Claims Analysis
Total Claims: 18
Claim 1
Independent Claim
156 words
A method of monitoring wall thickness of pipes in a piping system comprising the steps of: boring holes in the outer surfaces of walls of the pipes at predetermined locations along the pipes and to depths larger than the thicknesses at which the pipes will rupture leaving residual wall thicknesses between the ends of the holes and the inner surfaces of the walls; inserting tracer materials in the holes to be released into fluid in the piping system when pipe wall thinning exceeds the residual wall thickness at any of the holes; monitoring fluid flow through the piping system to sense the presence of the tracer materials in the fluid; and determining the location of the hole from which the tracer material was released whereby pipe wall thinning can be detected prior to rupture and thinning of particular pipes within the piping system can be determined to facilitate repair with minimal downtime of the piping system.
Claim 2
Independent Claim
156 words
A method of monitoring wall thickness of pipes in a piping system comprising the steps of: boring holes in the outer surfaces of walls of the pipes at predetermined locations along the pipes and to depths larger than the thicknesses at which the pipes will rupture leaving residual wall thicknesses between the ends of the holes and the inner surfaces of the walls; inserting tracer materials in the holes to be released into fluid in the piping system when pipe wall thinning exceeds the residual wall thickness at any of the holes; monitoring fluid flow through the piping system to sense the presence of the tracer materials in the fluid; and determining the location of the hole from which the tracer material was released whereby pipe wall thinning can be detected prior to rupture and thinning of particular pipes within the piping system can be determined to facilitate repair with minimal downtime of the piping system.
Claim 3
Dependent Claim
54 words
The method as recited in claim 1 wherein said step of inserting tracer material includes inserting different tracer materials in different holes to associate each tracer material with a predetermined location and said step of determining the location of a hole from which a tracer material was released includes analyzing the sensed tracer material.
Claim 4
Dependent Claim
46 words
The method as recited in claim 1 wherein the tracer materials are radioactive and said step of determining the location of the hole from which a sensed tracer material was released includes measuring the radiation external of the piping system to find locations with reduced radioactivity.
Claim 5
Dependent Claim
63 words
The method as recited in claim 1 wherein the tracer materials are maintained in the holes under pressure in vessels and pressure indicators communicate with each vessel to produce a visible signal upon reduction in pressure within the vessels and said step of determinig the location of the hole for which the tracer material was released includes visual inspection of the pressure indicators.
Claim 6
Dependent Claim
30 words
The method as recited in claim 1 wherein said step of boring holes includes determining the predetermined locations as positions of maximum turbulence with the use of mass transfer coefficients.
Claim 7
Dependent Claim
32 words
The method as recited in claim 5 wherein said step of boring holes includes boring two spaced holes at a predetermined location to allow for uncertainties in determining positions of maximum turbulence.
Claim 8
Dependent Claim
16 words
The method as recited in claim 6 wherein the two spaced holes have the same depth.
Claim 9
Dependent Claim
76 words
The method as recited in claim 1 wherein said step of boring holes includes boring first and second holes at a predetermined location to first and second depths to produce first and second different residual wall thicknesses and further comprising the step of determining the rate of pipe wall thinning at the predetermined location by dividing the difference in residual wall thickness by the time elapsed between sensing tracer materials from the first and second holes.
Claim 10
Dependent Claim
29 words
The method as recited in claim 1 wherein said step of inserting tracer materials in the holes includes welding plugs in the holes to seal the tracer materials therein.
Claim 11
Dependent Claim
24 words
The method as recited in claim 9 wherein the plugs are made of the same material as the pipes in which they is welded.
Claim 12
Dependent Claim
17 words
The method as recited in claim 1 wherein the tracer material is a chemical composition under pressure.
Claim 13
Independent Claim
98 words
A method of monitoring thinning of a pipe carrying a fluid comprising the steps of: boring a hole in the outer wall of the pipe to a predetermined depth greater than the wall thickness at which the pipe will rupture to produce a blind end spaced from the internal surface of the pipe wall by a predetermined residual wall thickness, inserting a tracer material in the hole adjacent the blind end, and monitoring the fluid passing through the pipe to sense presence of the tracer material whereby pipe thinning corresponding to the residual wall thickness can be detected.
Claim 14
Independent Claim
98 words
A method of monitoring thinning of a pipe carrying a fluid comprising the steps of: boring a hole in the outer wall of the pipe to a predetermined depth greater than the wall thickness at which the pipe will rupture to produce a blind end spaced from the internal surface of the pipe wall by a predetermined residual wall thickness, inserting a tracer material in the hole adjacent the blind end, and monitoring the fluid passing through the pipe to sense presence of the tracer material whereby pipe thinning corresponding to the residual wall thickness can be detected.
Claim 15
Dependent Claim
33 words
The method as recited in claim 12 and further comprising the step of welding a plug made of the same material as the pipe in the hole to seal the tracer material therein.
Claim 16
Dependent Claim
13 words
The method as recited in claim 13 wherein the tracer material is radioactive.
Claim 17
Dependent Claim
108 words
The method as recited in claim 12 wherein a second hole is bored adjacent the first hole to a predetermined depth less than the predetermined depth of the first hole to produce a predetermined residual wall thickness greater than the predetermined residual wall thickness of the first hole, a tracer material is inserted in the second hole, the fluid is monitored to sense the presence of tracer materials from the first and second holes and the rate of thinning of the pipe wall is determined from the time between sensing of the tracer materials and the difference in the residual wall thicknesses of the first and second holes.
Claim 18
Dependent Claim
34 words
The method as recited as claim 12 and further comprising the step of determining the rate of pipe wall thinning from the time when the tracer material is sensed and the residual wall thickness.