Abstract

Abstract A turbo-alternator plant, particularly for shipboard use on waste-heat generated steam, in which the turbine and alternator rotors are coupled directly together governed to a speed giving a desired frequency of a.c. output.

Inventors

  • 👤 Edmund Porter Crowdy
  • 👤 Hector Fillippus Alexander Drentham-Susman

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-10-28 21:22
CPC Classifications
F; F01; F01D; F01D15/00; F01D15/10; F01D25/00; F01D25/18; F01D25/22; F01K; F01K13/00; F02; F02G; F02G5/00; F02G5/02; Y; Y02; Y02T; Y02T10/00; Y02T10/10; Y02T10/12; Y10; Y10S; Y10S60/00; Y10S60/916

Claims Analysis

Total Claims: 8
Claim 1
Independent Claim 154 words
In a turbo-alternator plant comprising a prime mover producing hot exhaust gases, a waste heat boiler connected to receive the exhaust gases from the prime mover and thereby generating steam, a turbine receiving the steam to be driven thereby, an alternator, each of said turbine and said alternator having a rotor, the rotors being drivingly connected, and a steam condenser connected to receive steam exhausting from the turbine; the improvement, wherein the turbine rotor and alternator rotor are directly connected together and are disposed with the rotational axis of the said rotors vertical, the alternator being above the turbine and wherein there is a bearing arrangement supporting the said rotors including a bearing supporting the weight of their rotors, said bearing being within the environment of said condenser receiving steam exhausting from the turbine, and there being means governing the rotor composite to a speed appropriate to the desired frequency of the alternator output.
Claim 2
Dependent Claim 154 words
In a turbo-alternator plant comprising a prime mover producing hot exhaust gases, a waste heat boiler connected to receive the exhaust gases from the prime mover and thereby generating steam, a turbine receiving the steam to be driven thereby, an alternator, each of said turbine and said alternator having a rotor, the rotors being drivingly connected, and a steam condenser connected to receive steam exhausting from the turbine; the improvement, wherein the turbine rotor and alternator rotor are directly connected together and are disposed with the rotational axis of the said rotors vertical, the alternator being above the turbine and wherein there is a bearing arrangement supporting the said rotors including a bearing supporting the weight of their rotors, said bearing being within the environment of said condenser receiving steam exhausting from the turbine, and there being means governing the rotor composite to a speed appropriate to the desired frequency of the alternator output.
Claim 3
Dependent Claim 14 words
A turbo-alternator plant according to claim 1, wherein the alternator is a two-pole alternator.
Claim 4
Dependent Claim 54 words
A turbo-alternator plant according to claim 1, wherein the bearing arrangement comprises means stabilising the alternator rotor transversely, said means being two anti-friction grease-lubricated bearings, and the said bearing within the condenser environment also stablising the turbine rotor and being a water-lubricated bearing at the side of the turbine rotor remote from the alternator.
Claim 5
Dependent Claim 26 words
A turbo-alternator plant according to claim 3, wherein the weight-supporting bearing and turbine-stabilising bearing are combined in a journal and foot-step bearing which is water lubricated.
Claim 6
Dependent Claim 44 words
A turbo-alternator plant according to claim 4, comprising a source of supply of water for lubricating the foot-step bearing including a feed water return from the condenser to the waste heat boiler, and a pipe leading from the feed-water return to the foot-step bearing.
Claim 7
Dependent Claim 39 words
A turbo-alternator plant according to claim 1, wherein the steam outlet from the turbine is connected to deliver exhaust steam directly into the condenser so that the exhaust flow from the turbine is substantially unimpeded and good drainage secured.
Claim 8
Dependent Claim 35 words
A turbo-alternator according to any of claims 1, further comprising a throttle valve controlling the flow of steam to the turbine and a by-pass valve to lead any excess steam directly to a heat sink.

References Cited (Backward Citations)

GB267251A Cited
GB1012744A Cited
US3359731A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1980-09-19 1981-03-21 1981-09-20 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1984-09-19 1985-03-21 1985-09-20 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 1988-09-19 1989-03-21 1989-09-20 $7700.00 Window Closed / Lapsed

Assigned Categories & Tags

No categories assigned to this patent yet.

Assign Category Tag