Claims Analysis
Total Claims: 11
Claim 1
Independent Claim
387 words
A method of relieving and eliminating ground water buildup near at least a portion of a foundation wall of a building, wherein the building has a basement floor that is internal with respect to the foundation wall, and wherein the basement floor has a top surface, and wherein the building has a footer drain line system extending along the foundation wall portion, including the steps of: (a) digging a trench at a location that is external with respect to and extending along but spaced a substantial distance on the order of several feet laterally outwardly from an underground wall which forms a portion of a foundation wall of a building, the trench extending to a depth below the height of a top surface of a basement floor of the building; (b) installing an elongate auxiliary drain line means in the trench at a level below that of the height of the top surface of the basement floor of the building and at a level below that of nearby portions of the footer drain line system, with the auxiliary drain line means being similarly spaced a substantial distance from and external to the underground wall for providing openings at spaced locations along the elongate auxiliary drain line means to admit water from a surrounding area that is external with respect to the undergrond wall into the auxiliary drain line means, including establishing at least one branch line connection between the auxiliary drain line means and the nearby footer drain line portions so that water may discharge from the footer drain line system through the branch line connection into the auxiliary drain line means; (c) providing means for connecting the auxiliary drain line means to a storm drain line which serves the building so that water which is admitted to the auxiliary drain line means is channeled into the storm drain line; and, (d) filling substantially all but the topmost few inches of the trench with particulate material to provide porous reservoir means surrounding the auxiliary drain line means at a location which is external with respect to the underground wall and extending upwardly from the auxiliary drain line means for receiving ground water and ducting it to the auxiliary ground drain line means to prevent the buildup of ground water in the vicinity of the foundation wall portion.
Claim 2
Independent Claim
387 words
A method of relieving and eliminating ground water buildup near at least a portion of a foundation wall of a building, wherein the building has a basement floor that is internal with respect to the foundation wall, and wherein the basement floor has a top surface, and wherein the building has a footer drain line system extending along the foundation wall portion, including the steps of: (a) digging a trench at a location that is external with respect to and extending along but spaced a substantial distance on the order of several feet laterally outwardly from an underground wall which forms a portion of a foundation wall of a building, the trench extending to a depth below the height of a top surface of a basement floor of the building; (b) installing an elongate auxiliary drain line means in the trench at a level below that of the height of the top surface of the basement floor of the building and at a level below that of nearby portions of the footer drain line system, with the auxiliary drain line means being similarly spaced a substantial distance from and external to the underground wall for providing openings at spaced locations along the elongate auxiliary drain line means to admit water from a surrounding area that is external with respect to the undergrond wall into the auxiliary drain line means, including establishing at least one branch line connection between the auxiliary drain line means and the nearby footer drain line portions so that water may discharge from the footer drain line system through the branch line connection into the auxiliary drain line means; (c) providing means for connecting the auxiliary drain line means to a storm drain line which serves the building so that water which is admitted to the auxiliary drain line means is channeled into the storm drain line; and, (d) filling substantially all but the topmost few inches of the trench with particulate material to provide porous reservoir means surrounding the auxiliary drain line means at a location which is external with respect to the underground wall and extending upwardly from the auxiliary drain line means for receiving ground water and ducting it to the auxiliary ground drain line means to prevent the buildup of ground water in the vicinity of the foundation wall portion.
Claim 3
Dependent Claim
91 words
The method of claim 1 wherein the step of establishing at least one branch line connection between the auxiliary drain line means and the footer drain line system includes the steps of: (a) digging an underground tunnel from a lower portion of the trench to the vicinity of the footer drain line system; and, (b) positioning a connecting conduit in the tunnel at an angle of incline extending downwardly from a point of connection with the footer drain tile system to a point of connection with the auxiliary drain line means.
Claim 4
Dependent Claim
47 words
The method of claim 1 wherein the step of providing means for connecting the auxiliary drain line means to the storm drain line includes the step of constructing a manhole at a location of the connection between the auxiliary drain line means and the storm drain line.
Claim 5
Dependent Claim
72 words
The method of claim 3 wherein, should the storm drain line be found to be positioned too high for the auxiliary drain line means to define by gravity into the storm drain line at the location of the manhole, the auxiliary drain line means is connected to drain into the manhole, and a sump pump is provided in the manhole to transfer water from within the manhole to the storm drain line.
Claim 6
Dependent Claim
43 words
The method of claim 3 wherein, should the storm drain line have a history of backing up into the footer drain line system, a check valve is installed in the storm drain line within the confines of the manhole to prevent such backups.
Claim 7
Dependent Claim
36 words
The method of claim 1 wherein the building has at least one downspout, and the method further includes the step of installing a branch conduit to duct water from the downspout into the auxiliary drain line.
Claim 8
Dependent Claim
32 words
The method of claim 1 wherein the building has at least one downspout, and the method further includes the step of installing a leaf trap in the downspout at a near-ground-level location.
Claim 9
Dependent Claim
132 words
The method of claim 8 wherein the step of installing a leaf trap includes the steps of: (a) providing a leaf trap having a housing with an upper end, a lower end, an inlet near the upper end, an outlet near the lower end, a discharge opening located intermediate the inlet and the outlet, a closure for closing the discharge opening, and screen means carried in the housing for passing water through the housing from the inlet to the outlet, and for directing leaves, pieces of roofing and other debris toward a collection position located near the discharge opening; and (b) positioning the leaf trap to receive water through the inlet from an upper portion of the downspout, and to discharge water from the outlet into a lower portion of the downspout.
Claim 10
Dependent Claim
30 words
The method of claim 8 wherein the step of providing a leaf trap additionally includes the step of providing means biasing the closure toward a position closing the discharge opening.
Claim 11
Dependent Claim
76 words
The method of claim 8 wherein the step of providing a leaf trap having screen means includes the step of providing a screen extending in an inclined manner across the path of flow and being operable to direct water from the inlet opening toward the discharge opening should a substantial buildup of debris occur within the housing for opening the closure and for discharging at least a portion of the collected debris through the discharge opening.