US4100714A
Expired / Lapsed
US
⏱️ 0.0 years remaining
Method of positioning and supporting a machine
Assignee: Individual
•
Filing: 1976-09-22
•
Granted: 1978-07-18
•
Expires: 1996-09-22
Abstract
Abstract A method of positioning and supporting a large industrial machine or other object on its foundation comprising placing hydraulic jacking units between the machine and the foundation, pressurizing the jacking units to move the object relative to the foundation to a selected position, maintaining the liquid in the jacking units under pressure so as to support the machine in its selected position, and pouring a hardenable grouting mixture around the jacking units to fix them in their selected positions.
Inventors
- 👤 Morris Randall Stith, Jr.
Bibliographic Details
Application Number
—
Jurisdiction
US
Data Source
google_patents
Last Synchronized
2026-11-07 02:15
CPC Classifications
F; F16; F16M; F16M7/00; B; B23; B23Q; B23Q1/00; B23Q1/0054; B66; B66F; B66F3/00; B66F3/24; Y; Y10; Y10T; Y10T29/00; Y10T29/49; Y10T29/49826; Y10T29/49888
Claims Analysis
Total Claims: 11
Claim 1
Independent Claim
246 words
The method of positioning and supporting an object, such as a large machine or other structure, on a foundation comprising the steps of: placing a plurality of hydraulic jacking units between the foundation and the object, each of said units having a first member engageable with the object to be positioned and supported, a base member engageable with the foundation, and piston and cylinder means between the first member and the base member so that upon the application of hydraulic pressure to the piston and cylinder means, the first member moves relative to the base member, said first member having a generally downwardly facing surface; introducing a liquid under pressure into each of said jacking units to move the object relative to the foundation to a selected position, said liquid constituting a hydraulic working fluid; maintaining said liquid in each of said jacking units under pressure so as to support said object in its selected position; introducing a flowable, hardenable material, such as grout, around the jacking units with the hardenable material filling the space between said downwardly facing surface and said foundation; effecting the hardening of said hardenable material for fixing said jacking units in their selected positions; and relieving said pressure from said liquid within said jacking units after said hardenable material has hardened so as to insure that substantially all of the loading applied to the jacking units by said object is carried by said hardenable material bearing against said downwardly facing surface.
Claim 2
Independent Claim
246 words
The method of positioning and supporting an object, such as a large machine or other structure, on a foundation comprising the steps of: placing a plurality of hydraulic jacking units between the foundation and the object, each of said units having a first member engageable with the object to be positioned and supported, a base member engageable with the foundation, and piston and cylinder means between the first member and the base member so that upon the application of hydraulic pressure to the piston and cylinder means, the first member moves relative to the base member, said first member having a generally downwardly facing surface; introducing a liquid under pressure into each of said jacking units to move the object relative to the foundation to a selected position, said liquid constituting a hydraulic working fluid; maintaining said liquid in each of said jacking units under pressure so as to support said object in its selected position; introducing a flowable, hardenable material, such as grout, around the jacking units with the hardenable material filling the space between said downwardly facing surface and said foundation; effecting the hardening of said hardenable material for fixing said jacking units in their selected positions; and relieving said pressure from said liquid within said jacking units after said hardenable material has hardened so as to insure that substantially all of the loading applied to the jacking units by said object is carried by said hardenable material bearing against said downwardly facing surface.
Claim 3
Dependent Claim
32 words
The method of claim 1 which includes the further step of securing the object to the foundation after the object is supported in its selected position and the hardenable material has hardened.
Claim 4
Dependent Claim
42 words
The method of claim 2 wherein the step of securing the object to the foundation comprises bolting the object to the foundation immediately adjacent at least some of said jacking units thereby to prevent relative movement between the object and the foundation.
Claim 5
Dependent Claim
23 words
The method of claim 1 which further comprises the preliminary step of forming recesses in said foundation for reception of said jacking units.
