Method for increasing the recovery of natural gas from a geo-pressured aquifer

Assignee: TRANSCO DEVELOPMENT Co
•
Filing: 1976-05-24
•
Granted: 1977-08-16
•
Expires: 1996-05-24
📄 Original PDF 🌐 Google Patents 🔄 Sync Now

Abstract

Abstract A method of increasing the recovery of natural gas from a geo-pressured aquifer containing water and gas and having a zone of free gas dispersed in water, by providing one or more wells extending from the surface to and completed in the geo-pressured aquifer in said zone and allowing the aquifer to flow water and gas under natural pressure through the well and lowering the pressure in the aquifer sufficiently to allow the gas to be released from solution in the water whereby the gas released will migrate more freely to the well and be produced. Also, any gas-phase saturation in the aquifer and any deposit of gaseous hydrocarbons in the formation in pressure communication with the wells will expand due to lowered aquifer pressure and be encouraged to flow to the wells and be recovered. Preferably, the wells are produced at a high enough rate of production to reduce the existing aquifer pressure in the drainage area of the wells as quickly as possible so that gas may be released from solution in the water and so that gaseous hydrocarbons in the formation may expand and flow to the wells. A high initial flow rate of at least 15,000 barrels of water per day from each well is necessary to effect the lowering of the aquifer pressure by at least 25% in order to provide the necessary mobility of the gas to obtain the enhanced gas recovery by the present method.

Inventors

  • 👤 Harold L. Cook, Jr.
  • 👤 Ernest C. Geer

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-10-25 23:47
CPC Classifications
E; E21; E21B; E21B43/00

Claims Analysis

Total Claims: 14
Claim 1
Independent Claim 117 words
A method of increasing the recovery of natural gas from a geo-pressured aquifer containing water and gas in solution in the water and a zone of free gas dispersed in water comprising, providing one or more wells extending from the surface and completed in the geo-pressured aquifer in said zone, allowing the geo-pressured aquifer to flow water and natural gas under aquifer pressure through the well so as to lower the pressure in the aquifer sufficiently to allow a portion of the free gas dispersed in the water and a portion of the gas in solution to be released from the water whereby the released natural gas will migrate more freely to the well and be produced.
Claim 2
Independent Claim 117 words
A method of increasing the recovery of natural gas from a geo-pressured aquifer containing water and gas in solution in the water and a zone of free gas dispersed in water comprising, providing one or more wells extending from the surface and completed in the geo-pressured aquifer in said zone, allowing the geo-pressured aquifer to flow water and natural gas under aquifer pressure through the well so as to lower the pressure in the aquifer sufficiently to allow a portion of the free gas dispersed in the water and a portion of the gas in solution to be released from the water whereby the released natural gas will migrate more freely to the well and be produced.
Claim 3
Dependent Claim 23 words
The method of claim 1 wherein, the existing bottom-hole pressure of said wells is reduced by at least 25 percent within 1 year.
Claim 4
Dependent Claim 30 words
The method of claim 1 including, allowing the aquifer to initially flow water from each of the wells at a rate of at least 15,000 barrels of water per day.
Claim 5
Dependent Claim 16 words
The method of claim 1 including, recovering through said well hydrocarbon liquids present in the aquifer.
Claim 6
Independent Claim 119 words
A method of increasing the recovery of natural gas from a geo-pressured aquifer containing water and gas in solution in the water and a zone of free gas dispersed in water comprising, providing one or more wells extending from the surface and completed in the geo-pressured aquifer in said zone, producing water from the wells at a high enough rate of production for obtaining a low bottom-hole working pressure in said wells while maintaining artesian flow of water to cause a portion of the free gas dispersed in the water and a portion of the gas in solution to be released from the water whereby the released natural gas will migrate more freely to the well and be produced.
Claim 7
Independent Claim 119 words
A method of increasing the recovery of natural gas from a geo-pressured aquifer containing water and gas in solution in the water and a zone of free gas dispersed in water comprising, providing one or more wells extending from the surface and completed in the geo-pressured aquifer in said zone, producing water from the wells at a high enough rate of production for obtaining a low bottom-hole working pressure in said wells while maintaining artesian flow of water to cause a portion of the free gas dispersed in the water and a portion of the gas in solution to be released from the water whereby the released natural gas will migrate more freely to the well and be produced.
Claim 8
Dependent Claim 30 words
The method of claim 5 including, allowing the aquifer to initially flow water from each of the wells at a rate of at least 15,000 barrels of water per day.
Claim 9
Independent Claim 116 words
A method of increasing the recovery of natural gas from a geo-pressured aquifer containing water and gas in solution in the water and a section having dispersed free saturation in the water comprising, providing one or more wells extending from the surface and completed in the geo-pressured aquifer in said section, producing water from the wells at a high enough rate of production to reduce the existing bottom-hole pressure of the wells by at least 25 percent whereby a portion of the free gas dispersed in the water and a portion of the gas in solution will be released from the water and the released gas will migrate more freely to the well and be produced.
Claim 10
Independent Claim 116 words
A method of increasing the recovery of natural gas from a geo-pressured aquifer containing water and gas in solution in the water and a section having dispersed free saturation in the water comprising, providing one or more wells extending from the surface and completed in the geo-pressured aquifer in said section, producing water from the wells at a high enough rate of production to reduce the existing bottom-hole pressure of the wells by at least 25 percent whereby a portion of the free gas dispersed in the water and a portion of the gas in solution will be released from the water and the released gas will migrate more freely to the well and be produced.
Claim 11
Dependent Claim 24 words
The method of claim 7 wherein the initial flow rate from each of the wells is at least 15,000 barrels per day of water.
Claim 12
Dependent Claim 15 words
The method of claim 8 including, recovering hydrocarbon liquids through wells present in the aquifer.
Claim 13
Independent Claim 148 words
A method of increasing the recovery of natural gas from a geo-pressured aquifer containing water and gas in solution in the water and a zone having dispersed free gas saturation in the water comprising, providing one or more wells extending from the surface and completed in the geo-pressured aquifer in said zone, producing water from the wells, under aquifer pressure, at an initial flow rate from each of the walls of at least 15,000 barrels per day of water, reducing the existing bottom-hole pressure of the wells by at least 25 percent whereby a portion of the free gas dispersed in the water and a portion of the gas in solution will be released from the water and the released gas will migrate more freely to the well and be produced, and maintaining the initial flow rate and reducing said pressure by said 25 percent within 1 year.
Claim 14
Independent Claim 148 words
A method of increasing the recovery of natural gas from a geo-pressured aquifer containing water and gas in solution in the water and a zone having dispersed free gas saturation in the water comprising, providing one or more wells extending from the surface and completed in the geo-pressured aquifer in said zone, producing water from the wells, under aquifer pressure, at an initial flow rate from each of the walls of at least 15,000 barrels per day of water, reducing the existing bottom-hole pressure of the wells by at least 25 percent whereby a portion of the free gas dispersed in the water and a portion of the gas in solution will be released from the water and the released gas will migrate more freely to the well and be produced, and maintaining the initial flow rate and reducing said pressure by said 25 percent within 1 year.

References Cited (Backward Citations)

US2077912A Cited
US3215198A Cited
US3302581A Cited
US3382933A Cited
US3785446A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1980-08-15 1981-02-14 1981-08-16 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1984-08-15 1985-02-14 1985-08-16 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 1988-08-15 1989-02-14 1989-08-16 $7700.00 Window Closed / Lapsed

Assigned Categories & Tags

No categories assigned to this patent yet.

Assign Category Tag