Foam gravel packing in highly deviated wells
Assignee: Chevron USA Inc
•
Filing: 1982-07-06
•
Granted: 1984-07-17
•
Expires: 2002-07-06
Abstract
Abstract A method for packing particulate material in the annulus surrounding a liner in a subsurface well having a substantial deviation from vertical. Foam carrier fluid is employed for placing the particulate material. The geometry of the apparatus at the location where the material is to be placed is described.
Inventors
- 👤 Thomas D. Elson
- 👤 Ralph S. Millhone
Bibliographic Details
Application Number
—
Jurisdiction
US
Data Source
google_patents
Last Synchronized
2026-11-08 21:53
CPC Classifications
E; E21; E21B; E21B43/00; E21B43/02; E21B43/04; E21B21/00; E21B21/14
Claims Analysis
Total Claims: 14
Claim 1
Independent Claim
162 words
A method for packing particulate material in the annulus surrounding a liner having production perforations therethrough positioned in a subsurface well bore having substantial deviation from vertical comprising the steps of: (a) positioning said liner in said subsurface well bore having substantial deviation from the vertical adjacent to said subsurface to be packed near the end of a well bore conductor and centralizing said liner in said well bore, (b) generating at the earth's surface a relatively dry stable foam material having a liquid volume fraction between 0.02 and 0.2, (c) fluidizing said particulate material with said stable foam, (d) forcing said fluidized foam-particulate mixture down said well bore conductor and into said annulus surrounding said liner, (e) causing said particulate material of said foam-particulate mixture to be retained in said annulus beginning at or substantially near the downhole end of said liner, (f) moving said foam of said foam-particulate mixture upwardly through the inside of said liner and said well bore.
Claim 2
Independent Claim
162 words
A method for packing particulate material in the annulus surrounding a liner having production perforations therethrough positioned in a subsurface well bore having substantial deviation from vertical comprising the steps of: (a) positioning said liner in said subsurface well bore having substantial deviation from the vertical adjacent to said subsurface to be packed near the end of a well bore conductor and centralizing said liner in said well bore, (b) generating at the earth's surface a relatively dry stable foam material having a liquid volume fraction between 0.02 and 0.2, (c) fluidizing said particulate material with said stable foam, (d) forcing said fluidized foam-particulate mixture down said well bore conductor and into said annulus surrounding said liner, (e) causing said particulate material of said foam-particulate mixture to be retained in said annulus beginning at or substantially near the downhole end of said liner, (f) moving said foam of said foam-particulate mixture upwardly through the inside of said liner and said well bore.
Claim 3
Dependent Claim
16 words
The method of claim 1 wherein said foam has a liquid volume fraction of about 0.05.
Claim 4
Dependent Claim
35 words
The method of claim 1 wherein an inner conductor is placed within said liner and said foam of said foam-particulate mixture is moved upwardly through said inner conductor from said downhole end of said liner.
Claim 5
Dependent Claim
26 words
The method of claim 3 wherein said inner conductor has an outside diameter measurement which is at least 80% of the inside diameter of said liner.
Claim 6
Dependent Claim
35 words
The method of claim 1 wherein a liquid volume fraction characteristic of said foam is established for temperature and pressure conditions existing in said subsurface well bore where said particulate material is to be packed.
Claim 7
Dependent Claim
37 words
The method of claim 1 wherein the foam-particulate mixture in the annulus surrounding said liner is maintained in flow and velocity toward said downhole end of said liner prior to retaining said particulate material in said annulus.
Claim 8
Dependent Claim
49 words
The method of claim 1 wherein foam separated from said foam-particulate mixture is preferentially moved upwardly through the inside of said liner from the deepest vertical end of said annulus surrounding said liner and restricted from movement through said production perforations in said liner above said deepest vertical end.
Claim 9
Dependent Claim
45 words
The method of claim 1 wherein a tail pipe is inserted inside said liner and moving of said foam of said foam-particulate material is upward through said tail pipe from the end thereof adjacent to the deepest vertical end of said annulus surrounding said liner.
Claim 10
Dependent Claim
33 words
The method of claim 8 wherein the inner annulus between said tail pipe and the inside of said liner is so constructed and arranged as to restrict foam moving through said inner annulus.
Claim 11
Dependent Claim
16 words
The method of claim 1 wherein the foam is stabilized by adding a viscosifying agent thereto.
Claim 12
Dependent Claim
12 words
The method of claim 10 wherein the viscosifying agent is a polymer.
Claim 13
Independent Claim
123 words
A method for reducing particulate material settling and duning in packing particulate material in an annulus surrounding a centralized liner positioned in a subsurface well bore deviated more than 60° from vertical comprising: (a) suspending said particulate material in a dry stable foam having a liquid volume fraction between 0.02 and 0.2 to create a foam-particulate mixture, (b) flowing said foam-particulate mixture into said annulus within said well bore deviated more than 60° from vertical at a flow rate and velocity to maintain mixture flow toward the deepest vertical end of said annulus, (c) separating said foam from said foam-particulate mixture, beginning at said deepest vertical end of said annulus, and (d) moving said separated foam upward through the inside of said liner.
Claim 14
Independent Claim
123 words
A method for reducing particulate material settling and duning in packing particulate material in an annulus surrounding a centralized liner positioned in a subsurface well bore deviated more than 60° from vertical comprising: (a) suspending said particulate material in a dry stable foam having a liquid volume fraction between 0.02 and 0.2 to create a foam-particulate mixture, (b) flowing said foam-particulate mixture into said annulus within said well bore deviated more than 60° from vertical at a flow rate and velocity to maintain mixture flow toward the deepest vertical end of said annulus, (c) separating said foam from said foam-particulate mixture, beginning at said deepest vertical end of said annulus, and (d) moving said separated foam upward through the inside of said liner.
References Cited (Backward Citations)
US3530940A
Cited
US3587740A
Cited
US3603398A
Cited
US3583483A
Cited
US3963076A
Cited
US3999608A
Cited
US4119150A
Cited
USPTO Annuity & Maintenance Windows
| Annuity Stage | Window Opens | Payment Deadline | Surcharge Period Until | Estimated Fee | Status |
|---|---|---|---|---|---|
| 3.5 Years (Year 4) | 1987-07-17 | 1988-01-16 | 1988-07-17 | $2000.00 | Window Closed / Lapsed |
| 7.5 Years (Year 8) | 1991-07-17 | 1992-01-16 | 1992-07-17 | $3760.00 | Window Closed / Lapsed |
| 11.5 Years (Year 12) | 1995-07-17 | 1996-01-16 | 1996-07-17 | $7700.00 | Window Closed / Lapsed |