Claims Analysis
Total Claims: 9
Claim 1
Independent Claim
207 words
An offshore platform structure comprising: a negatively buoyant one-piece platform defining a substantially horizontal support surface for accepting a vessel thereon; a plurality of support legs on said platform being supported by the sea bottom below the surface of the water for stably supporting said platform, said legs being spaced to define a passage between said legs; a plurality of jacking mechanisms secured to said platform and adapted to engage said legs for raising and lowering said platform with respect to said legs to position said platform above water level or below water level; heave absorbing means disposed substantially across the passage between said legs, said heave absorbing means comprising a fender of pliable material providing a flexible surface extending above said support surface for engagement with the bottom of the vessel to dampen vertical motion thereof during docking and means for moving said fender between a first position wherein said fender is raised above the surface of the support surface to a second position wherein said fender is below the surface of the support surface; and a substantially flat-bottomed work barge to be floated over said platform through said passage and to be supported without attachment on said platform at a raised position above water level.
Claim 2
Dependent Claim
207 words
An offshore platform structure comprising: a negatively buoyant one-piece platform defining a substantially horizontal support surface for accepting a vessel thereon; a plurality of support legs on said platform being supported by the sea bottom below the surface of the water for stably supporting said platform, said legs being spaced to define a passage between said legs; a plurality of jacking mechanisms secured to said platform and adapted to engage said legs for raising and lowering said platform with respect to said legs to position said platform above water level or below water level; heave absorbing means disposed substantially across the passage between said legs, said heave absorbing means comprising a fender of pliable material providing a flexible surface extending above said support surface for engagement with the bottom of the vessel to dampen vertical motion thereof during docking and means for moving said fender between a first position wherein said fender is raised above the surface of the support surface to a second position wherein said fender is below the surface of the support surface; and a substantially flat-bottomed work barge to be floated over said platform through said passage and to be supported without attachment on said platform at a raised position above water level.
Claim 3
Dependent Claim
19 words
The structure of claim 1 including: means to selectively mount and demount said jacking mechanisms relative to said legs.
Claim 4
Dependent Claim
25 words
The structure of claim 1 wherein: said platform comprises a plurality of open network of trusslike members arranged between said legs transversely to said passage.
Claim 5
Dependent Claim
29 words
The structure of claim 1 including: a mechanism for locking said negatively buoyant platform in place on said supports, permitting jacking equipment comprising said jacking mechanisms to be removed.
Claim 6
Dependent Claim
21 words
The structure of claim 1 wherein: said jacking mechanisms each comprise a plurality of jacks powered from a common power plant.
Claim 7
Dependent Claim
21 words
The structure of claim 1 including: a mat structure resting on the sea bottom to which said support legs are secured.
Claim 8
Dependent Claim
65 words
The structure of claim 1 including: a plurality of clamps disposed along one of said support legs for supporting a riser flow pipe extending from an underwater well head to said work barge, said clamps having an internal cross sections slightly larger than the cross section of the riser pipe to permit movement of said support legs relative to the riser to prevent loading thereof.
Claim 9
Dependent Claim
33 words
The structure of claim 7 including: a disconnectable coupling disposed between said work barge and a riser connected to an underwater well head to facilitate removal of said barge from the well site.