Claims Analysis
Total Claims: 9
Claim 1
Independent Claim
199 words
An improvement to the method of making structures from at least one workpiece wherein said at least one workpiece is contained about its periphery between a pair of dies creating an actual gap therebetween, and said pair of dies is contained between a pair of non-inflatable platens, after which said at least one workpiece is formed within said pair of dies by fluid under pressure, said improvement comprising: providing force adjustment means to adjust the force applied by said pair of dies to said at least one workpiece for varying said actual gap between said pair of dies; sensing the actual gap between said pair of dies during forming, and providing a first output signal proportional to said actual gap; providing a second output signal proportional to a preferred gap between said pair of dies that is produced when said force is the minimum amount necessary for said step of forming said at least one workpiece; and controlling said force adjustment means using said first and second signals such that the actual gap substantially equals said preferred gap so that said minimum force is applied to said pair of dies during said steps of forming at least one workpiece.
Claim 2
Dependent Claim
199 words
An improvement to the method of making structures from at least one workpiece wherein said at least one workpiece is contained about its periphery between a pair of dies creating an actual gap therebetween, and said pair of dies is contained between a pair of non-inflatable platens, after which said at least one workpiece is formed within said pair of dies by fluid under pressure, said improvement comprising: providing force adjustment means to adjust the force applied by said pair of dies to said at least one workpiece for varying said actual gap between said pair of dies; sensing the actual gap between said pair of dies during forming, and providing a first output signal proportional to said actual gap; providing a second output signal proportional to a preferred gap between said pair of dies that is produced when said force is the minimum amount necessary for said step of forming said at least one workpiece; and controlling said force adjustment means using said first and second signals such that the actual gap substantially equals said preferred gap so that said minimum force is applied to said pair of dies during said steps of forming at least one workpiece.
Claim 3
Dependent Claim
44 words
In the method of claim 1, wherein: said adjustment means comprises an inflatable platen between one of said pair of dies and one of said non-inflatable platens; and said step of controlling said inflatable platen comprises controlling the pressure level within said inflatable platen.
Claim 4
Dependent Claim
77 words
The method of claim 2, wherein said step of controlling said pressure level within said inflatable platen comprises: providing a source of pressurized fluid and a conduit coupling said fluid to said inflatable platen; supplying said first and second signals to the input of a controller; applying an output signal of said controller to control a valve means in said conduit to control said pressure within said inflatable platen in response to said output of said controller.
Claim 5
Dependent Claim
27 words
The method of claim 1 or 2 or 3 including the additional step of providing a buffer platen between said inflatable platen and said pair of dies.
Claim 6
Dependent Claim
242 words
In the apparatus for forming a structure comprising a pair of dies adapted to contained at least one workpiece about its periphery, said at least one workpiece creating an actual gap between said pair of dies, a pair of non-inflatable platens adapted to apply a clamping force to said pair of dies and means to apply a fluid under pressure to said at least one workpiece to form said at least one workpiece against at least one of said pair of dies, the improvement comprising: force adjustment means mounted between one of said pair of dies and one of said pair of non-inflatable platens adapted to maintain the force applied to said pair of dies and at least one workpiece for varying said actual gap between said pair of dies; a sensor mounted within said actual gap adapted to sense changes in the dimensions of said actual gap providing a first output signal proportional to the dimensions of said actual gap during said forming of said structure; a signal generator adapted to provide a second output signal proportional to a preferred gap dimension that is produced when said force is the minimum amount necessary for forming said at least one workpiece; and control means coupled to and adapted to regulate said force adjusting means, and coupled to said sensor and said signal generator, adapted to use said first and second output signals such that the actual gap substantially equals said preferred gap.
Claim 7
Dependent Claim
242 words
In the apparatus for forming a structure comprising a pair of dies adapted to contained at least one workpiece about its periphery, said at least one workpiece creating an actual gap between said pair of dies, a pair of non-inflatable platens adapted to apply a clamping force to said pair of dies and means to apply a fluid under pressure to said at least one workpiece to form said at least one workpiece against at least one of said pair of dies, the improvement comprising: force adjustment means mounted between one of said pair of dies and one of said pair of non-inflatable platens adapted to maintain the force applied to said pair of dies and at least one workpiece for varying said actual gap between said pair of dies; a sensor mounted within said actual gap adapted to sense changes in the dimensions of said actual gap providing a first output signal proportional to the dimensions of said actual gap during said forming of said structure; a signal generator adapted to provide a second output signal proportional to a preferred gap dimension that is produced when said force is the minimum amount necessary for forming said at least one workpiece; and control means coupled to and adapted to regulate said force adjusting means, and coupled to said sensor and said signal generator, adapted to use said first and second output signals such that the actual gap substantially equals said preferred gap.
Claim 8
Dependent Claim
77 words
The apparatus of claim 5 wherein said force adjustment means comprises an inflatable platen, and said control means comprises: a source of pressurized fluid; a conduit coupling said fluid to said inflatable platen; a valve means mounted in said conduit for controlling the pressure level within said platen; a controller adapted to receive said first and second output signals and to provide an input signal to said valve means to control said pressure within said inflatable platen.
Claim 9
Dependent Claim
24 words
The apparatus of claim 5 or 6 wherein said apparatus further includes a buffer platen between said inflatable platen and said pair of dies.