Abstract Proper operation of a system fault monitor is verified while the monitor is coupled on-line with the system and to an alarm line. During periods when actual system signals are produced, the monitor is coupled through one of two time delay circuits to the alarm line. During periods when no actual signals are produced by the system, the monitor input is switched to an error signal generator and the monitor output is coupled through the other time delay circuit to processing circuitry which detects the presence of the alarm signal after the circuit time delay. If no alarm signal is detected, a failure of the monitor and/or delay circuit is indicated.
Inventors
- 👤 Paul H. Feldman
Bibliographic Details
Application Number
—
Jurisdiction
US
Data Source
google_patents
Last Synchronized
2026-11-09 00:01
CPC Classifications
G; G01; G01S; G01S1/00; G01S1/02; G01S1/022
Claims Analysis
Total Claims: 10
Claim 1
Independent Claim
427 words
A test circuit for verifying proper operation of a fault monitor coupled on-line between a source of actual system signals and an alarm line, the system being inoperative at certain inactive time periods so that the actual signals are produced periodically over known operating time periods, said circuit comprising: means for generating during said inactive time periods, an erroneous signal operative to induce the monitor to generate an alarm signal that is to be generated by the monitor when a like false signal is produced by the system during said operating time periods, first switch means for selectively switching an input of the monitor to connect with the source of actual system signals during said operating time periods and with an output of said false signal generating means during said inactive time periods; first and second filter means each for retarding by a certain duration a signal applied to an input of the filter means; second switch means for selectively switching an output of the monitor to the input of said first filter means; third switch means for selectively switching the output of the monitor to the input of said second filter means; alarm line connect means for connecting a selected output of said first and said second filter means to said alarm line; and processing means coupled to said false signal generating means and adapted to control operations of said first to said third switch means and said alarm line connect means, so that in a given test interval (a) said first switch means is set during the known operating time periods to connect the monitor input with the source of actual system signals, said second switch means is closed and said third switch means is open so that output signals from the monitor are applied only to said first filter means, (b) during said inactive time periods the first switch means is set to connect the monitor input with the output of said false signal generating means, the third switch means is closed and the second switch means is open so that output signals from the monitor are applied only to said second filter means, and (c) said alarm line connect means is set to connect the alarm line to the output of said first filter means; wherein said processing means includes means for determining when said false signal has been provided to the monitor input for said certain duration, and first verifying means coupled to the output of said second filter means for detecting the presence of the alarm signal after said certain duration.
Claim 2
Dependent Claim
427 words
A test circuit for verifying proper operation of a fault monitor coupled on-line between a source of actual system signals and an alarm line, the system being inoperative at certain inactive time periods so that the actual signals are produced periodically over known operating time periods, said circuit comprising: means for generating during said inactive time periods, an erroneous signal operative to induce the monitor to generate an alarm signal that is to be generated by the monitor when a like false signal is produced by the system during said operating time periods, first switch means for selectively switching an input of the monitor to connect with the source of actual system signals during said operating time periods and with an output of said false signal generating means during said inactive time periods; first and second filter means each for retarding by a certain duration a signal applied to an input of the filter means; second switch means for selectively switching an output of the monitor to the input of said first filter means; third switch means for selectively switching the output of the monitor to the input of said second filter means; alarm line connect means for connecting a selected output of said first and said second filter means to said alarm line; and processing means coupled to said false signal generating means and adapted to control operations of said first to said third switch means and said alarm line connect means, so that in a given test interval (a) said first switch means is set during the known operating time periods to connect the monitor input with the source of actual system signals, said second switch means is closed and said third switch means is open so that output signals from the monitor are applied only to said first filter means, (b) during said inactive time periods the first switch means is set to connect the monitor input with the output of said false signal generating means, the third switch means is closed and the second switch means is open so that output signals from the monitor are applied only to said second filter means, and (c) said alarm line connect means is set to connect the alarm line to the output of said first filter means; wherein said processing means includes means for determining when said false signal has been provided to the monitor input for said certain duration, and first verifying means coupled to the output of said second filter means for detecting the presence of the alarm signal after said certain duration.
