Abstract

Abstract The element moulding consists of metal mesh and contains prepunched perforations. These perforations for the introduction of reinforcing bars are arranged in a row parallel to the longitudinal edge of the element moulding. When concreting the first stage the element moulding is buttressed unilaterally with wooden support elements. Before commencing the concreting of the second stage the wooden support elements are removed. The element moulding is used as sunken shuttering for both stages of the concrete structure. The erection of element moulding shuttering is easy and effortless; the bonding of both stages flawlessly effected.

Inventors

  • 👤 Heinz Witschi
  • 👤 Peter Fankhauser

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-11-03 19:55
CPC Classifications
E; E04; E04G; E04G21/00; E04G21/12; E04G21/125; E04B; E04B5/00; E04B5/16; E04B5/32; E04G11/00; E04G11/36; E04G11/365; E04B2005/322

Claims Analysis

Total Claims: 17
Claim 1
Independent Claim 168 words
Apparatus for use in a two-stage concrete pouring construction process such as pouring floors or ceilings for buildings, comprising: a horizontal shuttering; an element moulding for use as a sunken shuttering comprising a rigid profile metal mesh on said horizontal shuttering, said mesh having two longitudinal edges; a plank liner arranged between the metal mesh and the horizontal shuttering for spacing the mesh from the horizontal shuttering, said plank liner being removable before the concrete pouring of the second stage; a plurality of horizontally oriented reinforcing bars; perforation means in said element moulding for introducing the plurality of horizontally oriented reinforcing bars, said perforation means being disposed in two parallel lines, each line laying near one of the two longitudinal edges of the element moulding; and support means for laterally buttressing the element moulding metal mesh on one side and to be fixed to said horizontal shuttering before the introduction of the concrete pouring of a first stage, and removable before the concrete pouring of the second stage.
Claim 2
Dependent Claim 168 words
Apparatus for use in a two-stage concrete pouring construction process such as pouring floors or ceilings for buildings, comprising: a horizontal shuttering; an element moulding for use as a sunken shuttering comprising a rigid profile metal mesh on said horizontal shuttering, said mesh having two longitudinal edges; a plank liner arranged between the metal mesh and the horizontal shuttering for spacing the mesh from the horizontal shuttering, said plank liner being removable before the concrete pouring of the second stage; a plurality of horizontally oriented reinforcing bars; perforation means in said element moulding for introducing the plurality of horizontally oriented reinforcing bars, said perforation means being disposed in two parallel lines, each line laying near one of the two longitudinal edges of the element moulding; and support means for laterally buttressing the element moulding metal mesh on one side and to be fixed to said horizontal shuttering before the introduction of the concrete pouring of a first stage, and removable before the concrete pouring of the second stage.
Claim 3
Dependent Claim 13 words
Apparatus of claim 1, wherein several sections of element mouldings are stacked vertically.
Claim 4
Dependent Claim 20 words
Element moulding of claim 2, wherein several sections of element mouldings are attached to the support means by fastening means.
Claim 5
Dependent Claim 17 words
Element moulding of claim 1, wherein several sections of element mouldings are laid end to end longitudinally.
Claim 6
Dependent Claim 20 words
Element moulding of claim 4, wherein several sections of moulding are attached to the support element means by fastening means.
Claim 7
Dependent Claim 18 words
Element moulding of claim 1, wherein: said metal mesh is castellated in a U-form with a connecting bridge.
Claim 8
Dependent Claim 35 words
Element moulding according to claim 1, wherein several sections of the element moulding are stacked vertically and unilaterally buttressed by said removable support means before the introduction of the concrete pouring of the first stage.
Claim 9
Dependent Claim 47 words
Apparatus of claim 6, wherein said U-form metal mesh includes a leg portion which is parallel to said shuttering and said plank liner, said leg portion bearing upon said plank liner and supporting the metal mesh prior to the pouring of the concrete of the first sage.
Claim 10
Dependent Claim 120 words
Apparatus for use in a two-stage concrete pouring construction process such as pouring floors or ceilings for buildings, comprising: a shuttering; an element moulding comprising a rigid profile metal mesh mounted on said shuttering; a plank liner arranged between the metal mesh and the shuttering for spacing the metal mesh from the shuttering; perforation means in said metal mesh; a plurality of reinforcing bars extending through said perforation means transversely to said metal mesh; and support means for laterally buttressing the element moulding metal mesh on one side, said support means being adapted to be fixed to said shuttering before the introduction of the concrete pouring of a first stage, and removable before the concrete pouring of the second stage.
Claim 11
Dependent Claim 120 words
Apparatus for use in a two-stage concrete pouring construction process such as pouring floors or ceilings for buildings, comprising: a shuttering; an element moulding comprising a rigid profile metal mesh mounted on said shuttering; a plank liner arranged between the metal mesh and the shuttering for spacing the metal mesh from the shuttering; perforation means in said metal mesh; a plurality of reinforcing bars extending through said perforation means transversely to said metal mesh; and support means for laterally buttressing the element moulding metal mesh on one side, said support means being adapted to be fixed to said shuttering before the introduction of the concrete pouring of a first stage, and removable before the concrete pouring of the second stage.
Claim 12
Dependent Claim 14 words
Element moulding of claim 9, wherein several sections of element mouldings are stacked vertically.
Claim 13
Dependent Claim 20 words
Element moulding of claim 9, wherein several sections of element mouldings are attached to the support means by fastening means.
Claim 14
Dependent Claim 17 words
Element moulding of claim 9, wherein several sections of element mouldings are laid end to end longitudinally.
Claim 15
Dependent Claim 21 words
Element moulding of claim 9, wherein several sections of element moulding are attached to the support element means by fastening means.
Claim 16
Dependent Claim 18 words
Element moulding of claim 9, wherein said metal mesh is castellated in a U-form with a connecting bridge.
Claim 17
Dependent Claim 47 words
Apparatus of claim 14, wherein said U-form metal mesh includes a leg portion which is parallel to said shuttering and said plank liner, said leg portion bearing upon said plank liner and supporting the metal mesh prior to the pouring of the concrete of the first stage.

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1988-03-25 1988-09-24 1989-03-26 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1992-03-25 1992-09-24 1993-03-26 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 1996-03-25 1996-09-24 1997-03-26 $7700.00 Window Closed / Lapsed