Combined gas-steam power plant with a fuel gasification device
Assignee: Kraftwerk Union AG
•
Filing: 1979-08-08
•
Granted: 1981-02-17
•
Expires: 1999-08-08
Abstract
Abstract Combined gas-steam power plant, including a device for carrying out a gasification reaction at overpressure between oxygen and fuel fed to the gasification device, a heat exchanger and a charged steam generator disposed down stream of the gasification device in flow direction of fuel gas generated by the gasification device, a gas turbine receiving a flue gas stream from the steam generator, an air decomposition device having a first outlet line carrying oxygen to the gasification device and a second outlet line carrying nitrogen through the heat exchanger to the gas stream between the steam generator and gas turbine.
Inventors
- 👤 Hermann Bruckner
- 👤 Werner Emsperger
Bibliographic Details
Application Number
—
Jurisdiction
US
Data Source
google_patents
Last Synchronized
2026-11-05 09:09
CPC Classifications
F; F25; F25J; F25J3/00; F25J3/02; F25J3/04; F25J3/04006; F25J3/04109; F25J3/04145; C; C01; C01B; C01B3/00; C01B3/02; C01B3/32; C01B3/34; C01B3/36; F01; F01K; F01K23/00; F01K23/02; F01K23/06; F01K23/067; F01K23/068; F02; F02C; F02C6/00; F02C6/04; F02C6/10; F25J3/04012; F25J3/04018; F25J3/0403; F25J3/04036; F25J3/04115; F25J3/04127; F25J3/04521; F25J3/04527; F25J3/04539; F25J3/04545; F25J3/04563; F25J3/04575; F25J3/04581; F25J3/04593; F25J3/046; F25J3/04612; F25J3/04618; F25J2240/00; F25J2240/90; Y; Y02; Y02E; Y02E20/00; Y02E20/16; Y02E20/18
Claims Analysis
Total Claims: 5
Claim 1
Independent Claim
98 words
Combined gas-steam power plant, comprising means for carrying out a gasification reaction at overpressure between oxygen and fuel fed to said gasification means, a heat exchanger and a charged steam generator disposed down stream of said gasification means in flow direction of fuel gas generated by said gasification means, a gas turbine receiving a flue gas stream from said steam generator, an air decomposition device having a first outlet line carrying oxygen to said gasification means and a second outlet line carrying nitrogen through said heat exchanger to said gas stream between said steam generator and gas turbine.
Claim 2
Dependent Claim
98 words
Combined gas-steam power plant, comprising means for carrying out a gasification reaction at overpressure between oxygen and fuel fed to said gasification means, a heat exchanger and a charged steam generator disposed down stream of said gasification means in flow direction of fuel gas generated by said gasification means, a gas turbine receiving a flue gas stream from said steam generator, an air decomposition device having a first outlet line carrying oxygen to said gasification means and a second outlet line carrying nitrogen through said heat exchanger to said gas stream between said steam generator and gas turbine.
Claim 3
Dependent Claim
32 words
Power plant according to claim 1, including a compressor driven by said gas turbine, and means for delivering air to said air decomposition device from a point down stream of said compressor.
Claim 4
Dependent Claim
49 words
Power plant according to claim 1, including a gas purification device disposed down stream of said heat exchanger in flow direction of the fuel gas, and a plurality of further heat exchangers disposed between said first-mentioned heat exchanger and said gas purification device for step-wise cooling of fuel gases.
Claim 5
Dependent Claim
34 words
Power plant according to claim 1, including an expansion turbine disposed down stream of said purification device, and further compressors driven by said expansion turbine and disposed in said first and second outlet lines.
References Cited (Backward Citations)
USPTO Annuity & Maintenance Windows
| Annuity Stage | Window Opens | Payment Deadline | Surcharge Period Until | Estimated Fee | Status |
|---|---|---|---|---|---|
| 3.5 Years (Year 4) | 1984-02-17 | 1984-08-18 | 1985-02-17 | $2000.00 | Window Closed / Lapsed |
| 7.5 Years (Year 8) | 1988-02-17 | 1988-08-18 | 1989-02-17 | $3760.00 | Window Closed / Lapsed |
| 11.5 Years (Year 12) | 1992-02-17 | 1992-08-18 | 1993-02-17 | $7700.00 | Window Closed / Lapsed |