Abstract

Abstract A process and apparatus for the continuous production of shaped aluminum alloy-particulate composites. The process comprises metering at a substantially constant ratio a particulate solid molten aluminum alloy containing at least 0.10% by weight of magnesium into a mixing station while continuously vigorously agitating to produce a homogeneous mixture, simultaneously discharging from the mixing station a homogeneous mixture of molten aluminum alloy and particulate solid, transferring the mixture to a forming station and shaping and solidifying the composite.

Inventors

  • 👤 Malachi P. Kenney
  • 👤 Kenneth P. Young
  • 👤 Alan A. Koch

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-10-24 19:19
CPC Classifications
C; C22; C22C; C22C1/00; C22C1/12; Y; Y10; Y10S; Y10S164/00; Y10S164/90

Claims Analysis

Total Claims: 12
Claim 1
Independent Claim 194 words
A continuous process for the production of a shaped composite of an aluminum alloy and a particulate solid other than an aluminum alloy comprising metering into a mixing station, at a substantially constant ratio by weight, the particulate solid in uncoated form and molten aluminum alloy containing at least 0.10% by weight of magnesium while said aluminum alloy and particulate solid are continuously vigorously agitated at a shear rate sufficient to produce a homogeneous mixture of molten aluminum alloy and particulate solid, simultaneously with said metering step continuously discharging a homogeneous mixture of molten aluminum alloy and particulate solid into a holding station, said mixture being continuously agitated in said holding station while the temperature of the alloy is maintained above the liquidus temperature, said agitation being at a shear rate of at least 200 sec. 1 and being sufficient to maintain the mixture homogeneous and to substantially prevent chemical reaction between the alloy and said particulate solid, tranversing said molten aluminum alloy-particulate mixture while still homogeneous to a forming station and shaping and solidifying said aluminum alloy-particulate composite at said forming station into a shaped part containing a particulate solid uniformly dispersed therein.
Claim 2
Dependent Claim 194 words
A continuous process for the production of a shaped composite of an aluminum alloy and a particulate solid other than an aluminum alloy comprising metering into a mixing station, at a substantially constant ratio by weight, the particulate solid in uncoated form and molten aluminum alloy containing at least 0.10% by weight of magnesium while said aluminum alloy and particulate solid are continuously vigorously agitated at a shear rate sufficient to produce a homogeneous mixture of molten aluminum alloy and particulate solid, simultaneously with said metering step continuously discharging a homogeneous mixture of molten aluminum alloy and particulate solid into a holding station, said mixture being continuously agitated in said holding station while the temperature of the alloy is maintained above the liquidus temperature, said agitation being at a shear rate of at least 200 sec. 1 and being sufficient to maintain the mixture homogeneous and to substantially prevent chemical reaction between the alloy and said particulate solid, tranversing said molten aluminum alloy-particulate mixture while still homogeneous to a forming station and shaping and solidifying said aluminum alloy-particulate composite at said forming station into a shaped part containing a particulate solid uniformly dispersed therein.
Claim 3
Dependent Claim 13 words
The process of claim 1 in which the particulate solid is silica sand.
Claim 4
Dependent Claim 29 words
The process of claim 1 in which the particulate solid is continuously metered into said mixing station and the molten aluminum alloy is incrementally metered into said mixing station.
Claim 5
Dependent Claim 19 words
The process of claim 1 in which the aluminum alloy contains from 0.10 to 10% by weight of magnesium.
Claim 6
Dependent Claim 19 words
The process of claim 5 in which the aluminum alloy contains from 0.2 to 1% by weight of magnesium.
Claim 7
Dependent Claim 26 words
The process of claim 1 in which the particulate solid comprises from 1 to 50% by weight of the total weight of the aluminum alloy-sand composite.
Claim 8
Dependent Claim 23 words
The process of claim 7 in which the particulate solid comprises from 15-40% by weight of the total weight of the aluminum-particulate composite.
Claim 9
Dependent Claim 16 words
The process of claim 1 in which the aluminum alloy-particulate composite is shaped by die casting.
Claim 10
Dependent Claim 24 words
The process of claim 1 in which said vigorous agitation produces sufficient centrifigal force to continuously discharge the aluminum-sand mixture from the mixing station.
Claim 11
Dependent Claim 191 words
A continuous process for the production of a shaped aluminum alloy-sand composite comprising metering into a mixing station, at a substantially constant ratio by weight, uncoated sand and molten aluminum alloy containing from 0.10% to 10% by weight of magnesium while said aluminum and sand are continuously vigorously agitated at a shear rate sufficient to produce a homogeneous mixture of molten aluminum alloy and sand, simultaneously with said metering step continuously discharging from said mixing station into a holding station a homogeneous mixture of molten aluminum alloy and sand, said mixture being continuously agitated in said holding station while the temperature of the alloy is maintained above the liquidus temperature, said agitation being at a shear rate of at least 200 sec. -1 and being sufficient to maintain the mixture homogeneous and to substantially prevent chemical reaction between the alloy and sand, transferring said homogeneous aluminum alloy-sand mixture while still molten to a forming station and shaping and solidifying said aluminum alloy-sand composite at said forming station into a non-load bearing shaped part, the sand comprising from 15-40% by weight of the total weight of the composite and uniformly dispersed therein.
Claim 12
Dependent Claim 191 words
A continuous process for the production of a shaped aluminum alloy-sand composite comprising metering into a mixing station, at a substantially constant ratio by weight, uncoated sand and molten aluminum alloy containing from 0.10% to 10% by weight of magnesium while said aluminum and sand are continuously vigorously agitated at a shear rate sufficient to produce a homogeneous mixture of molten aluminum alloy and sand, simultaneously with said metering step continuously discharging from said mixing station into a holding station a homogeneous mixture of molten aluminum alloy and sand, said mixture being continuously agitated in said holding station while the temperature of the alloy is maintained above the liquidus temperature, said agitation being at a shear rate of at least 200 sec. -1 and being sufficient to maintain the mixture homogeneous and to substantially prevent chemical reaction between the alloy and sand, transferring said homogeneous aluminum alloy-sand mixture while still molten to a forming station and shaping and solidifying said aluminum alloy-sand composite at said forming station into a non-load bearing shaped part, the sand comprising from 15-40% by weight of the total weight of the composite and uniformly dispersed therein.

References Cited (Backward Citations)

US3110939A Cited
AT225362B Cited
DE1166421B Cited
DE1245049B Cited
US3305902A Cited
US3521698A Cited
US3600163A Cited
GB1543206A Cited
US4330027A Cited
SU770650A1 Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1987-09-25 1988-03-26 1988-09-25 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1991-09-25 1992-03-26 1992-09-25 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 1995-09-25 1996-03-26 1996-09-25 $7700.00 Window Closed / Lapsed

Assigned Categories & Tags

No categories assigned to this patent yet.

Assign Category Tag