Abstract

Abstract The invention relates to a method for producing insulations of foamed plastic material, in cabinets and doors of refrigerators, freezers and the like. According to the invention, a metered quantity of a foamable mixture is fed into the gaps between the inner and outer walls of a cabinet or door, placed in a foaming jig; the foaming process is controlled by sensing characteristic parameters, for example, the temperature of the jig, cabinet or door, or the pressure of the foaming plastic material, comparing them with reference parameters or data stored in a data processing unit. A control signal is generated to open the foaming jig and to unmold or remove the cabinet or door when at least one of the processing parameters has reached a pre-established value. The metered quantity of mixture fed in each subsequent foaming operation is corrected each time according to the changes in the peak pressure of the foam with respect to the previous foaming operation.

Inventors

  • 👤 Carlo Fiorentini

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-10-28 01:51
CPC Classifications
F; F25; F25D; F25D23/00; F25D23/06; F25D23/062; F25D23/064; B; B29; B29B; B29B7/00; B29B7/74; B29B7/7404; B29C; B29C44/00; B29C44/34; B29C44/60; B29L; B29L2031/00; B29L2031/762; B29L2031/7622

Claims Analysis

Total Claims: 11
Claim 1
Independent Claim 156 words
A method for producing insulation comprised of foamed plastic materials in structures such as cabinets and doors of coolers characterized by spaced apart outer and inner walls, comprising the steps of: feeding a metered quantity of a foamable mixture into the spaces between the outer and inner walls of such structures positioned in a foaming jig; letting the foamable mixture expand until it fills the aforesaid spaces; sensing change in value for at least one of the foaming process parameters and memorizing data in a data processing unit during each foaming operation; comparing said sensed parameter with a reference parameter memorized in the data processing unit, and emitting a control signal by said data processing unit to control the removal of the structure from the foaming jig, after the sensed value of said at least one process parameter has undergone a variation of a pre-established quantity with respect to a reference value of said reference parameter.
Claim 2
Independent Claim 156 words
A method for producing insulation comprised of foamed plastic materials in structures such as cabinets and doors of coolers characterized by spaced apart outer and inner walls, comprising the steps of: feeding a metered quantity of a foamable mixture into the spaces between the outer and inner walls of such structures positioned in a foaming jig; letting the foamable mixture expand until it fills the aforesaid spaces; sensing change in value for at least one of the foaming process parameters and memorizing data in a data processing unit during each foaming operation; comparing said sensed parameter with a reference parameter memorized in the data processing unit, and emitting a control signal by said data processing unit to control the removal of the structure from the foaming jig, after the sensed value of said at least one process parameter has undergone a variation of a pre-established quantity with respect to a reference value of said reference parameter.
Claim 3
Dependent Claim 60 words
A method as claimed in claim 1, in which said foaming process parameters, are selected from the following ones: the pressure exerted by the foam on the walls of the structure; the peak value of said pressure; the temperature of the structure; the temperature of the foaming jig; and the metered amount of the foaming mixture fed into the structure.
Claim 4
Dependent Claim 43 words
A method as claimed in claim 1, comprising the step of changing the process value of said foaming process parameters for a subsequent foaming operation, in relation to the process value of the same parameter obtained during at least one previous foaming operation.
Claim 5
Dependent Claim 54 words
A method as claimed in claim 1, comprising the step of emitting a control signal by said processing unit to cause the structure to be unloaded from the jig after the pressure value exerted by the foam on the walls has been reduced by a pre-established quantity with respect to a reference pressure value.
Claim 6
Dependent Claim 58 words
A method as claimed in claim 1, comprising the step of emitting a control signal by said processing unit to cause the structure to be unloaded from the jig after the pressure value exerted by the foam on the walls has decreased by a pre-established quantity in percentage with respect to the peak value of the foam pressure.
Claim 7
Dependent Claim 38 words
A method as claimed in claim 3, further comprising the step of changing the metered quantity of the mixture fed into the structure, in relation to the maximum pressure reached by the foam in a previous foaming operation.
Claim 8
Dependent Claim 74 words
A method as claimed in claim 6, in which a metered quantity of mixture including a packing or extra amount of mixture is fed into the structure, said method further comprising the step of changing said extra amount of mixture for a foaming operation subsequent to a previous one corresponding to changes in the pressure value of said previous foaming operation with respect to a reference pressure value memorized in said data processing unit.
Claim 9
Dependent Claim 31 words
A method as claimed in claim 7, further comprising the step of controlling the packing degree of the structure, by comparing peak pressure of the foam, with said reference pressure value.
Claim 10
Dependent Claim 45 words
A method as claimed in claim 7, comprising the step of controlling the packing degree of the structure by comparing the peak pressure or the pressure of the foam at the moment of discharging the structure from the foaming jig with said reference pressure value.
Claim 11
Dependent Claim 32 words
A method as claimed in claim 3, further comprising the step of changing the metered quantity of the mixture in relation to the maximum temperature reached by the structure or the jig.

References Cited (Backward Citations)

US3265784A Cited
US3628901A Cited
US3937776A Cited
US3893792A Cited
US3859400A Cited
US4094940A Cited
US4399105A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1991-08-23 1992-02-22 1992-08-23 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1995-08-23 1996-02-22 1996-08-23 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 1999-08-23 2000-02-22 2000-08-23 $7700.00 Window Closed / Lapsed

Assigned Categories & Tags

No categories assigned to this patent yet.

Assign Category Tag