for a given load
Assignee: Johnson Group
•
Filing: 1988-04-14
•
Granted: 1989-07-25
•
Expires: 2008-04-14
Abstract
Abstract To reduce the number of boiler sequences over time executed for a given heating load without adversely affecting boiler efficiency, the call signal applied to the boiler to initiate a sequence in response to a demand for heating is delayed as a function of outside temperature and time elapsed since the end of the previous sequence. Accumulated burn time and sequence count are displayed to monitor boiler performance.
Inventors
- 👤 Harry Wildgen
Bibliographic Details
Application Number
—
Jurisdiction
US
Data Source
google_patents
Last Synchronized
2026-11-05 22:16
CPC Classifications
F; F23; F23N; F23N5/00; F23N5/20; F23N5/203; F23N1/00; F23N1/002; G; G05; G05D; G05D23/00; G05D23/19; G05D23/1906; G05D23/1912; F23N2223/00; F23N2223/22; F23N2225/00; F23N2225/08; F23N2225/14; F23N2227/00; F23N2227/04; F23N2227/10
Claims Analysis
Total Claims: 16
Claim 1
Independent Claim
109 words
In a boiler controlled to operate in a boiler sequence characterized by pre-purge, ignition, firing and post purge sequence steps, the sequence being initiated by a call signal representative of a demand for heating, an improved control for reducing the number of boiler sequences executed by the boiler over time, comprising: first means for measuring ambient temperature and generating a first output corresponding thereto; second means for determining a time elapsed since the end of the previous boiler sequence and generating a second output corresponding thereto; and third means, responsive to said first and second outputs of said first and second means respectively, for controllably delaying said call signal.
Claim 2
Dependent Claim
109 words
In a boiler controlled to operate in a boiler sequence characterized by pre-purge, ignition, firing and post purge sequence steps, the sequence being initiated by a call signal representative of a demand for heating, an improved control for reducing the number of boiler sequences executed by the boiler over time, comprising: first means for measuring ambient temperature and generating a first output corresponding thereto; second means for determining a time elapsed since the end of the previous boiler sequence and generating a second output corresponding thereto; and third means, responsive to said first and second outputs of said first and second means respectively, for controllably delaying said call signal.
Claim 3
Dependent Claim
32 words
The improved boiler control of claim 1, wherein: said means for controllably delaying a portion of the next boiler sequence comprises means for delaying an ignition portion of said next boiler sequence.
Claim 4
Dependent Claim
27 words
The improved boiler control of claim 1, wherein: said means for measuring the ambient temperature and elapsed time comprises means for generating a corresponding digital output signal.
Claim 5
Dependent Claim
37 words
The improved boiler control of claim 1, wherein: said means for measuring the ambient temperature and elapsed time comprises a real time clock and means for generating a digital output signal responsive to real time determined thereby.
Claim 6
Dependent Claim
27 words
The improved boiler control of claim 1, wherein: said third means comprises fourth means for delaying said ignition step in the next one of said boiler sequences.
Claim 7
Dependent Claim
28 words
The improved boiler control of claim 1, wherein: said fourth means comprises means for storing data corresponding to at least one of said first, second and third outputs.
Claim 8
Dependent Claim
15 words
The improved boiler control of claim 6, further comprising: microprocessor means for processing said data.
Claim 9
Dependent Claim
97 words
In a boiler controlled to execute a boiler sequence comprising successive pre-purge, ignition, firing and post purge steps initiated by a call signal in response to a demand for heating, a method of reducing the number of boiler sequences executed by the boiler over time, comprising the steps of: measuring ambient temperature to obtain a first signal; determining a time elapsed since the end of the previous boiler sequence to obtain a second signal; combining the first and second signals to obtain a third signal; and controllably delaying the call signal in accordance with the third signal.
