Abstract

Abstract A DC power controller for controlling the rate at which direct current is furnished to a load. A signal generator provides a periodic signal having a first value during a first portion of each period and a second value during a second portion of the period. A switch such as a power MOSFET enables direct current from the source to flow through the load during the time the signal has one of said values and prevents the current from flowing during the time the signal has the other value. A control is manually operable to vary the relative durations of the first and second portions of each period and thereby control the rate at which electric power is furnished to the load. A plurality of MOSFETS may be arranged in parallel if the load draws more current than one MOSFET can safely switch. Surge and back EMF protection are provided for inductive or variable resistance loads.

Inventors

  • 👤 Gary L. Bowles

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-11-03 22:07
CPC Classifications
H; H02; H02M; H02M3/00; H02M3/02; H02M3/04; H02M3/10; H02M3/145; H02M3/155; H03; H03K; H03K17/00; H03K17/12; H03K17/122; H03K17/51; H03K17/56; H03K17/687; H03K17/6877; Y; Y10; Y10S; Y10S388/00; Y10S388/907; Y10S388/915

Claims Analysis

Total Claims: 13
Claim 1
Independent Claim 189 words
Apparatus for controlling the rate at which electric power is furnished to a load from a source of direct current, the apparatus comprising: a signal generator operative to provide a periodic signal having a first value during a first portion of each period and a second value during a second portion of the period, the signal generator comprising a timing capacitor and circuit means operative to alternately charge the capacitor at a first rate and discharge the capacitor at a second rate, the duration of the first portion of each period being determined by the first and the duration of the second portion of each period being determined by the second rate, switch means responsive to the signal to enable direct current from the source to flow through the load during the time the signal has one of said values and to prevent the current from flowing during the time the signal has the other value; and control means manually operable to vary the relative durations of the first and second portions of each period and thereby control the rate at which electric power is furnished to the load.
Claim 2
Dependent Claim 189 words
Apparatus for controlling the rate at which electric power is furnished to a load from a source of direct current, the apparatus comprising: a signal generator operative to provide a periodic signal having a first value during a first portion of each period and a second value during a second portion of the period, the signal generator comprising a timing capacitor and circuit means operative to alternately charge the capacitor at a first rate and discharge the capacitor at a second rate, the duration of the first portion of each period being determined by the first and the duration of the second portion of each period being determined by the second rate, switch means responsive to the signal to enable direct current from the source to flow through the load during the time the signal has one of said values and to prevent the current from flowing during the time the signal has the other value; and control means manually operable to vary the relative durations of the first and second portions of each period and thereby control the rate at which electric power is furnished to the load.
Claim 3
Dependent Claim 56 words
Apparatus according to claim 1 wherein the control means comprises a potentiometer and the circuit means comprises a first diode operative to establish a charging circuit for the capacitor through a first portion of the potentiometer and a second diode operative to establish a discharging circuit for the capacitor through a second portion of the potentiometer.
Claim 4
Dependent Claim 19 words
Apparatus according to claim 1 wherein the switch means comprises a plurality of switch elements in a parallel configuration.
Claim 5
Dependent Claim 12 words
Apparatus according to claim 3 wherein the switch elements comprise power MOSFETs.
Claim 6
Dependent Claim 18 words
Apparatus according to claim 4 and further comprising current surge limiting means in parallel relationship with the MOSFETs.
Claim 7
Dependent Claim 22 words
Apparatus according to claim 1 and further comprising means to protect the switch means from any back EMF developed across the load.
Claim 8
Dependent Claim 19 words
Apparatus according to claim 1 wherein the duration of the period is not significantly affected by the control means.
Claim 9
Dependent Claim 273 words
Apparatus for controlling the rate at which electric power is furnished to a load from a source of direct current, the apparatus comprising: a signal generator operative to provide a periodic signal having a first value during a first portion of each period and a second value during a second portion of the period, the signal generator including a timing capacitor, a potentiometer, and circuit means including a first diode operative to establish a charging circuit for the capacitor through a first portion of the potentiometer and a second diode operative to establish a discharging circuit for the capacitor through a second portion of the potentiometer, the circuit means being operative to alternately charge the capacitor at a first rate and discharge the capacitor at a second rate, the duration of the first portion of each period being determined by the first rate and the duration of the second portion of each period being determined by the second rate; an amplifier including an NPN transistor and a PNP transistor in a push-pull configuration, operative to receive the signal from the signal generator and amplify the signal; and switch means including current surge limiting means, responsive to the amplified signal to enable direct current from the source to flow through the load during the time the signal has one of its values and to prevent the current from flowing during the time the signal has the other of its values; the potentiometer being manually operable to vary the relative durations of the first and second portions of each period and thereby to control the rate at which electric power is furnished to the load.
Claim 10
Dependent Claim 273 words
Apparatus for controlling the rate at which electric power is furnished to a load from a source of direct current, the apparatus comprising: a signal generator operative to provide a periodic signal having a first value during a first portion of each period and a second value during a second portion of the period, the signal generator including a timing capacitor, a potentiometer, and circuit means including a first diode operative to establish a charging circuit for the capacitor through a first portion of the potentiometer and a second diode operative to establish a discharging circuit for the capacitor through a second portion of the potentiometer, the circuit means being operative to alternately charge the capacitor at a first rate and discharge the capacitor at a second rate, the duration of the first portion of each period being determined by the first rate and the duration of the second portion of each period being determined by the second rate; an amplifier including an NPN transistor and a PNP transistor in a push-pull configuration, operative to receive the signal from the signal generator and amplify the signal; and switch means including current surge limiting means, responsive to the amplified signal to enable direct current from the source to flow through the load during the time the signal has one of its values and to prevent the current from flowing during the time the signal has the other of its values; the potentiometer being manually operable to vary the relative durations of the first and second portions of each period and thereby to control the rate at which electric power is furnished to the load.
Claim 11
Dependent Claim 19 words
Apparatus according to claim 8 wherein the switch means comprises a plurality of power MOSFETs in a parallel configuration.
Claim 12
Dependent Claim 22 words
Apparatus according to claim 8 and further comprising means to protect the switch means from any back EMF developed across the load.
Claim 13
Dependent Claim 18 words
Apparatus according to claim 8 wherein the duration of the period is not significantly affected by the potentiometer.

References Cited (Backward Citations)

US3875486A Cited
US4155069A Cited
US4217526A Cited
US4441068A Cited
US4599555A Cited
US4673851A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1992-06-19 1992-12-19 1993-06-20 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1996-06-19 1996-12-19 1997-06-20 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 2000-06-19 2000-12-19 2001-06-20 $7700.00 Window Closed / Lapsed