Claim 3
Dependent Claim
172 words
A test circuit according to claim 1, wherein said processing means includes means for reversing, in an alternate test interval, the operating states of said second and said third switch means and said alarm line connect means, so that (a) during the known operating time periods of the system, said second switch means is open and said third switch means is closed so that output signals from the monitor are applied only to said second filter means, (b) during the inactive time periods of the system said third switch means is open and said second switch means is closed so that output signals from the monitor are applied only to said first filter means, and (c) said alarm line connect means is set to connect the alarm line to the output of said second filter means, and second verifying means coupled to the output of said first filter means for detecting the presence of the alarm signal after said false signal has been provided to the monitor input for said certain duration.
Claim 4
Dependent Claim
34 words
A test circuit according to claim 1, including fail alert means associated with said first verifying means for signaling the absence of the alarm signal from said second filter means after said certain duration.
Claim 5
Dependent Claim
63 words
A test circuit according to claim 2, including first fail alert means associated with said first verifying means for signaling the absence of the alarm signal from said second filter means after said certain duration, and second fail alert means associated with said second verifying means for signaling the absence of the alarm signal from said first filter means after said certain duration.
Claim 6
Dependent Claim
238 words
A process for verifying proper operation of a fault monitor coupled on-line between a source of actual system signals and an alarm line, the system being inoperative at certain inactive time periods so that the actual signals are produced periodically over known operating time periods, the process comprising the steps of: generating, during the inactive time periods, an erroneous signal for inducing the monitor to generate an alarm signal which would otherwise be generated by the monitor when a like erroneous signal is produced by the system during the operating time periods; switching an input of the monitor to connect with the source of actual system signals during the operating time periods of the system, and with the generated erroneous signal during the inactive time periods; retarding by a certain duration an output of the monitor with first filter means during said operating time periods in a given test interval; retarding by said certain duration the output of the monitor with second filter means during said inactive time periods in said given test interval; connecting an output of the first filter means with the alarm line in said given test interval; and detecting the presence of the alarm signal at an output of the second filter means after the erroneous signal is input to the monitor for said certain duration during said given test interval, thereby verifying that the monitor and the second filter means are properly operating.
Claim 7
Dependent Claim
238 words
A process for verifying proper operation of a fault monitor coupled on-line between a source of actual system signals and an alarm line, the system being inoperative at certain inactive time periods so that the actual signals are produced periodically over known operating time periods, the process comprising the steps of: generating, during the inactive time periods, an erroneous signal for inducing the monitor to generate an alarm signal which would otherwise be generated by the monitor when a like erroneous signal is produced by the system during the operating time periods; switching an input of the monitor to connect with the source of actual system signals during the operating time periods of the system, and with the generated erroneous signal during the inactive time periods; retarding by a certain duration an output of the monitor with first filter means during said operating time periods in a given test interval; retarding by said certain duration the output of the monitor with second filter means during said inactive time periods in said given test interval; connecting an output of the first filter means with the alarm line in said given test interval; and detecting the presence of the alarm signal at an output of the second filter means after the erroneous signal is input to the monitor for said certain duration during said given test interval, thereby verifying that the monitor and the second filter means are properly operating.
Claim 8
Dependent Claim
105 words
The process of claim 5, including, during an alternate test interval, retarding the output of the monitor with the first filter means during said inactive time periods of the system, retarding the output of the monitor with the second filter means during said operating time periods, connecting the output of the second filter means with said alarm line, and detecting the presence of the alarm signal at the output of the first filter means after the erroneous signal is input to the monitor for said certain duration during the alternate test interval, thereby verifying that the monitor and the first filter means are properly operating.
