← Back to Patent Explorer
US4412760A Expired / Lapsed US ⏱️ 0.0 years remaining

Method for producing a structure having cohesion by means of a material comprising non-coherent solid particles

Assignee: Societe Civile des Brevets Henri Vidal
•
Filing: 1981-02-11
•
Granted: 1983-11-01
•
Expires: 2001-02-11
📄 Original PDF 🌐 Google Patents 🔄 Sync Now

Abstract

Abstract There is constructed around pillars of a mine chamber on the ground a rectangular enclosure which is defined by superimposed layers of U-section elements. The concavity of the latter faces inwardly of the enclosure. A pulverulent material is poured by a hydraulic filling method into the enclosure. This pulverent material preferably comprises light fine ash having hydraulic properties. Owing to the reinforcements embedded in the mass, the structure initially behaves as stabilized earth, but, in the end, the material sets and becomes coherent so that finally the structure has a lean concrete character.

Inventors

  • 👤 Henri Vidal

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-11-08 06:43
CPC Classifications
E; E02; E02D; E02D29/00; E02D29/02; E02D29/0258; E02D29/0275; E21; E21F; E21F15/00; E21F15/08

Claims Analysis

Total Claims: 27
Claim 1
Independent Claim 156 words
A method for consolidating at least one pillar of ground against collapse, said method comprising the steps of constructing around and in spaced relation to said at least one pillar a continuous wall of superimposed cladding elements having integral reinforcing means extending from said cladding elements toward said at least one pillar in a plurality of substantially horizontal vertically spaced-apart planes, filling the space between said wall and said at least one pillar with material including substantially non-coherent solid particles to frictionally contact said reinforcing means and constitute a frictionally stabilized structure that immediately protects said at least one pillar, said material including additional means which when mixed with said particles cause said material to set and become a cohesive structure, the time required for the setting of said material and the quality of said particles and said additional means of said material are not critical for the desired consolidation of said at least one pillar.
Claim 2
Independent Claim 156 words
A method for consolidating at least one pillar of ground against collapse, said method comprising the steps of constructing around and in spaced relation to said at least one pillar a continuous wall of superimposed cladding elements having integral reinforcing means extending from said cladding elements toward said at least one pillar in a plurality of substantially horizontal vertically spaced-apart planes, filling the space between said wall and said at least one pillar with material including substantially non-coherent solid particles to frictionally contact said reinforcing means and constitute a frictionally stabilized structure that immediately protects said at least one pillar, said material including additional means which when mixed with said particles cause said material to set and become a cohesive structure, the time required for the setting of said material and the quality of said particles and said additional means of said material are not critical for the desired consolidation of said at least one pillar.
Claim 3
Dependent Claim 17 words
A method according to claim 1, wherein the material comprises solid particles having pozzolanic or hydraulic properties.
Claim 4
Dependent Claim 19 words
A method according to claim 2, wherein the solid particles having pozzolanic or hydraulic properties are based on ash.
Claim 5
Dependent Claim 19 words
A method according to claim 2, wherein the solid particles having pozzolanic or hydraulic properties are based on slag.
Claim 6
Dependent Claim 19 words
A method according to claim 2, wherein the solid particles having pozzolanic or hydraulic properties are of volcanic origin.
Claim 7
Dependent Claim 20 words
A method according to claim 1, wherein said additional means include a product of addition which is capable of setting.
Claim 8
Dependent Claim 13 words
A method according to claim 6, wherein said product of addition is lime.
Claim 9
Dependent Claim 13 words
A method according to claim 6, wherein said product of addition is cement.
Claim 10
Dependent Claim 14 words
A method according to claim 6, wherein said product of addition is calcium chloride.
Claim 11
Dependent Claim 27 words
A method according to claim 6, wherein the product of addition comprises a substance which, after having been employed, changes and acquires the properties of an adhesive.
Claim 12
Dependent Claim 27 words
A method according to claim 6, wherein the product of addition comprises a substance which, after having been employed, changes and acquires the properties of a binder.
Claim 13
Dependent Claim 25 words
A method according to claim 6, 7, 8, 9, 10 or 11, wherein the product of addition is employed in the form of a solution.
Claim 14
Dependent Claim 25 words
A method according to claim 6, 7, 8, 9, 10 or 11, wherein the product of addition is employed in the form of a suspension.
Claim 15
Dependent Claim 25 words
A method according to claim 6, 7, 8, 9, 10 or 11, wherein the product of addition is employed in the form of an emulsion.
Claim 16
Independent Claim 26 words
A method according to any one of the claims 1 to 6, 10 and 11, wherein said material is placed in position by a hydraulic filling.
Claim 17
Independent Claim 46 words
A method according to any one of the claims 1 to 6, 10 and 11, wherein the cladding of the facing wall means is obtained by horizontally juxtaposing and superimposing U-section elements having a concavity which faces inwardly of the structure and flanges which constitute reinforcements.
Claim 18
Independent Claim 48 words
A method according to any one of the claims 1 to 6, 10 and 11, wherein the cladding of the wall is obtained by horizontally juxtaposing and superimposing U-section elements having a concavity which faces inwardly of the structure and flanges which constitute reinforcements and support further reinforcements.