Claim 10
Dependent Claim
97 words
In a boiler controlled to execute a boiler sequence comprising successive pre-purge, ignition, firing and post purge steps initiated by a call signal in response to a demand for heating, a method of reducing the number of boiler sequences executed by the boiler over time, comprising the steps of: measuring ambient temperature to obtain a first signal; determining a time elapsed since the end of the previous boiler sequence to obtain a second signal; combining the first and second signals to obtain a third signal; and controllably delaying the call signal in accordance with the third signal.
Claim 11
Dependent Claim
25 words
The method of claim 8, including the steps of accumulating an aggregate firing time during a predetermined time interval and displaying said aggregate firing time.
Claim 12
Dependent Claim
28 words
The method of claim 8, including the step of counting the number of boiler sequences executed by said boiler during a predetermined time interval and displaying said number.
Claim 13
Dependent Claim
24 words
The method of claim 8, further comprising the step of: storing data representative of at least one of said first, second and third signals.
Claim 14
Dependent Claim
104 words
The method of claim 8, wherein: the step of controllably delaying said call signal comprises the step of computing a time delay according to a relationship D=(PCH).(T).(%/°F.) where D is said time delay, PCH is "percentage off time", the measured length of hold off time since the end of the previous boiler cycle, T is the outside ambient temperature in °F., and (%/°F.) is a programmed parameter representing the percentage of hold off time per degree Fahrenheit of the outside ambient temperature that is determined empirically during execution of boiler sequences and is related to the size and type of load on the boiler.
Claim 15
Dependent Claim
181 words
In a boiler controlled to execute a boiler sequence initiated by a call signal in response to a demand for heating, a method of reducing the number of boiler sequences executed by the boiler over time, comprising the steps of: measuring an ambient temperature; determining a time elapsed since the end of the previous boiler sequence; and controllably delaying the initation of the current boiler sequence in accordance with the measured ambient temperature and time elapsed, wherein: the step of controllably delaying initiation of the next one of said boiler sequences comprises the step of computing a time delay according to a relationship D=(PCH).(T).(%/°F.) where D is said time delay, PCH is "percentage off time", the measured length of hold off time since the end of the previous boiler cycle, T is outside ambient temperature in °F., and (%/°F.) is a programmed parameter representing the percentage of hold off time per degree Fahrenheit of the outside ambient temperature that is determined empirically during the execution of boiler sequences and is related to the size and type of load on the boiler.
Claim 16
Dependent Claim
181 words
In a boiler controlled to execute a boiler sequence initiated by a call signal in response to a demand for heating, a method of reducing the number of boiler sequences executed by the boiler over time, comprising the steps of: measuring an ambient temperature; determining a time elapsed since the end of the previous boiler sequence; and controllably delaying the initation of the current boiler sequence in accordance with the measured ambient temperature and time elapsed, wherein: the step of controllably delaying initiation of the next one of said boiler sequences comprises the step of computing a time delay according to a relationship D=(PCH).(T).(%/°F.) where D is said time delay, PCH is "percentage off time", the measured length of hold off time since the end of the previous boiler cycle, T is outside ambient temperature in °F., and (%/°F.) is a programmed parameter representing the percentage of hold off time per degree Fahrenheit of the outside ambient temperature that is determined empirically during the execution of boiler sequences and is related to the size and type of load on the boiler.
References Cited (Backward Citations)
US2477728A
Cited
US3979059A
Cited
US4292813A
Cited
US4637349A
Cited
US4502625A
Cited
GB2151815A
Cited
US4634046A
Cited
USPTO Annuity & Maintenance Windows
| Annuity Stage | Window Opens | Payment Deadline | Surcharge Period Until | Estimated Fee | Status |
|---|---|---|---|---|---|
| 3.5 Years (Year 4) | 1992-07-24 | 1993-01-23 | 1993-07-25 | $2000.00 | Window Closed / Lapsed |
| 7.5 Years (Year 8) | 1996-07-24 | 1997-01-23 | 1997-07-25 | $3760.00 | Window Closed / Lapsed |
| 11.5 Years (Year 12) | 2000-07-24 | 2001-01-23 | 2001-07-25 | $7700.00 | Window Closed / Lapsed |