Nuclear power plant with cooling circuit
Assignee: Kraftwerk Union AG
•
Filing: 1981-07-17
•
Granted: 1983-11-22
•
Expires: 2001-07-17
Abstract
Abstract A nuclear power plant with a metallic, circulatory cooling loop formed with welding seams and including, as components thereof, a reactor pressure vessel, a heat consumer and a pump, as well as a coolant line connecting the components to one another, and thermal insulation provided on the cooling loop, the welding seams being testable by a track-traversing testing device, including a multiplicity of fixedly installed tracks having like profile and being associated, respectively, with welding seams on the components and the cooling line, at least part of the thermal insulation being in vicinity of the tracks and being formed as removable cassettes.
Inventors
- 👤 Hans Kastl
- 👤 Georg Gugel
Bibliographic Details
Application Number
—
Jurisdiction
US
Data Source
google_patents
Last Synchronized
2026-10-24 10:38
CPC Classifications
G; G21; G21C; G21C17/00; G21C17/017; Y; Y02; Y02E; Y02E30/00; Y02E30/30
Claims Analysis
Total Claims: 14
Claim 1
Independent Claim
102 words
A nuclear power plant with a metallic, circulatory cooling loop formed with welding seams and including, as components thereof, a reactor pressure vessel, a heat consumer and a pump, as well as a coolant line connecting the components to one another, and thermal insulation provided on the cooling loop, the welding seams being testable by a track-traversing testing device, comprising a multiplicity of fixedly installed tracks having like profile and being associated, respectively, with welding seams on the components and the cooling line, at least part of the thermal insulation being in vicinity of said tracks and being formed as removable cassettes.
Claim 2
Dependent Claim
102 words
A nuclear power plant with a metallic, circulatory cooling loop formed with welding seams and including, as components thereof, a reactor pressure vessel, a heat consumer and a pump, as well as a coolant line connecting the components to one another, and thermal insulation provided on the cooling loop, the welding seams being testable by a track-traversing testing device, comprising a multiplicity of fixedly installed tracks having like profile and being associated, respectively, with welding seams on the components and the cooling line, at least part of the thermal insulation being in vicinity of said tracks and being formed as removable cassettes.
Claim 3
Dependent Claim
48 words
Nuclear power plant according to claim 1 wherein said tracks are fastened to the components and to the coolant line at respective regions thereof at which a non-removable part of the thermal insulation is located, said cassettes having releasable connections with the non-removable part of the thermal insulation.
Claim 4
Dependent Claim
59 words
Nuclear power plant according to claim 1, including stationary building parts surrounding the components and the coolant line, said tracks being fastened to said building parts and said thermally insulating cassettes being disposed between said tracks and the respective components and coolant line, the side of said tracks facing towards the respective cassettes being traversible by the testing device.
Claim 5
Dependent Claim
53 words
Nuclear power plant according to claim 1 wherein said tracks are fastened to the components and to the coolant line at respective regions thereof at which a non-removable part of the thermal insulation is located, the non-removable part of the thermal insulation being fastened to said tracks and, in turn, carrying said cassettes.
Claim 6
Dependent Claim
62 words
Nuclear power plant according to claim 1 including fixed supports for said tracks, said tracks being fastened to the components and to the coolant line at respective regions thereof at which a non-removable part of the thermal insulation is located, the non-removable part of the thermal insulation being fastened to said fixed supports for said tracks and, in turn, carrying said cassettes.
Claim 7
Dependent Claim
60 words
Nuclear power plant according to claim 1 wherein the circulatory cooling loop includes a pipe elbow and wherein at least one of said tracks is of annular construction and surrounds the pipe elbow, and further including a stationary support, said one track extending outwardly from the stationary support along a circular arc coincident with the axis of the pipe elbow.
Claim 8
Dependent Claim
25 words
Nuclear power plant according to claim 5 wherein said stationary support comprises a pivot shaft coincident with the center of curvature of said circular arc.
Claim 9
Dependent Claim
16 words
Nuclear power plant according to claim 1 wherein said tracks are provided with removable protective plates.
Claim 10
Dependent Claim
17 words
Nuclear power plant according to claim 1 including a guide for measuring cables carried by said tracks.
Claim 11
Dependent Claim
17 words
Nuclear power plant according to claim 9 wherein said guide terminates in a radiation-proof test observation station.
Claim 12
Dependent Claim
15 words
Nuclear power plant according to claim 1 wherein the testing device has magnetically adhering rollers.
Claim 13
Dependent Claim
46 words
Nuclear power plant according to claim 1 including a base carriage traversible on said tracks, an arm supported on said base carriage, the testing device being carried by said arm, a drive motor for displacing said arm, said drive motor being controlled by a programmable storage.
Claim 14
Dependent Claim
22 words
Nuclear power plant according to claim 12 wherein said base carriage has a device for programming said storage associated with said tracks.
References Cited (Backward Citations)
USPTO Annuity & Maintenance Windows
| Annuity Stage | Window Opens | Payment Deadline | Surcharge Period Until | Estimated Fee | Status |
|---|---|---|---|---|---|
| 3.5 Years (Year 4) | 1986-11-21 | 1987-05-23 | 1987-11-22 | $2000.00 | Window Closed / Lapsed |
| 7.5 Years (Year 8) | 1990-11-21 | 1991-05-23 | 1991-11-22 | $3760.00 | Window Closed / Lapsed |
| 11.5 Years (Year 12) | 1994-11-21 | 1995-05-23 | 1995-11-22 | $7700.00 | Window Closed / Lapsed |