Claims Analysis
Total Claims: 7
Claim 1
Independent Claim
139 words
A method of controlling the finished density as a wet slurry delivered to a well for cementing the well, the method comprising the steps of: (a) mixing a first fixed and insufficient flow of water and dry cement to form wet slurry having a density in excess of the desired density for cementing a well wherein the wet slurry flows continuously for delivery to the well; (b) adding a variable supplemental flow of water to the wet slurry having the excessive density to reduce the density of the wet slurry; (c) measuring the density of the flowing wet slurry after adding the variable supplemental flow of water; and (d) controlling the variable supplemental flow of water added to the flowing wet slurry having excessive density to obtain a flowing wet slurry having the desired density for cementing a well.
Claim 2
Independent Claim
139 words
A method of controlling the finished density as a wet slurry delivered to a well for cementing the well, the method comprising the steps of: (a) mixing a first fixed and insufficient flow of water and dry cement to form wet slurry having a density in excess of the desired density for cementing a well wherein the wet slurry flows continuously for delivery to the well; (b) adding a variable supplemental flow of water to the wet slurry having the excessive density to reduce the density of the wet slurry; (c) measuring the density of the flowing wet slurry after adding the variable supplemental flow of water; and (d) controlling the variable supplemental flow of water added to the flowing wet slurry having excessive density to obtain a flowing wet slurry having the desired density for cementing a well.
Claim 3
Dependent Claim
38 words
The method of claim 1 including the step of measuring the variable supplemental flow of water, and determining the required supplemental water flow rate required to achieve the desired density of the wet slurry for cementing a well.
Claim 4
Dependent Claim
59 words
The method of claim 1 including a preliminary mixing step which mixes the dry cement and the first fixed and insufficient flow of water to form the flowing wet slurry having the excessive density; and thereafter mixing the required supplemental water with the flowing wet slurry to achieve the desired density of the wet slurry for cementing the well.
Claim 5
Dependent Claim
23 words
The method of claim 3 wherein the step of measuring the density occurs after mixing the required supplemental water with the wet slurry.
Claim 6
Independent Claim
155 words
A method of controlling the finished density of a flowing wet slurry delivered to a well for cementing the well, the method comprising the steps of: (a) in a continuous flow mixing apparatus receiving dry cement, the step of mixing a first and insufficient flow of water with the dry cement to form a flow of slurry having a deficiency of water; (b) continuously delivering the flow of slurry having a deficiency of water past a measuring device, the measuring device determining the deficiency of water in the flowing wet slurry and forming a signal indicative thereof; (c) adding a variable supplemental flow of water to the flowing wet slurry wherein the amount of water is determined by the signal indicative of the deficiency of water; and (d) after adding the supplemental flow of water, then delivering the flowing wet slurry with a sufficient measure of water therein to a well for cementing the well.
Claim 7
Independent Claim
155 words
A method of controlling the finished density of a flowing wet slurry delivered to a well for cementing the well, the method comprising the steps of: (a) in a continuous flow mixing apparatus receiving dry cement, the step of mixing a first and insufficient flow of water with the dry cement to form a flow of slurry having a deficiency of water; (b) continuously delivering the flow of slurry having a deficiency of water past a measuring device, the measuring device determining the deficiency of water in the flowing wet slurry and forming a signal indicative thereof; (c) adding a variable supplemental flow of water to the flowing wet slurry wherein the amount of water is determined by the signal indicative of the deficiency of water; and (d) after adding the supplemental flow of water, then delivering the flowing wet slurry with a sufficient measure of water therein to a well for cementing the well.