Claim 9
Dependent Claim
478 words
A microwave landing subsystem such as an elevation subsystem or an azimuth subsystem wherein the subsystem includes a test circuit for verifying proper operation of a fault monitor coupled on-line between a source of actual subsystem signals and an alarm line, the subsystem being inoperative at certain inactive time periods during operation of another subsystem so that the actual signals are produced periodically over known operating time periods, said subsystem comprising: first means for generating periodic subsystem signals; a monitor for monitoring signals generated by said first means; means for generating during said inactive time periods of said first means, a false signal operative to induce the monitor to generate an alarm signal that is to be generated by the monitor when a like false signal is produced by the first means during said operating time periods, first switch means for selectively switching an input of the monitor to connect with the source of said first means signals during said operating time periods and with an output of said false signal generating means during said inactive time periods; first and second filter means each for retarding by a certain duration a signal applied to an input of the filter means; second switch means for selectively switching an output of the monitor to the input of said first filter means; third switch means for selectively switching the output of the monitor to the input of said second filter means; alarm line connect means for connecting a selected output of said first and said second filter means to said alarm line; and processing means coupled to said false signal generating means and adapted to control operations of said first to said third switch means and said alarm line connect means, so that in a given test interval (a) said first switch means is set during the known operating time periods to connect the monitor input with the source of said first means system signals, said second switch means is closed and said third switch means is open so that output signals from the monitor are applied only to said first filter means, (b) during said inactive time periods of said first means the first switch means is set to connect the monitor input with the output of said false signal generating means, the third switch means is closed and the second switch means is open so that output signals from the monitor are applied only to said second filter means, and (c) said alarm line connect means is set to connect the alarm line to the output of said first filter means; wherein said processing means includes means for determining when said false signal has been provided to the monitor input for said certain duration, and first verifying means coupled to the output of said second filter means for detecting the presence of the alarm signal after said certain duration.
Claim 10
Dependent Claim
478 words
A microwave landing subsystem such as an elevation subsystem or an azimuth subsystem wherein the subsystem includes a test circuit for verifying proper operation of a fault monitor coupled on-line between a source of actual subsystem signals and an alarm line, the subsystem being inoperative at certain inactive time periods during operation of another subsystem so that the actual signals are produced periodically over known operating time periods, said subsystem comprising: first means for generating periodic subsystem signals; a monitor for monitoring signals generated by said first means; means for generating during said inactive time periods of said first means, a false signal operative to induce the monitor to generate an alarm signal that is to be generated by the monitor when a like false signal is produced by the first means during said operating time periods, first switch means for selectively switching an input of the monitor to connect with the source of said first means signals during said operating time periods and with an output of said false signal generating means during said inactive time periods; first and second filter means each for retarding by a certain duration a signal applied to an input of the filter means; second switch means for selectively switching an output of the monitor to the input of said first filter means; third switch means for selectively switching the output of the monitor to the input of said second filter means; alarm line connect means for connecting a selected output of said first and said second filter means to said alarm line; and processing means coupled to said false signal generating means and adapted to control operations of said first to said third switch means and said alarm line connect means, so that in a given test interval (a) said first switch means is set during the known operating time periods to connect the monitor input with the source of said first means system signals, said second switch means is closed and said third switch means is open so that output signals from the monitor are applied only to said first filter means, (b) during said inactive time periods of said first means the first switch means is set to connect the monitor input with the output of said false signal generating means, the third switch means is closed and the second switch means is open so that output signals from the monitor are applied only to said second filter means, and (c) said alarm line connect means is set to connect the alarm line to the output of said first filter means; wherein said processing means includes means for determining when said false signal has been provided to the monitor input for said certain duration, and first verifying means coupled to the output of said second filter means for detecting the presence of the alarm signal after said certain duration.
References Cited (Backward Citations)
US3932870A
Cited
US4195300A
Cited
US4138678A
Cited
US4333081A
Cited
US4423418A
Cited
US4532517A
Cited
US4625209A
Cited
US4644357A
Cited
USPTO Annuity & Maintenance Windows
| Annuity Stage | Window Opens | Payment Deadline | Surcharge Period Until | Estimated Fee | Status |
|---|---|---|---|---|---|
| 3.5 Years (Year 4) | 1991-04-19 | 1991-10-19 | 1992-04-19 | $2000.00 | Window Closed / Lapsed |
| 7.5 Years (Year 8) | 1995-04-19 | 1995-10-19 | 1996-04-19 | $3760.00 | Window Closed / Lapsed |
| 11.5 Years (Year 12) | 1999-04-19 | 1999-10-19 | 2000-04-19 | $7700.00 | Window Closed / Lapsed |