Claim 19
Independent Claim 24 words
A method according to any one of the claims 1 to 6, 10 and 11, wherein the reinforcements are formed by relatively flexible bands.
Claim 20
Dependent Claim 12 words
A method according to claim 16, wherein said flanges are wide flanges.
Claim 21
Independent Claim 113 words
A method for working a mine by the bord-and-pillar method, comprising constructing, around a group of pillars, on a foot wall of a mine chamber, an enclosure having walls which define a closed contour, said walls being obtained by horizontal juxtaposition and superimposition of U-section elements whose concavity faces inwardly of the enclosure and whose flanges form reinforcements, and producing inside the enclosure a hydraulic fill comprising initially pulverulent non-coherent solid particles and additional means which, when mixed with said particles, produce a setting of said fill over a non-critical period of time, the fill frictionally engaging the reinforcements to initially consolidate the pillars and ultimately consolidating the pillars as a cohesive mass.
Claim 22
Independent Claim 113 words
A method for working a mine by the bord-and-pillar method, comprising constructing, around a group of pillars, on a foot wall of a mine chamber, an enclosure having walls which define a closed contour, said walls being obtained by horizontal juxtaposition and superimposition of U-section elements whose concavity faces inwardly of the enclosure and whose flanges form reinforcements, and producing inside the enclosure a hydraulic fill comprising initially pulverulent non-coherent solid particles and additional means which, when mixed with said particles, produce a setting of said fill over a non-critical period of time, the fill frictionally engaging the reinforcements to initially consolidate the pillars and ultimately consolidating the pillars as a cohesive mass.
Claim 23
Independent Claim 120 words
A method for working a mine by the bord-and-pillar method, comprising constructing, around a group of pillars, on a foot wall of a mine chamber, an enclosure having walls which define a closed contour, said walls being obtained by horizontal justaposition and superimposition of U-section elements whose concavity faces inwardly of the enclosure and whose flanges support reinforcements in the form of relatively flexible bands, and producing inside the enclosure a hydraulic fill comprising initially pulverulent non-coherent solid particles and additional means which, when mixed with said particles, produce a setting of said fill over a non-critical period of time, the fill frictionally engaging the reinforcements to initially consolidate the pillars and ultimately consolidating the pillars as a cohesive mass.
Claim 24
Independent Claim 120 words
A method for working a mine by the bord-and-pillar method, comprising constructing, around a group of pillars, on a foot wall of a mine chamber, an enclosure having walls which define a closed contour, said walls being obtained by horizontal justaposition and superimposition of U-section elements whose concavity faces inwardly of the enclosure and whose flanges support reinforcements in the form of relatively flexible bands, and producing inside the enclosure a hydraulic fill comprising initially pulverulent non-coherent solid particles and additional means which, when mixed with said particles, produce a setting of said fill over a non-critical period of time, the fill frictionally engaging the reinforcements to initially consolidate the pillars and ultimately consolidating the pillars as a cohesive mass.
Claim 25
Dependent Claim 15 words
A method according to claim 20 or 21, wherein said contour is a rectangular contour.
Claim 26
Independent Claim 123 words
A method for producing a structure which sets over a non-critical period of time, said method comprising in combination constructing an enclosure comprising a continuous wall of superimposed cladding elements which are integral with reinforcing means which extend from said cladding elements inwardly of said enclosure substantially in a plurality of substantially horizontal vertically spaced-apart planes, filling the space within said enclosure with a material comprising substantially non-coherent solid particles that frictionally contact said reinforcing means and initially constitute a stabilized structure owing to the action of said friction, said material including additional means mixed with said particles that causes said material to set, said noncriticality being due to the immediate stabilizing effect of said friction between said material and said reinforcing means.
Claim 27
Independent Claim 123 words
A method for producing a structure which sets over a non-critical period of time, said method comprising in combination constructing an enclosure comprising a continuous wall of superimposed cladding elements which are integral with reinforcing means which extend from said cladding elements inwardly of said enclosure substantially in a plurality of substantially horizontal vertically spaced-apart planes, filling the space within said enclosure with a material comprising substantially non-coherent solid particles that frictionally contact said reinforcing means and initially constitute a stabilized structure owing to the action of said friction, said material including additional means mixed with said particles that causes said material to set, said noncriticality being due to the immediate stabilizing effect of said friction between said material and said reinforcing means.

References Cited (Backward Citations)

CA567320A Cited
US3570253A Cited
US3376146A Cited
US3340693A Cited
US3557876A Cited
US3713489A Cited
US3876005A Cited
US3799787A Cited
US4059963A Cited
US4309059A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1986-10-31 1987-05-02 1987-11-01 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1990-10-31 1991-05-02 1991-11-01 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 1994-10-31 1995-05-02 1995-11-01 $7700.00 Window Closed / Lapsed

Assigned Categories & Tags

No categories assigned to this patent yet.

Assign Category Tag