Method for bringing a well under control
Assignee: Schlumberger Technology Corp
•
Filing: 1978-01-06
•
Granted: 1979-03-13
•
Expires: 1998-01-06
Abstract
Abstract An improved method is disclosed for bringing a well under control by injecting a well-controlling fluid into an adjacent well, through the subterranean formation, and thence into the out-of-control well, wherein the improvement lies in a particular sequence of steps whereby fluid communication between the boreholes is established or improved.
Inventors
- 👤 Joseph P. Pavlich
Bibliographic Details
Application Number
—
Jurisdiction
US
Data Source
google_patents
Last Synchronized
2026-11-07 11:11
CPC Classifications
E; E21; E21B; E21B43/00; E21B43/25; E21B43/26; E21B33/00; E21B33/10; E21B33/13; E21B33/138; E21B43/16; E21B43/17; E21B43/261
Claims Analysis
Total Claims: 5
Claim 1
Independent Claim
200 words
In a method for bringing under control a first well which penetrates a subterranean formation and which is producing fluids at an uncontrolled rate, wherein a well-controlling fluid is indirectly injected into the first well by injecting the fluid into a second well, forcing said fluid through the formation separating the two wells, and thence into the first well until the first well is brought under control, and wherein prior to injecting said well-controlling fluid into the second well, the formation between said wells is fractured to establish or improve fluid communication between the wells, said fracturing operation including injecting at least two stages of a viscous non-Newtonian fracturing fluid carrying a solid into a fracture in said formation at a fracturing rate and pressure, and temporarily reducing said fluid injection rates and pressures at least once between the first and the last of said stages to close the fracture at least partially, the improvement which comprises: immediately preceding the temporary rate and pressure reducing step, injecting in sequence both (a) a non-Newtonian viscous fracturing fluid substantially free of solids and (b) an inefficient penetrating fluid substantially free of solids, all of said injections being made via the second well.
Claim 2
Dependent Claim
200 words
In a method for bringing under control a first well which penetrates a subterranean formation and which is producing fluids at an uncontrolled rate, wherein a well-controlling fluid is indirectly injected into the first well by injecting the fluid into a second well, forcing said fluid through the formation separating the two wells, and thence into the first well until the first well is brought under control, and wherein prior to injecting said well-controlling fluid into the second well, the formation between said wells is fractured to establish or improve fluid communication between the wells, said fracturing operation including injecting at least two stages of a viscous non-Newtonian fracturing fluid carrying a solid into a fracture in said formation at a fracturing rate and pressure, and temporarily reducing said fluid injection rates and pressures at least once between the first and the last of said stages to close the fracture at least partially, the improvement which comprises: immediately preceding the temporary rate and pressure reducing step, injecting in sequence both (a) a non-Newtonian viscous fracturing fluid substantially free of solids and (b) an inefficient penetrating fluid substantially free of solids, all of said injections being made via the second well.
Claim 3
Dependent Claim
43 words
The method of claim 1 including as a preliminary step in the fracturing operation, prior to injecting the first stage of solids-carrying fluid, injecting a fracturing fluid into the formation at a rate and pressure sufficient to initiate a fracture in said formation.
Claim 4
Dependent Claim
26 words
The method of claim 1 wherein said temporary rate and pressure reducing step comprises continuing to inject said inefficient penetrating fluid, but at a matrix rate.
Claim 5
Dependent Claim
23 words
The method of claim 1 wherein the well-controlling fluid is selected from the group consisting of drilling muds, cement slurries, or heavy brine.
References Cited (Backward Citations)
US3003557A
Cited
US3179172A
Cited
US3642068A
Cited
US3592266A
Cited
US3710865A
Cited
US3933205A
Cited
US3948325A
Cited
USPTO Annuity & Maintenance Windows
| Annuity Stage | Window Opens | Payment Deadline | Surcharge Period Until | Estimated Fee | Status |
|---|---|---|---|---|---|
| 3.5 Years (Year 4) | 1982-03-12 | 1982-09-11 | 1983-03-13 | $2000.00 | Window Closed / Lapsed |
| 7.5 Years (Year 8) | 1986-03-12 | 1986-09-11 | 1987-03-13 | $3760.00 | Window Closed / Lapsed |
| 11.5 Years (Year 12) | 1990-03-12 | 1990-09-11 | 1991-03-13 | $7700.00 | Window Closed / Lapsed |