Abstract

Abstract A method of flow testing a producing formation through a well including lowering into the well a recording pressure and temperature device to measure pressure and temperature as functions of time, then lowering into the well a test chamber closed at the bottom by a surface activated valve. The space between the chamber and the top of the formation is sealed and immediately thereafter the pressure and temperature of the well is measured. The valve on the test chamber is opened to allow formation fluids to enter therein and the pressure and temperature is measured as a function of time for a substantial period of time during which the pressure in the chamber increases, whereby the flow capacity and skin factor of the formation can be calculated.

Inventors

  • 👤 James N. Bostic, III
  • 👤 Robert D. Carter
  • 👤 Ram G. Agarwal
  • 👤 Ronald F. Crowell

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-10-27 21:55
CPC Classifications
E; E21; E21B; E21B49/00; E21B49/08; E21B49/087; E21B47/00; E21B47/10; E21B49/008

Claims Analysis

Total Claims: 14
Claim 1
Independent Claim 89 words
A method of flow testing a producing low-permeability gas-formation through a well comprising: (a) placing an instrument adjacent the formation; (b) placing test chamber apparatus in the well; (c) sealing the space between said test chamber apparatus and the well and measuring the pressure and temperature within the well with said instrument; (d) allowing formation fluids to enter said test chamber apparatus; and (e) measuring the pressure and temperature within the well as a function of time by said instrument as the pressure within said test chamber apparatus increases.
Claim 2
Independent Claim 89 words
A method of flow testing a producing low-permeability gas-formation through a well comprising: (a) placing an instrument adjacent the formation; (b) placing test chamber apparatus in the well; (c) sealing the space between said test chamber apparatus and the well and measuring the pressure and temperature within the well with said instrument; (d) allowing formation fluids to enter said test chamber apparatus; and (e) measuring the pressure and temperature within the well as a function of time by said instrument as the pressure within said test chamber apparatus increases.
Claim 3
Independent Claim 110 words
A method of flow testing a low-permeability gas-producing formation through a well comprising: (a) placing an instrument adjacent the formation; (b) placing perforating means opposite the formation; (c) placing test chamber apparatus in the well; (d) sealing the space between said test chamber apparatus and the well; (e) actuating said perforating means to permit flow of formation fluid into the well; (f) measuring the pressure and temperature within the well with said instrument; (g) allowing formation fluids to enter said test chamber apparatus; and (h) measuring the pressure and temperature within the well as a function of time by said instrument as the pressure within said test chamber apparatus increases.
Claim 4
Independent Claim 110 words
A method of flow testing a low-permeability gas-producing formation through a well comprising: (a) placing an instrument adjacent the formation; (b) placing perforating means opposite the formation; (c) placing test chamber apparatus in the well; (d) sealing the space between said test chamber apparatus and the well; (e) actuating said perforating means to permit flow of formation fluid into the well; (f) measuring the pressure and temperature within the well with said instrument; (g) allowing formation fluids to enter said test chamber apparatus; and (h) measuring the pressure and temperature within the well as a function of time by said instrument as the pressure within said test chamber apparatus increases.
Claim 5
Independent Claim 17 words
The method of claims 1 or 2 wherein said instrument is a recording pressure and temperature bomb.
Claim 6
Independent Claim 21 words
The method of claims 1 or 2 wherein said test chamber apparatus is provided with a valve controllable from the surface.
Claim 7
Independent Claim 21 words
The method of claims 1 or 2 wherein the pressure within said test chamber is lower than that of said formation.
Claim 8
Independent Claim 23 words
The method of claims 1 or 2 wherein the space between said test chamber and the well is sealed by a gravel packer.
Claim 9
Dependent Claim 29 words
The method of claim 4 wherein formation fluids enter said test chamber by opening said valve, whereby fluids from said formation flow into said test chamber under variable pressures.
Claim 10
Dependent Claim 46 words
The method of claim 1 wherein after allowing formation fluids to enter said test chamber the pressure and temperature are measured as a function of time for a substantial period of time during which the pressure in said test chamber rises substantially above its lowest level.
Claim 11
Dependent Claim 184 words
An improved method of flow testing a low-permeability gas-producing formation in a well including the following steps: (a) lowering into said well a recording pressure and temperature instrument to measure pressure and temperature as functions of time adjacent to the face of said producing formation in said well, (b) lowering into said well a test chamber closed at the bottom by a valve controllable from the surface, with the pressure in said chamber substantially lower than that of said formation, (c) sealing the space between said chamber and said well near the top of said formation, (d) measuring with said recording pressure and temperature instrument the pressure and temperature shortly after said sealing, (e) opening said controllable valve, whereby fluids from said formation flow into said test chamber under variable pressures, and (f) measuring with said recording pressure and temperature instrument the pressure and temperature as a function of time for a substantial period of time during which the pressure in said test chamber rises substantially above its lowest value, whereby the flow capacity and the skin factor of said formation can be calculated.
Claim 12
Dependent Claim 184 words
An improved method of flow testing a low-permeability gas-producing formation in a well including the following steps: (a) lowering into said well a recording pressure and temperature instrument to measure pressure and temperature as functions of time adjacent to the face of said producing formation in said well, (b) lowering into said well a test chamber closed at the bottom by a valve controllable from the surface, with the pressure in said chamber substantially lower than that of said formation, (c) sealing the space between said chamber and said well near the top of said formation, (d) measuring with said recording pressure and temperature instrument the pressure and temperature shortly after said sealing, (e) opening said controllable valve, whereby fluids from said formation flow into said test chamber under variable pressures, and (f) measuring with said recording pressure and temperature instrument the pressure and temperature as a function of time for a substantial period of time during which the pressure in said test chamber rises substantially above its lowest value, whereby the flow capacity and the skin factor of said formation can be calculated.
Claim 13
Dependent Claim 59 words
A method in accordance with claim 9, in which said formation is behind the well casing, including the steps of (g) lowering a gun perforator or the like to a position opposite said formation prior to step (b), and (h) actuating said perforator after step (c) and before step (d), to permit flow of formation fluid into said well.
Claim 14
Dependent Claim 21 words
A method in accordance with claim 10 in which said gun perforator is connected at the bottom of said test chamber.

References Cited (Backward Citations)

US2158569A Cited
US3478584A Cited
US3550445A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1987-01-02 1987-07-04 1988-01-03 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1991-01-02 1991-07-04 1992-01-03 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 1995-01-02 1995-07-04 1996-01-03 $7700.00 Window Closed / Lapsed

Assigned Categories & Tags

No categories assigned to this patent yet.

Assign Category Tag