US4077812A
Expired / Lapsed
US
⏱️ 0.0 years remaining
Method of working steel machine parts including machining during quench cooling
Assignee: NTN Corp
•
Filing: 1976-03-22
•
Granted: 1978-03-07
•
Expires: 1996-03-22
Abstract
Abstract The invention provides a method of working steel machine parts, and it relates to a composite technique consisting of machining and heat-treatment, which makes use of the fact that at temperatures in the vicinity of or above the Ms point during quench cooling, the structure of steel assumes a state of supercooled austenite or a portion thereof assumes a state of martensite transformation or beinite transformation, suitable for machining, and in such state desired machining is applied to steel machine parts, which are then cooled to room temperature for hardening. Other merits and details will be made clear.
Inventors
- 👤 Hajime Tani
Bibliographic Details
Application Number
—
Jurisdiction
US
Data Source
google_patents
Last Synchronized
2026-11-07 09:28
CPC Classifications
C; C21; C21D; C21D1/00; C21D1/26; C21D1/32; B; B23; B23P; B23P25/00
Claims Analysis
Total Claims: 8
Claim 1
Independent Claim
179 words
A method of working steel machine parts comprising uniformly heating a steel bank to an elevated temperature in the range 950°-1300° C, subjecting the heated steel blank at the elevated temperature to a plastic working operation to produce a steel blank suitable for use as a steel machine part, continuously cooling the worked steel blank from the working temperature to a temperature in the range 700°-850° C, subjecting the cooled steel blank to isothermal retention in the cooled temperature range for spheroidization of cementite, uniformly heating the cooled steel blank to a predetermined quenching temperature, said quenching temperature being selected in accordance with the kind of steel used for the blank, placing the heated steel blank in a cooling medium and quickly quench cooling the steel blank to a temperature in the vicinity of the Ms point of the steel, subjecting the cooled steel blank to a machining or cutting operation while the steel blank is at a temperature preceding the temperature at which hardening will occur, and thereafter permitting the worked steel blank to cool to room temperature.
Claim 2
Independent Claim
179 words
A method of working steel machine parts comprising uniformly heating a steel bank to an elevated temperature in the range 950°-1300° C, subjecting the heated steel blank at the elevated temperature to a plastic working operation to produce a steel blank suitable for use as a steel machine part, continuously cooling the worked steel blank from the working temperature to a temperature in the range 700°-850° C, subjecting the cooled steel blank to isothermal retention in the cooled temperature range for spheroidization of cementite, uniformly heating the cooled steel blank to a predetermined quenching temperature, said quenching temperature being selected in accordance with the kind of steel used for the blank, placing the heated steel blank in a cooling medium and quickly quench cooling the steel blank to a temperature in the vicinity of the Ms point of the steel, subjecting the cooled steel blank to a machining or cutting operation while the steel blank is at a temperature preceding the temperature at which hardening will occur, and thereafter permitting the worked steel blank to cool to room temperature.
Claim 3
Dependent Claim
17 words
A method of working as set forth in claim 1, wherein the machining is a turning operation.
Claim 4
Dependent Claim
17 words
A method of working as set forth in claim 1, wherein the machining is a grinding operation.
Claim 5
Dependent Claim
23 words
A method of working as set forth in claim 1, wherein the machining is a plastic working operation and a subseqent turning operation.
Claim 6
Dependent Claim
23 words
A method of working as set forth in claim 1, wherein the machining is a plastic working operation and a subsequent grinding operation.
Claim 7
Dependent Claim
25 words
A method of working as set forth in claim 1, wherein the cutting is followed by beinite transformation and then by cooling to room temperature.
Claim 8
Dependent Claim
9 words
The product produced by the method of claim 1.
References Cited (Backward Citations)
US2717846A
Cited
US3281287A
Cited
US3425877A
Cited
US3535910A
Cited
US3386862A
Cited
US3752709A
Cited
USPTO Annuity & Maintenance Windows
| Annuity Stage | Window Opens | Payment Deadline | Surcharge Period Until | Estimated Fee | Status |
|---|---|---|---|---|---|
| 3.5 Years (Year 4) | 1981-03-06 | 1981-09-05 | 1982-03-07 | $2000.00 | Window Closed / Lapsed |
| 7.5 Years (Year 8) | 1985-03-06 | 1985-09-05 | 1986-03-07 | $3760.00 | Window Closed / Lapsed |
| 11.5 Years (Year 12) | 1989-03-06 | 1989-09-05 | 1990-03-07 | $7700.00 | Window Closed / Lapsed |