Method of constructing a large spherical tank supported by a skirt on land
Assignee: Moss Rosenberg Verft AS
•
Filing: 1983-03-28
•
Granted: 1985-06-11
•
Expires: 2003-03-28
Abstract
Abstract In the construction of a large, land-based skirt-supported spherical tank, the tank is partially prefabricated, its bottom polar cup section being produced ready for mounting and stored inside the rest of the spherical shell. In this state, wherein the transportation height of the tank has been substantially reduced, the as yet unfinished spherical tank is transported to the erection site, where the bottom polar cap section is lowered into position and secured to the rest of the spherical shell.
Inventors
- 👤 Rolf F. Schrader
Bibliographic Details
Application Number
—
Jurisdiction
US
Data Source
google_patents
Last Synchronized
2026-11-09 09:47
CPC Classifications
E; E04; E04H; E04H7/00; E04H7/02; E04H7/04; E04H7/14
Claims Analysis
Total Claims: 13
Claim 1
Independent Claim
147 words
A method of constructing a large, land-based, skirt-supported spherical tank comprising the steps of, prefabricating said tank initially in two sections at a fabrication site by forming an upper, greater than hemispherical, tank section including a skirt support element and a bottom polar cap section, said upper tank section and said bottom polar cap section having complementary edges adapted to be joined at an erection site to form the completed tank, said edges defining a diameter smaller than the diameter of the completed tank, transporting the prefabricated tank sections to the erection site while supporting the bottom polar cap section inside of the upper tank section thereby reducing the height of the unit during transportation, lowering the bottom polar cap section at the erection site into position with said edges aligned and thereafter securing said bottom polar cap section to the upper section of the tank shell.
Claim 2
Independent Claim
147 words
A method of constructing a large, land-based, skirt-supported spherical tank comprising the steps of, prefabricating said tank initially in two sections at a fabrication site by forming an upper, greater than hemispherical, tank section including a skirt support element and a bottom polar cap section, said upper tank section and said bottom polar cap section having complementary edges adapted to be joined at an erection site to form the completed tank, said edges defining a diameter smaller than the diameter of the completed tank, transporting the prefabricated tank sections to the erection site while supporting the bottom polar cap section inside of the upper tank section thereby reducing the height of the unit during transportation, lowering the bottom polar cap section at the erection site into position with said edges aligned and thereafter securing said bottom polar cap section to the upper section of the tank shell.
Claim 3
Dependent Claim
46 words
A method according to claim 1, including the step of forming a hollow in the ground at the erection site before the prefabricated structure is brought into position at the erection site to provide room for lowering the bottom polar cap section of the sherical tank.
Claim 4
Dependent Claim
37 words
A method according to claim 1, including the step of supporting the prefabricated upper tank section with said polar cap therein during transportation by the use of a temporary support construction engaged with said skirt support element.
Claim 5
Dependent Claim
88 words
A method according to claim 3 including the steps of forming at the erection site a partial support skirt arranged to fit between elements of the temporary support construction in position to be engaged with said skirt support element and assume the support function, positioning the upper tank section with its skirt support element over said partial support skirt, completing the support skirt below the tank's skirt support element and engaging the tank's skirt support element with the completed support skirt and thereafter removing the temporary support construction.
Claim 6
Dependent Claim
63 words
A method according to claim 3 including the steps of removing said prefabricated tank sections into position at the erection site, forming at the erection site a support skirt beneath the tank's skirt support element and in engagement therewith and with the temporary support construction thereby to make the temporary support construction a part of the permanent skirt constructed at the erection site.
Claim 7
Dependent Claim
188 words
In a method of constructing a large, land-based skirt-supported spherical tank, the steps of prefabricating the spherical tank at a fabrication site in two sections by forming an upper greater than hemispherical tank section including a skirt support element and a bottom polar cap section, said upper tank section and said bottom polar cap sections having complimentary edges adapted to be welded together at an erection site to form the completed tank, said edges defining a diameter smaller than the diameter of the completed tank, transporting the prefabricated tank section to the erection site while supporting the bottom polar cap section by suspending it inside the upper section of the spherical tank shell, thereby reducing the height of the unit during transportation, forming slideways for skid transportation of the tank to the erection site, said transportation step including moving the tank section along said slideways into a desired final position at the erection site, lowering the bottom polar cap section at the final position of the tank into position with said edges aligned and thereafter securing said bottom polar cap section of the tank shell along side edge.
Claim 8
Dependent Claim
188 words
In a method of constructing a large, land-based skirt-supported spherical tank, the steps of prefabricating the spherical tank at a fabrication site in two sections by forming an upper greater than hemispherical tank section including a skirt support element and a bottom polar cap section, said upper tank section and said bottom polar cap sections having complimentary edges adapted to be welded together at an erection site to form the completed tank, said edges defining a diameter smaller than the diameter of the completed tank, transporting the prefabricated tank section to the erection site while supporting the bottom polar cap section by suspending it inside the upper section of the spherical tank shell, thereby reducing the height of the unit during transportation, forming slideways for skid transportation of the tank to the erection site, said transportation step including moving the tank section along said slideways into a desired final position at the erection site, lowering the bottom polar cap section at the final position of the tank into position with said edges aligned and thereafter securing said bottom polar cap section of the tank shell along side edge.
Claim 9
Dependent Claim
78 words
A method according to claim 6, wherein said step of forming slideways includes the steps of forming at least first and second perpendicularly extending and intersecting slideways each consisting of a pair of parallelly extending skid slides, and the additional steps of forming a construction hollow at the erection site to provide room for lowering the bottom polar cap section, the distance between the parallel skid slides being made wide enough to give room for the construction hollow.
