A method of installing a Vertically Moored Platform at a selected site in water, said platform having four buoyant legs positioned in a rectangular pattern which comprises: a. setting each buoyant leg on a section of a gravity base, the total buoyancy of the gravity base being sufficient to support said platform in water; b. towing the platform and gravity base to the selected well site; c. reducing the buoyancy of two adjacent gravity base sections until the platform is tilted toward said two gravity base sections while maintaining said gravity base in a buoyant condition completely above the bottom of said water; d. thereafter and while said gravity base is still completely above bottom reducing the buoyancy of all sections until the center line of the platform is vertical; then simultaneously reducing the buoyancy of each said gravity base section in a manner to maintain the center line of the platform vertical until all buoyancy of each gravity base section has been removed and has a submerged weight; e. then partially flooding the buoyant legs until an operating draft has been reached; and f. thereafter lowering the gravity base to the bottom of the body of water and securing anchor elongated members between each lowered gravity base section and its respective buoyant leg.
Claim 2
Independent Claim
214 words
A method of installing a Vertically Moored Platform at a selected site in water, said platform having four buoyant legs positioned in a rectangular pattern which comprises: a. setting each buoyant leg on a section of a gravity base, the total buoyancy of the gravity base being sufficient to support said platform in water; b. towing the platform and gravity base to the selected well site; c. reducing the buoyancy of two adjacent gravity base sections until the platform is tilted toward said two gravity base sections while maintaining said gravity base in a buoyant condition completely above the bottom of said water; d. thereafter and while said gravity base is still completely above bottom reducing the buoyancy of all sections until the center line of the platform is vertical; then simultaneously reducing the buoyancy of each said gravity base section in a manner to maintain the center line of the platform vertical until all buoyancy of each gravity base section has been removed and has a submerged weight; e. then partially flooding the buoyant legs until an operating draft has been reached; and f. thereafter lowering the gravity base to the bottom of the body of water and securing anchor elongated members between each lowered gravity base section and its respective buoyant leg.
Claim 3
Dependent Claim
48 words
A method as defined in claim 1, in which the gravity base is lowered on cables, including the further steps of: securing a group of a plurality of risers between each said gravity base section and its buoyant leg; placing said risers under tensioning; and removing said cables.
Claim 4
Dependent Claim
30 words
A method as defined in claim 2, including the steps of: providing a plurality of riser spacers for the risers along the vertical length of each group at selected intervals.
Claim 5
Dependent Claim
37 words
A method as defined in claim 1 in which said buoyant legs are bottle-shaped, having a narrow neck portion, and step (e) includes flooding the buoyant legs until the water line is on the narrow neck portion.
Claim 6
Dependent Claim
24 words
A method as defined in claim 1, including providing auxiliary tanks for each buoyant leg and step (e) includes partially flooding the auxiliary tanks.
Claim 7
Dependent Claim
41 words
A method as defined in claim 1 in which step (c) includes reducing the buoyancy of two adjacent gravity base sections until the normal vertical center line of the platform makes an angle of about 20 degress with the true vertical.
Claim 8
Independent Claim
191 words
A method of installing a Vertically Moored Platform at a selected site, said platform having four buoyant legs positioned in a rectangular pattern which comprises: a. setting each buoyant leg on a section of a gravity base, the total buoyancy of the gravity base being sufficient to support said platform in water; b. positioning riser spacers on top of said gravity base; c. towing the platform and gravity base to the selected well site; d. reducing the buoyancy of two adjacent gravity base sections until the platform is tilted toward said two gravity base sections; e. thereafter reducing the buoyancy of all sections until the center line of the platform is vertical; then simultaneously reducing the buoyancy of each gravity base section until all buoyancy of each gravity base section has been removed and has a submerged weight; f. then partially flooding the buoyant legs until an operating draft has been reached; and g. thereafter lowering the gravity base to the bottom of th body of water while simultaneously lowering said riser spacers into position and securing anchor elongated members between each lowered gravity base section and its respective buoyant leg.
Claim 9
Independent Claim
191 words
A method of installing a Vertically Moored Platform at a selected site, said platform having four buoyant legs positioned in a rectangular pattern which comprises: a. setting each buoyant leg on a section of a gravity base, the total buoyancy of the gravity base being sufficient to support said platform in water; b. positioning riser spacers on top of said gravity base; c. towing the platform and gravity base to the selected well site; d. reducing the buoyancy of two adjacent gravity base sections until the platform is tilted toward said two gravity base sections; e. thereafter reducing the buoyancy of all sections until the center line of the platform is vertical; then simultaneously reducing the buoyancy of each gravity base section until all buoyancy of each gravity base section has been removed and has a submerged weight; f. then partially flooding the buoyant legs until an operating draft has been reached; and g. thereafter lowering the gravity base to the bottom of th body of water while simultaneously lowering said riser spacers into position and securing anchor elongated members between each lowered gravity base section and its respective buoyant leg.
Claim 10
Dependent Claim
23 words
A method as defined in claim 7 in which: said spacers are lowered by cables at spaced intervals prior to lowering said risers.
Claim 11
Dependent Claim
44 words
A method as defined in claim 7 in which said spacers are positioned on top of the gravity base and lowered with the gravity base, then raising the spacers one by one to a level selected for each spacer after the risers are lowered.
Claim 12
Independent Claim
224 words
A method of installing a Vertically Moored Platform at a selected site in water, said platform having at least three buoyant legs positioned in a geometrical pattern which comprises: a. setting each buoyant leg on one of a plurality of buoyant sections of a gravity base, the total buoyancy of the gravity base being sufficient to support said platform in water; b. towing the platform and gravity base to the selected well site; c. reducing the buoyancy of at least one gravity base section until the platform is tilted toward said at least one gravity base section while maintaining said gravity base in a buoyant condition completely above the bottom of said water; d. thereafter and while said gravity base is still completely above bottom reducing the buoyancy of all sections until the center line of the platform is vertical; then simultaneously reducing the buoyancy of each said gravity base section in a manner to maintain the center line of the platform vertical until all buoyancy of each gravity base section has been removed and has a submerged weight; e. then partially flooding the buoyant legs until an operating draft has been reached; and f. thereafter lowering the gravity base of the bottom of the body of water and securing anchor elonated members between each lowered gravity base section and its respective buoyant leg.
Claim 13
Independent Claim
224 words
A method of installing a Vertically Moored Platform at a selected site in water, said platform having at least three buoyant legs positioned in a geometrical pattern which comprises: a. setting each buoyant leg on one of a plurality of buoyant sections of a gravity base, the total buoyancy of the gravity base being sufficient to support said platform in water; b. towing the platform and gravity base to the selected well site; c. reducing the buoyancy of at least one gravity base section until the platform is tilted toward said at least one gravity base section while maintaining said gravity base in a buoyant condition completely above the bottom of said water; d. thereafter and while said gravity base is still completely above bottom reducing the buoyancy of all sections until the center line of the platform is vertical; then simultaneously reducing the buoyancy of each said gravity base section in a manner to maintain the center line of the platform vertical until all buoyancy of each gravity base section has been removed and has a submerged weight; e. then partially flooding the buoyant legs until an operating draft has been reached; and f. thereafter lowering the gravity base of the bottom of the body of water and securing anchor elonated members between each lowered gravity base section and its respective buoyant leg.