Abstract

Abstract An armored cable and a method of manufacturing an armored cable, said cable having a helically wrapped zinc-plated steel armor. The steel armor band has zinc protective layer on its two sides, and uncoated edges, to reduce manufacturing costs and improve cathodic protection. The zinc protective layer thereby comprises a first layer portion consisting of a zinc-iron alloy and a second layer portion, on top of said first layer portion consisting of essentially pure unalloyed zinc and having a thickness of at least 90% of the total layer thickness.

Inventors

  • 👤 Albertus T. M. Grooten

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-11-05 16:36
CPC Classifications
H; H01; H01B; H01B7/00; H01B7/17; H01B7/28; H01B7/2806

Claims Analysis

Total Claims: 7
Claim 1
Independent Claim 78 words
A cable comprising an armoring of a zinc-plated steel band in which the steel band comprises a zinc protective layer on the flat sides only of the band, said protective layer comprising a first layer portion consisting of a zinc iron alloy and a second layer portion on top of said first layer portion, consisting of essentially pure unalloyed zinc in which the thickness of the second layer portion is at least 90% of the total layer thickness.
Claim 2
Dependent Claim 78 words
A cable comprising an armoring of a zinc-plated steel band in which the steel band comprises a zinc protective layer on the flat sides only of the band, said protective layer comprising a first layer portion consisting of a zinc iron alloy and a second layer portion on top of said first layer portion, consisting of essentially pure unalloyed zinc in which the thickness of the second layer portion is at least 90% of the total layer thickness.
Claim 3
Dependent Claim 24 words
A cable as claimed in claim 1 wherein the thickness of the second layer portion is at least 95% of the total layer thickness.
Claim 4
Dependent Claim 41 words
A cable as claimed in claim 1 wherein the protective layer has a thickness of approximately 20-25 μm, the first layer portion has a thickness of approximately 0.1-0.5 μm and the second layer portion has a thickness of approximately 19.5-24.9 μm.
Claim 5
Independent Claim 104 words
A method of manufacturing an armored cable, comprising: applying onto both sides of a steel sheet a zinc protective layer such that a first layer portion consisting of zinc-iron alloy is formed and on top of said first layer portion a second layer portion consisting of essentially pure unalloyed zinc is formed whereby the thickness of the second layer portion is at least 90% of the total layer thickness, cutting said sheet into a plurality of elongated bands having the zinc layer on both sides and having unprotected edges, and helically wrapping said bands about a cable so as to form an armored cable.
Claim 6
Independent Claim 104 words
A method of manufacturing an armored cable, comprising: applying onto both sides of a steel sheet a zinc protective layer such that a first layer portion consisting of zinc-iron alloy is formed and on top of said first layer portion a second layer portion consisting of essentially pure unalloyed zinc is formed whereby the thickness of the second layer portion is at least 90% of the total layer thickness, cutting said sheet into a plurality of elongated bands having the zinc layer on both sides and having unprotected edges, and helically wrapping said bands about a cable so as to form an armored cable.
Claim 7
Dependent Claim 18 words
A method as claimed in claim 4, characterized in that said applying step comprises the Sendzimir coating process.

References Cited (Backward Citations)

US312673A Cited
US451605A Cited
US2041842A Cited
US3153696A Cited
GB2037060A Cited
GB2035666A Cited
GB2080242A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1987-03-27 1987-09-26 1988-03-27 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1991-03-27 1991-09-26 1992-03-27 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 1995-03-27 1995-09-26 1996-03-27 $7700.00 Window Closed / Lapsed

Assigned Categories & Tags

No categories assigned to this patent yet.

Assign Category Tag