Method and apparatus for plastifying and tearing up of damaged roadsurfaces and covers

Assignee: Individual
•
Filing: 1980-05-05
•
Granted: 1982-06-22
•
Expires: 2000-05-05
📄 Original PDF 🌐 Google Patents 🔄 Sync Now

Abstract

Abstract In a method for resurfacing a road, the road surface is first plastified and broken-up by first and second separable devices. The broken-up material is immediately distributed on the road surface by the second device, whereby the broken-up material is simultaneously rearranged and profiled or contoured without the introduction of fresh asphalt or bituminous material at this point of time. A road surfacing or repaver apparatus forming a third separate device then applies fresh asphalt or bituminous material onto the broken-up distributed, rearranged and profiled top surface of the road. Preferably, two distributions of the broken-up material are employed prior to the asphalt application and compaction of the broken-up and distributed material and the new asphalt material. A truck supplies fresh asphalt or bituminous material to the repaver.

Inventors

  • 👤 Walter Schoelkopf

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-10-24 05:16
CPC Classifications
E; E01; E01C; E01C23/00; E01C23/06; E01C23/12; E01C23/121; E01C23/065; E01C23/14; E01C7/00; E01C7/08; E01C7/18; E01C7/187; E01C7/35; E01C7/353

Claims Analysis

Total Claims: 9
Claim 1
Independent Claim 264 words
A method for resurfacing an old blacktop road surface by means of first, second, and third separate, mobile units performing a respective first, second, and third group of steps, wherein said first group performed by said first, separate mobile unit comprises the steps of: (a) providing, by means of a single heater, a single heat application to the old road surface for heating and plastifying the old road surface to a given depth (17), (b) breaking up only a top portion (18) of the heated old road surface to produce a broken-up material layer having a thickness substantially less than said given depth (17) of heated old road surface, (c) rearranging and distributing the broken-up material on the remaining still heated but otherwise undisturbed old road surface to produce a first profiled layer (19) of broken-up material, wherein said second separate mobile unit performs the steps of: (d) supplying fresh asphalt material into the third, separate mobile unit, and wherein said third group performed by said third, separate mobile unit comprises the steps of: (e) distributing fresh asphalt material on top of said profiled, broken-up layer (19) over the entire working width of the third unit while said road surface and the layer (19) of broken-up material are still sufficiently plastified from said single heat application, and (f) immediately profiling and compacting said fresh asphalt material as a top layer (25) together with said broken-up material layer (19) whereby the still heated but otherwise undisturbed old road surface enters into an intimate bond with the layers (19) and (25) in a single heat application.
Claim 2
Independent Claim 264 words
A method for resurfacing an old blacktop road surface by means of first, second, and third separate, mobile units performing a respective first, second, and third group of steps, wherein said first group performed by said first, separate mobile unit comprises the steps of: (a) providing, by means of a single heater, a single heat application to the old road surface for heating and plastifying the old road surface to a given depth (17), (b) breaking up only a top portion (18) of the heated old road surface to produce a broken-up material layer having a thickness substantially less than said given depth (17) of heated old road surface, (c) rearranging and distributing the broken-up material on the remaining still heated but otherwise undisturbed old road surface to produce a first profiled layer (19) of broken-up material, wherein said second separate mobile unit performs the steps of: (d) supplying fresh asphalt material into the third, separate mobile unit, and wherein said third group performed by said third, separate mobile unit comprises the steps of: (e) distributing fresh asphalt material on top of said profiled, broken-up layer (19) over the entire working width of the third unit while said road surface and the layer (19) of broken-up material are still sufficiently plastified from said single heat application, and (f) immediately profiling and compacting said fresh asphalt material as a top layer (25) together with said broken-up material layer (19) whereby the still heated but otherwise undisturbed old road surface enters into an intimate bond with the layers (19) and (25) in a single heat application.
Claim 3
Dependent Claim 45 words
The method of claim 1, wherein said step (c) of rearranging and distributing said broken-up material on said still hot but otherwise undisturbed old road surface is performed directly following said step (b), whereby said broken-up material is not picked up from said road surface.
Claim 4
Dependent Claim 78 words
The method of claim 1, wherein said step (b) of breaking up comprises drawing rows of tearing-up teeth along said road surface to a thickness (18) which is substantially less than said given depth (17), whereby the plastified road surface material is broken up and partially rearranged on said road surface by said tearing-up teeth, and further rearranging and distributing said broken-up material so that broken-up portions of material will take up different positions on the road surface.
Claim 5
Dependent Claim 26 words
The method of claim 1, further comprising profiling said broken-up layer (19) on said still hot road surface prior to distributing said fresh asphalt material thereon.
Claim 6
Dependent Claim 52 words
The method of claim 1, wherein said step of rearranging and distributing said broken-up material comprises rotating a pair of worms through said broken-up material following the breaking-up thereof, said worms being staggered laterally with respect to said road surface and each having a length of substantially one half the working width.
Claim 7
Dependent Claim 31 words
The method of claim 1, wherein said step of rearranging and distributing said broken-up material comprises moving a distributor continuously back and forth over the working width of said road surface.
Claim 8
Dependent Claim 25 words
The method of claim 1, further comprising drawing a screeding bar along said broken-up layer prior to the application of said fresh asphalt material thereto.
Claim 9
Dependent Claim 25 words
The method of claim 1, further comprising scratching said broken-up layer with means (26) on said third unit prior to distributing said fresh asphalt material.

References Cited (Backward Citations)

US1952452A Cited
US2053709A Cited
US2199884A Cited
US2328888A Cited
US2394017A Cited
US2747475A Cited
US3361042A Cited
US4018540A Cited
US4129398A Cited
US4124325A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1985-06-21 1985-12-21 1986-06-22 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1989-06-21 1989-12-21 1990-06-22 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 1993-06-21 1993-12-21 1994-06-22 $7700.00 Window Closed / Lapsed

Assigned Categories & Tags

No categories assigned to this patent yet.

Assign Category Tag