Claim 10
Dependent Claim
198 words
In a method of constructing a large, land-based skirt-supported spherical tank, the steps of prefabricating the spherical tank at a fabrication site in two sections by forming an upper greater than hemispherical tank section including a skirt support element and a bottom polar cap section, said upper tank section and said bottom polar cap section having complimentary edges adapted to be welded together at an erection site to form the completed tank, said edges defining a diameter smaller than the diameter of the completed tank, transporting the prefabricated tank section to the erection site while supporting the bottom polar cap section by suspending it inside the upper section of the spherical tank shell, thereby reducing the height of the unit during transportation, lowering the bottom polar cap section at the final position of the tank into position with said edges aligned and thereafter securing said bottom polar cap section of the tank shell along said edge and forming at the erection site a concrete skirt by using slip-form concrete construction and embedding said tank skirt support element secured to the tank within the concrete, including the step of anchoring the tank support skirt element in the concrete skirt.
Claim 11
Dependent Claim
198 words
In a method of constructing a large, land-based skirt-supported spherical tank, the steps of prefabricating the spherical tank at a fabrication site in two sections by forming an upper greater than hemispherical tank section including a skirt support element and a bottom polar cap section, said upper tank section and said bottom polar cap section having complimentary edges adapted to be welded together at an erection site to form the completed tank, said edges defining a diameter smaller than the diameter of the completed tank, transporting the prefabricated tank section to the erection site while supporting the bottom polar cap section by suspending it inside the upper section of the spherical tank shell, thereby reducing the height of the unit during transportation, lowering the bottom polar cap section at the final position of the tank into position with said edges aligned and thereafter securing said bottom polar cap section of the tank shell along said edge and forming at the erection site a concrete skirt by using slip-form concrete construction and embedding said tank skirt support element secured to the tank within the concrete, including the step of anchoring the tank support skirt element in the concrete skirt.
Claim 12
Dependent Claim
272 words
In a method of constructing a large, land-based skirt-supported spherical tank, the steps of prefabricating the spherical tank at a fabrication site in two sections by forming an upper greater than hemispherical tank section including a skirt support element and a bottom polar cap section, said upper tank section and said bottom polar cap section having complimentary edges adapted to be welded together at an erection site to form the completed tank, said edges defining a diameter smaller than the diameter of the completed tank, transporting the prefabricated tank section to the erection site while supporting the bottom polar cap section by suspending it inside the upper section of the spherical tank shell, thereby reducing the height of the unit during transportation, lowering the bottom polar cap section at the final position of the tank into position with said edges aligned and thereafter securing said bottom polar cap section of the tank shell along side edge supporting the prefabricated upper tank section during said transportation step by a temporary support construction engaged with the tank's skirt support element, casting a concrete skirt in several sections at the erection site, supporting said upper tank sections on said concrete skirt sections by use of a plurality of intermediate members between said tank support skirt and said concrete skirt sections, removing the tank support construction, engaging a plurality of jacks between said concrete skirt sections and said tank support skirt element for transfering the tank weight therebetween and for fine adjustment of the tank height, and thereafter casting more concrete up to a desired level for anchoring said tank skirt support element in the concrete.
Claim 13
Dependent Claim
272 words
In a method of constructing a large, land-based skirt-supported spherical tank, the steps of prefabricating the spherical tank at a fabrication site in two sections by forming an upper greater than hemispherical tank section including a skirt support element and a bottom polar cap section, said upper tank section and said bottom polar cap section having complimentary edges adapted to be welded together at an erection site to form the completed tank, said edges defining a diameter smaller than the diameter of the completed tank, transporting the prefabricated tank section to the erection site while supporting the bottom polar cap section by suspending it inside the upper section of the spherical tank shell, thereby reducing the height of the unit during transportation, lowering the bottom polar cap section at the final position of the tank into position with said edges aligned and thereafter securing said bottom polar cap section of the tank shell along side edge supporting the prefabricated upper tank section during said transportation step by a temporary support construction engaged with the tank's skirt support element, casting a concrete skirt in several sections at the erection site, supporting said upper tank sections on said concrete skirt sections by use of a plurality of intermediate members between said tank support skirt and said concrete skirt sections, removing the tank support construction, engaging a plurality of jacks between said concrete skirt sections and said tank support skirt element for transfering the tank weight therebetween and for fine adjustment of the tank height, and thereafter casting more concrete up to a desired level for anchoring said tank skirt support element in the concrete.
References Cited (Backward Citations)
US879196A
Cited
US1026059A
Cited
US1602664A
Cited
US1958487A
Cited
US2363992A
Cited
US2562601A
Cited
US2562602A
Cited
US3956816A
Cited
USPTO Annuity & Maintenance Windows
| Annuity Stage | Window Opens | Payment Deadline | Surcharge Period Until | Estimated Fee | Status |
|---|---|---|---|---|---|
| 3.5 Years (Year 4) | 1988-06-10 | 1988-12-10 | 1989-06-11 | $2000.00 | Window Closed / Lapsed |
| 7.5 Years (Year 8) | 1992-06-10 | 1992-12-10 | 1993-06-11 | $3760.00 | Window Closed / Lapsed |
| 11.5 Years (Year 12) | 1996-06-10 | 1996-12-10 | 1997-06-11 | $7700.00 | Window Closed / Lapsed |