← Back to Patent Explorer
US4132082A Expired / Lapsed US ⏱️ 0.0 years remaining

Piling

Assignee: Individual
•
Filing: 1976-11-26
•
Granted: 1979-01-02
•
Expires: 1996-11-26
📄 Original PDF 🌐 Google Patents 🔄 Sync Now

Abstract

Abstract A concrete pile fitted with a special slightly tapered concrete tip of larger area. The tip has a central open socket for receiving concrete poured in after the pile is in place.

Inventors

  • 👤 Stanley Merjan

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-10-29 04:35
CPC Classifications
E; E02; E02D; E02D13/00; E02D27/00; E02D27/10; E02D27/12; E02D27/14; E02D5/00; E02D5/22; E02D5/34; E02D5/38; E02D5/44; E02D5/72

Claims Analysis

Total Claims: 7
Claim 1
Independent Claim 128 words
A tip for a pile having a tubular metal stem, which stem is filled with concrete after the pile is driven, said tip being of reinforced concrete and having an upper central cavity adapted to receive said filling of concrete, said tip being tapered to increase in diameter from the bottom upwards, the maximum cross-sectional area of the tip being about 5 to 15 times the cross-sectional area of the stem, the taper being less than about 3 inches per foot and the axial height of said tip being at least about 2 feet, and in which said tip has an upper central tubular liner rigidly embedded in the concrete of said tip and to which the stem is adapted to be attached before said pile is driven.
Claim 2
Dependent Claim 128 words
A tip for a pile having a tubular metal stem, which stem is filled with concrete after the pile is driven, said tip being of reinforced concrete and having an upper central cavity adapted to receive said filling of concrete, said tip being tapered to increase in diameter from the bottom upwards, the maximum cross-sectional area of the tip being about 5 to 15 times the cross-sectional area of the stem, the taper being less than about 3 inches per foot and the axial height of said tip being at least about 2 feet, and in which said tip has an upper central tubular liner rigidly embedded in the concrete of said tip and to which the stem is adapted to be attached before said pile is driven.
Claim 3
Dependent Claim 46 words
A tip as in claim 1 in which said liner is a short length of corrugated metal shell and said cavity is of sufficient size to house a driving mandrel whereby the force of the pile driving hammer is transmitted to the bottom of said cavity.
Claim 4
Dependent Claim 41 words
A tip as in claim 1 in which said liner is a short length of pipe of sufficient strength to transmit pile driving forces to said tip from a connected length of pipe piling serving as the stem of said pile.
Claim 5
Dependent Claim 10 words
A tip as in claim 1, of substantially circular cross-section.
Claim 6
Dependent Claim 147 words
A tip for a pile having a tubular metal stem, which stem is filled with concrete after the pile is driven, said tip being of reinforced concrete and having an upper central cavity adapted to receive said filling of concrete, said tip being tapered to increase in diameter from the bottom upwards, the maximum cross-sectional area of the tip being about 5 to 15 times the cross-sectional area of the stem, the taper being less than about 3 inches per foot and the axial height of said tip being at least about 2 feet and in which the base of said tip has a diameter of at least 8 inches, the axial height of said tip is at least 2 feet and at least 1 foot greater than the depth of said cavity, the depth of said cavity being about 0.4 to 0.6 times said axial height.
Claim 7
Dependent Claim 147 words
A tip for a pile having a tubular metal stem, which stem is filled with concrete after the pile is driven, said tip being of reinforced concrete and having an upper central cavity adapted to receive said filling of concrete, said tip being tapered to increase in diameter from the bottom upwards, the maximum cross-sectional area of the tip being about 5 to 15 times the cross-sectional area of the stem, the taper being less than about 3 inches per foot and the axial height of said tip being at least about 2 feet and in which the base of said tip has a diameter of at least 8 inches, the axial height of said tip is at least 2 feet and at least 1 foot greater than the depth of said cavity, the depth of said cavity being about 0.4 to 0.6 times said axial height.

References Cited (Backward Citations)

US1778925A Cited
US2065507A Cited
US2187318A Cited
US3751931A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1982-01-01 1982-07-03 1983-01-02 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1986-01-01 1986-07-03 1987-01-02 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 1990-01-01 1990-07-03 1991-01-02 $7700.00 Window Closed / Lapsed

Assigned Categories & Tags

No categories assigned to this patent yet.

Assign Category Tag