Claim 6
Dependent Claim
55 words
The method of claim 1 wherein said hardenable material is an epoxy resin mixed with a suitable hardening agent or catalyst and with an aggregate to form grout, and wherein said step of effecting hardening of said hardenable material comprises permitting said grout to stand for a time sufficient to permit said resin to harden.
Claim 7
Dependent Claim
23 words
The method of claim 5 which further comprises heating the grout so as to reduce the time required for the resin to harden.
Claim 8
Independent Claim
252 words
The method of positioning and supporting an object, such as a large machine or other structure, on a foundation comprising the steps of: placing a plurality of hydraulic jacking units between the foundation and the object, each of said units having a generally downwardly facing surface; introducing a liquid under pressure into each of said jacking units to move the object relative to the foundation to a selected position, said liquid constituting a hydraulic working fluid; maintaining said liquid in each of said jacking units under pressure so as to support said object in its selected position; introducing a flowable, hardenable material, such as grout, around the jacking units with the hardenable material filling the space between said downwardly facing surface and said foundation; effecting the hardening of said hardenable material for fixing said jacking units in their selected positions with the weight of said object being substantially supported by said hardenable material engaging said downwardly facing surface; limiting the static loading of said hardenable material engaging said downwardly facing surface to about 750 psi; and subsequent to a period of use in the event said jacking units become loose in said hardenable material and thereby fail to properly support said object, introducing additional liquid under pressure into said jacking units to move said object to said selected position, and then introducing other hardenable material between said jacking units and said previously hardenable material thereby to again fix the jacking units so as to support the object in its said selected position.
Claim 9
Independent Claim
252 words
The method of positioning and supporting an object, such as a large machine or other structure, on a foundation comprising the steps of: placing a plurality of hydraulic jacking units between the foundation and the object, each of said units having a generally downwardly facing surface; introducing a liquid under pressure into each of said jacking units to move the object relative to the foundation to a selected position, said liquid constituting a hydraulic working fluid; maintaining said liquid in each of said jacking units under pressure so as to support said object in its selected position; introducing a flowable, hardenable material, such as grout, around the jacking units with the hardenable material filling the space between said downwardly facing surface and said foundation; effecting the hardening of said hardenable material for fixing said jacking units in their selected positions with the weight of said object being substantially supported by said hardenable material engaging said downwardly facing surface; limiting the static loading of said hardenable material engaging said downwardly facing surface to about 750 psi; and subsequent to a period of use in the event said jacking units become loose in said hardenable material and thereby fail to properly support said object, introducing additional liquid under pressure into said jacking units to move said object to said selected position, and then introducing other hardenable material between said jacking units and said previously hardenable material thereby to again fix the jacking units so as to support the object in its said selected position.
Claim 10
Dependent Claim
26 words
The method of claim 1 further comprising limiting the static loading of the hardenable material engaging said downwardly facing surface to about 750 psi or less.
Claim 11
Dependent Claim
26 words
The method of claim 8 further comprising limiting the static loading of the hardenable material engaging said downwardly facing surface to about 150 psi or less.
References Cited (Backward Citations)
CA604170A
Cited
US2451777A
Cited
US2540622A
Cited
US2812834A
Cited
GB879936A
Cited
US3223415A
Cited
US3190041A
Cited
US3194853A
Cited
US3417520A
Cited
US3599381A
Cited
US3594973A
Cited
CA938602A
Cited
USPTO Annuity & Maintenance Windows
| Annuity Stage | Window Opens | Payment Deadline | Surcharge Period Until | Estimated Fee | Status |
|---|---|---|---|---|---|
| 3.5 Years (Year 4) | 1981-07-17 | 1982-01-16 | 1982-07-18 | $2000.00 | Window Closed / Lapsed |
| 7.5 Years (Year 8) | 1985-07-17 | 1986-01-16 | 1986-07-18 | $3760.00 | Window Closed / Lapsed |
| 11.5 Years (Year 12) | 1989-07-17 | 1990-01-16 | 1990-07-18 | $7700.00 | Window Closed / Lapsed |