Integrated coal gasification plant and combined cycle system with air bleed and steam injection

Assignee: General Electric Co
•
Filing: 1986-04-21
•
Granted: 1988-11-22
•
Expires: 2006-04-21
📄 Original PDF 🌐 Google Patents 🔄 Sync Now

Abstract

Abstract An integrated coal gasification plant and combined cycle system employs a supply of compressed air bled off at an intermediate pressure from an air compressor portion of a gas turbine to supply the compressed-air needs of an oxygen plant associated with the coal gasification plant. The high-temperature exhaust from the turbine section of the gas turbine is employed to generate steam in a heat recovery steam generator. The steam drives a steam turbine to produce additional mechanical output. In order to compensate for the removal of the compressed air fed to the oxygen plant, the spent steam from the steam turbine is added to the compressed air and fuel in the combustor portion of the gas turbine. The unexpended energy in the steam fed to the combustor is recovered by expansion in the turbine of the gas turbine and by absorption in the heat receovery stem generator. The release of steam through the gas turbine, and other disclosed techniques, permits elimination of the capital cost of a condenser and cooling tower which would otherwise be required. In addition, the direct provision of compressed air to the oxygen plant eliminates the capital and operating cost of the separate compressor and electric motor conventionally required to provide such compressed air.

Inventors

  • 👤 Donald R. Plumley
  • 👤 Ashok K. Anand

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-10-29 04:13
CPC Classifications
F; F02; F02C; F02C3/00; F02C3/20; F02C3/30; F01; F01K; F01K21/00; F01K21/04; F01K21/042; F01K23/00; F01K23/02; F01K23/06; F01K23/067; F01K23/068; F02C7/00; F02C7/22; F02C7/224; Y; Y02; Y02E; Y02E20/00; Y02E20/16; Y02E20/18

Claims Analysis

Total Claims: 5
Claim 1
Independent Claim 143 words
An improved integrated coal gas and combined cycle plant including; a coal gas plant for producing gaseous fuel; an oxygen plant for supplying oxygen to said coal gas plant, a gas turbine plant producing a hot exhaust gas, a heat recovery steam generator receiving said hot exhaust gas and for producing a steam output, a non-condensing steam turbine for receiving said steam generator output; and, wherein the improvement comprises; means for a portion of the gas turbine plant compressed air to the oxygen plant; means for delivering substantially all of the steam turbine exhaust to the gas turbine plant combustor whereby the mass flow rate through the gas turbine plant remains substantially constant; and, a high pressure steam tap from said heat recovery steam generator to a gaseous fuel preheater whereby substantially all of the high pressure steam is converted back to feedwater.
Claim 2
Dependent Claim 143 words
An improved integrated coal gas and combined cycle plant including; a coal gas plant for producing gaseous fuel; an oxygen plant for supplying oxygen to said coal gas plant, a gas turbine plant producing a hot exhaust gas, a heat recovery steam generator receiving said hot exhaust gas and for producing a steam output, a non-condensing steam turbine for receiving said steam generator output; and, wherein the improvement comprises; means for a portion of the gas turbine plant compressed air to the oxygen plant; means for delivering substantially all of the steam turbine exhaust to the gas turbine plant combustor whereby the mass flow rate through the gas turbine plant remains substantially constant; and, a high pressure steam tap from said heat recovery steam generator to a gaseous fuel preheater whereby substantially all of the high pressure steam is converted back to feedwater.
Claim 3
Dependent Claim 41 words
The improved plant recited in claim 1 wherein the improvement further comprises: an intermediate pressure steam tap from said heat recovery steam generator to said steam turbine exhaust delivery means for selectively augmenting the steam supply to said gas turbine plant.
Claim 4
Dependent Claim 172 words
An integrated coal gasification and combined cycle power plant comprising: a coal gasification plant for producing coal gas; an oxygen plant for producing oxygen for the coal gasification plant; a combined cycle plant including a steam turbine, a heat recovery steam generator and a gas turbine plant; the gas turbine plant receiving coal gas from the coal gasification plant and including an air compressor, a combustor and a gas turbine; means for delivering at least a portion of the steam turbine exhaust to the gas turbine plant to replace the diverted air portion whereby the mass flow through the gas turbine plant remains constant; means for tapping off unexpanded steam from the heat recovery steam generator to augment the flow of steam to the gas turbine plant; and, means for heating the coal gas delivered to the gas turbine plant including heat exchange means connected to a second steam tap on the heat recovery steam generator. means for diverting a portion of the gas turbine plant compressor air to the oxygen plant;
Claim 5
Dependent Claim 172 words
An integrated coal gasification and combined cycle power plant comprising: a coal gasification plant for producing coal gas; an oxygen plant for producing oxygen for the coal gasification plant; a combined cycle plant including a steam turbine, a heat recovery steam generator and a gas turbine plant; the gas turbine plant receiving coal gas from the coal gasification plant and including an air compressor, a combustor and a gas turbine; means for delivering at least a portion of the steam turbine exhaust to the gas turbine plant to replace the diverted air portion whereby the mass flow through the gas turbine plant remains constant; means for tapping off unexpanded steam from the heat recovery steam generator to augment the flow of steam to the gas turbine plant; and, means for heating the coal gas delivered to the gas turbine plant including heat exchange means connected to a second steam tap on the heat recovery steam generator. means for diverting a portion of the gas turbine plant compressor air to the oxygen plant;

References Cited (Backward Citations)

US2959005A Cited
US3703807A Cited
US3832845A Cited
US3930367A Cited
SU523998A1 Cited
US4058974A Cited
JPS5268608A Cited
JPS5535108A Cited
US4472936A Cited
US4488398A Cited
JPS5954736A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1991-11-22 1992-05-23 1992-11-22 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1995-11-22 1996-05-23 1996-11-22 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 1999-11-22 2000-05-23 2000-11-22 $7700.00 Window Closed / Lapsed