Abstract

Abstract A computer controlled training simulator for a thermal power plant includes a switching device for selecting interactive or independent operation of a boiler simulation section, a turbine simulation section and a generator simulator section. In the interactive mode, the boiler, turbine and generator sections operate as corresponding sections of a single power plant for training operators of the respective sections. In the independent mode, the individual sections are operated as the corresponding sections of three separate power plants so that training of operators of each section can proceed without delays associated with functions of the other two sections.

Inventors

  • 👤 Fumio Sakamoto

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-11-01 19:24
CPC Classifications
G; G09; G09B; G09B25/00; G09B25/02

Claims Analysis

Total Claims: 3
Claim 1
Independent Claim 260 words
An operator training simulator for training operators of a thermal power plant, comprising: a trainer's console producing signals in correspondence to an arbitrary state of process of a thermal power plant as set up by a trainer; a computer including a boiler control section, a turbine control section and a generator control section all for performing predetermined computation of simulation of operation of respective power plant sections in response to the signals produced on said trainer's console; a training equipment including a boiler training section, a turbine training section and a generator training section connected to the respective control sections of said computer and adapted to display the state of a respective boiler plant section, a turbine plant section and a generator plant section obtained as a result of computation by said computer, said equipment being capable of varying the state of process by sending operating signals produced in correspondence to actions taken by trainees back to said computer; and a switch device having (1) a disconnecting mode for functionally dividing the boiler control section, the turbine control section and the generator control section of said computer so that the control sections concurrently operate independently of each other as if three independent power plants are operated in response to the respective training sections, and also having (2) a connecting mode for linking the boiler control section, the turbine control section and the generator control section of said computer so that the control sections operate interactively as if a single unitary power plant is operated in response to the training sections.
Claim 2
Dependent Claim 260 words
An operator training simulator for training operators of a thermal power plant, comprising: a trainer's console producing signals in correspondence to an arbitrary state of process of a thermal power plant as set up by a trainer; a computer including a boiler control section, a turbine control section and a generator control section all for performing predetermined computation of simulation of operation of respective power plant sections in response to the signals produced on said trainer's console; a training equipment including a boiler training section, a turbine training section and a generator training section connected to the respective control sections of said computer and adapted to display the state of a respective boiler plant section, a turbine plant section and a generator plant section obtained as a result of computation by said computer, said equipment being capable of varying the state of process by sending operating signals produced in correspondence to actions taken by trainees back to said computer; and a switch device having (1) a disconnecting mode for functionally dividing the boiler control section, the turbine control section and the generator control section of said computer so that the control sections concurrently operate independently of each other as if three independent power plants are operated in response to the respective training sections, and also having (2) a connecting mode for linking the boiler control section, the turbine control section and the generator control section of said computer so that the control sections operate interactively as if a single unitary power plant is operated in response to the training sections.
Claim 3
Dependent Claim 35 words
An operator training simulator according to claim 1, wherein said trainer's console is made up of three sections in correspondence to said boiler control section, turbine control section and generator control section of said computer.

References Cited (Backward Citations)

US3421232A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1989-12-15 1990-06-16 1990-12-16 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1993-12-15 1994-06-16 1994-12-16 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 1997-12-15 1998-06-16 1998-12-16 $7700.00 Window Closed / Lapsed