Control of a steam-heating power plant

Assignee: Honeywell International Inc
•
Filing: 1975-08-18
•
Granted: 1977-08-02
•
Expires: 1995-08-18
📄 Original PDF 🌐 Google Patents 🔄 Sync Now

Abstract

Abstract Apparatus for the control of steam-heating power plants to optimize the use of energy in producing the required steam and electrical power comprising means for sensing steam and electricity demands, means for comparing these sensed demands with the electricity and steam output of turbine means in the plant, and means for adjusting operating set points of the turbines and steam generator for coordinated control of power plant energy consumption and production.

Inventors

  • 👤 James R. Vance

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-10-28 15:15
CPC Classifications
F; F01; F01K; F01K7/00; F01K7/34; F01K7/345

Claims Analysis

Total Claims: 4
Claim 1
Independent Claim 246 words
A control system for an apparatus adapted for producing steam and electricity to meet demands for same, said apparatus including (1) steam generator means for producing high pressure steam in response to a fuel load signal, (2) first turbine means for producing electricity from said high pressure steam, said first turbine means being adapted to exhaust intermediate pressure steam having a pressure between the high pressure steam and that pressure corresponding to condensing conditions, (3) second turbine means for producing electricity from a portion of said intermediate pressure steam and (4) means for withdrawal of the remaining intermediate pressure steam to supply said steam demand, said first and second turbine means being adapted to supply electricity to a common power network, each turbine means having means for setting the turbine load level in response to a load command signal, said control system comprising: (a) means for sensing steam and electricity demand-variables, (b) means for comparing said sensed demand-variables with the electricity and steam outputs of said first and second turbine means, respectively, and producing adjusted load command signals for each turbine means, (c) means for producing an adjusted fuel-load signal for said steam generator means in response to said adjusted load command signals, and (d) means for transmitting said turbine load command signals to said first and second turbine means, respectively, and said adjusted fuel-load signal to said steam generator means for coordinated adjustment of said steam generator means and said first and second turbine means.
Claim 2
Dependent Claim 246 words
A control system for an apparatus adapted for producing steam and electricity to meet demands for same, said apparatus including (1) steam generator means for producing high pressure steam in response to a fuel load signal, (2) first turbine means for producing electricity from said high pressure steam, said first turbine means being adapted to exhaust intermediate pressure steam having a pressure between the high pressure steam and that pressure corresponding to condensing conditions, (3) second turbine means for producing electricity from a portion of said intermediate pressure steam and (4) means for withdrawal of the remaining intermediate pressure steam to supply said steam demand, said first and second turbine means being adapted to supply electricity to a common power network, each turbine means having means for setting the turbine load level in response to a load command signal, said control system comprising: (a) means for sensing steam and electricity demand-variables, (b) means for comparing said sensed demand-variables with the electricity and steam outputs of said first and second turbine means, respectively, and producing adjusted load command signals for each turbine means, (c) means for producing an adjusted fuel-load signal for said steam generator means in response to said adjusted load command signals, and (d) means for transmitting said turbine load command signals to said first and second turbine means, respectively, and said adjusted fuel-load signal to said steam generator means for coordinated adjustment of said steam generator means and said first and second turbine means.
Claim 3
Dependent Claim 247 words
In apparatus adapted for producing steam and electricity to meet demands for same which comprises: (1) a steam generator for producing high pressure steam from fuel in response to a fuel-load setting signal, (2) first turbine means for producing electricity from said high pressure steam, said first turbine means being adapted to exhaust intermediate pressure steam having a pressure between the high pressure steam and that pressure corresponding to condensing conditions, (3) second turbine means for producing electricity from a portion of said intermediate pressure steam, and (4) means for withdrawing the remaining intermediate pressure steam to supply said steam demand, said first and second turbine means being adapted to supply electricity to a common power network and each turbine means having means for setting the turbine load-level in response to a load command signal, the improvement which comprises a system for coordinating control of the amounts of steam and electricity produced including: (a) means for sensing steam and electricity demand-variables, (b) means for comparing said sensed demand-variables with the electricity output and steam output of said first and second turbine means, respectively, and adjusting the load command signals for said first and second turbine means, (c) means for adjusting the fuel-load setting signal for said steam generator means to correlate it with said adjusted load command signals, and (d) means for transmitting said adjusted turbine load signals to said first and second turbine means, respectively, and said adjusted fuel-load settings signal to said steam generator means.
Claim 4
Dependent Claim 247 words
In apparatus adapted for producing steam and electricity to meet demands for same which comprises: (1) a steam generator for producing high pressure steam from fuel in response to a fuel-load setting signal, (2) first turbine means for producing electricity from said high pressure steam, said first turbine means being adapted to exhaust intermediate pressure steam having a pressure between the high pressure steam and that pressure corresponding to condensing conditions, (3) second turbine means for producing electricity from a portion of said intermediate pressure steam, and (4) means for withdrawing the remaining intermediate pressure steam to supply said steam demand, said first and second turbine means being adapted to supply electricity to a common power network and each turbine means having means for setting the turbine load-level in response to a load command signal, the improvement which comprises a system for coordinating control of the amounts of steam and electricity produced including: (a) means for sensing steam and electricity demand-variables, (b) means for comparing said sensed demand-variables with the electricity output and steam output of said first and second turbine means, respectively, and adjusting the load command signals for said first and second turbine means, (c) means for adjusting the fuel-load setting signal for said steam generator means to correlate it with said adjusted load command signals, and (d) means for transmitting said adjusted turbine load signals to said first and second turbine means, respectively, and said adjusted fuel-load settings signal to said steam generator means.

References Cited (Backward Citations)

GB352074A Cited
US1915983A Cited
GB421947A Cited
US3623324A Cited
US3812377A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1980-08-01 1981-01-31 1981-08-02 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1984-08-01 1985-01-31 1985-08-02 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 1988-08-01 1989-01-31 1989-08-02 $7700.00 Window Closed / Lapsed