Abstract

Abstract This invention relates to a process whereby recovery of copper from copper ores using leaching and solvent extraction techniques can be increased. The process generally comprises leaching to obtain a pregnant leach liquor, washing ore residues with an extra quantity of water to obtain extra dissolved copper values, recovering said copper values, combining the extra wash water with the pregnant leach liquor, extracting copper values from the total leach liquor to yield a raffinate which still contains some copper values, and cycling part of the raffinate through a low pH extraction circuit to lower the copper values remaining in the raffinate to about 0.01 to 0.02 grams per liter or less before disposal.

Inventors

  • 👤 Soon Y. Wong

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-11-01 06:26
CPC Classifications
C; C01; C01G; C01G3/00; C01G3/003; C22; C22B; C22B15/00; C22B15/0063; C22B15/0065; C22B15/0067; C22B3/00; C22B3/20; C22B3/26; C22B3/30; C22B3/36; C22B3/362; C22B3/364; C22B3/42; Y; Y02; Y02P; Y02P10/00; Y02P10/20

Claims Analysis

Total Claims: 12
Claim 1
Independent Claim 386 words
A process for the recovery of copper values from copper-bearing ores comprising: a. leaching the ore with mineral acid in the presence of water to produce a pregnant liquor stream containing dissolved copper values, and washing the leached ore residue with an internal recycle stream from step (c) in addition to other wash waters, b. passing additional water through the leach vessel containing spent ore residues, said ore being disposed from the recovery system and said water being subsequently combined with the pregnant liquor stream from step (a) to form a resultant stream which is then passed through c. at least one first extraction stage containing an extraction agent for removal of copper values, said extraction stage producing a loaded organic extraction stream and an aqueous raffinate stream containing metal values not extracted from resultant stream of step (b) and separating said raffinate stream into a first internal stream of aqueous raffinate and a second internal stream of aqueous raffinate, d. passing the first internal raffinate recycle stream back to step (a) leach system, and e. passing the second internal stream to a second extraction having at least one extraction stage containing a second extracting agent where the copper values are extracted in the presence of a low pH extracting agent, said extraction stage producing a loaded organic stream and a disposal stream, while f. the loaded organic stream from step (e) is stripped in at least one stripping stage in the presence of sufficient stripping acid containing aqueous stripping agent, resulting in a stripped organic stream and a loaded stripping acid stream g. recycling the stripped organic stream from step (f) to the extraction stage of step (e) while h. the loaded stripping acid stream of step (f), containing recovered copper values is passed to the process described in step (a), while i. the loaded organic stream produced in step (c) is passed through at least one stripping stage wherein a stripped organic stream and a pregnant electrolyte stream is produced, subsequently j. recycling the stripped organic stream to the resultant stream extraction of step (c), while k. passing the pregnant electrolyte to a copper recovery process from which exits a spent electrolyte stream which is recycled to step (i) as a stripping agent, while 1. recovering the copper values as metal from step (k).
Claim 2
Dependent Claim 386 words
A process for the recovery of copper values from copper-bearing ores comprising: a. leaching the ore with mineral acid in the presence of water to produce a pregnant liquor stream containing dissolved copper values, and washing the leached ore residue with an internal recycle stream from step (c) in addition to other wash waters, b. passing additional water through the leach vessel containing spent ore residues, said ore being disposed from the recovery system and said water being subsequently combined with the pregnant liquor stream from step (a) to form a resultant stream which is then passed through c. at least one first extraction stage containing an extraction agent for removal of copper values, said extraction stage producing a loaded organic extraction stream and an aqueous raffinate stream containing metal values not extracted from resultant stream of step (b) and separating said raffinate stream into a first internal stream of aqueous raffinate and a second internal stream of aqueous raffinate, d. passing the first internal raffinate recycle stream back to step (a) leach system, and e. passing the second internal stream to a second extraction having at least one extraction stage containing a second extracting agent where the copper values are extracted in the presence of a low pH extracting agent, said extraction stage producing a loaded organic stream and a disposal stream, while f. the loaded organic stream from step (e) is stripped in at least one stripping stage in the presence of sufficient stripping acid containing aqueous stripping agent, resulting in a stripped organic stream and a loaded stripping acid stream g. recycling the stripped organic stream from step (f) to the extraction stage of step (e) while h. the loaded stripping acid stream of step (f), containing recovered copper values is passed to the process described in step (a), while i. the loaded organic stream produced in step (c) is passed through at least one stripping stage wherein a stripped organic stream and a pregnant electrolyte stream is produced, subsequently j. recycling the stripped organic stream to the resultant stream extraction of step (c), while k. passing the pregnant electrolyte to a copper recovery process from which exits a spent electrolyte stream which is recycled to step (i) as a stripping agent, while 1. recovering the copper values as metal from step (k).
Claim 3
Dependent Claim 16 words
A process as described in claim 1 wherein the leach process is a vat leach process.
Claim 4
Dependent Claim 30 words
A process as described in claim 2 wherein the step (c) extraction agent is selected from the group consisting of alpha hydroxy oximes, benzophenone oximes, and alkyl hydroxyphenyl alkyl ketoximes.
Claim 5
Dependent Claim 40 words
A process as described in claim 3 wherein the extraction agent is selected from the group consisting of 2-hydroxy-5-nonyl acetophenone oxime, 5-alkyl-2-hydroxyphenyl alkyl ketoximes, 8-hydroxyquinolines, 2-hydroxy-3'-methyl-5-ethylbenzophenoxime, 2-hydroxy-5-(1,1-dimethylpropyl)-benzophenoxime, 2-hydroxy-5-(1,1-dimethylethyl)-benzophenoxime, 2-hydroxy-5-octylbenzophenoxime, 2-hydroxy-5-nonyl-benzophenoxime, 2-hydroxy-5-dodecyl-benzophenoxime, 2-hydroxy-2',4'-dimethyl-5-octylbenzophenoxime, 2-hydroxy-2',3',5'-trimethyl-5-octylbenzophenoxime, 2-hydroxy-3,5-dinonylbenzophenoxime, 2hydroxy-4'-(1,1-dimethylethyl)-5-(2-pentyl)-benzophenoxime, 2-hydroxy-4'-(1,1-dimethylethyl)-5-(2-butyl)-benzophenoxime, 2-hydroxy-4-dodecyloxybenzophenoxime, 2-hydroxy-4'-(1,1-dimethylethyl)-5-methyl-benzophenoxime, 2-hydroxy-4',5-bis-(1,1-dimethylethyl) benzophenoxime.
Claim 6
Dependent Claim 19 words
A process as described in claim 1 wherein the step (e) extraction agent is a chlorinated hydroxy benzophenone oxime.
Claim 7
Dependent Claim 51 words
A process as described in claim 2 wherein the loaded stripping acid stream of step (f) is passed through an acid mixing stage where sufficient fresh acid is added to yield a solution containing the desired amount of acid for the process of step (a) before being passed to step (a).
Claim 8
Dependent Claim 39 words
A process as described in claim 1 wherein a mineral acid is added to the wash water of step (b) and the resulting solution utilized as a leaching agent in a dump leach, producing a second pregnant liquor stream.
Claim 9
Dependent Claim 32 words
A process as described in claim 7 wherein the pregnant liquor stream from the dump leach is combined with the pregnant liquor produced in step (a) prior to passage to step (c).
Claim 10
Dependent Claim 59 words
A process as described in claim 1 wherein the first internal stream of raffinate of step (c) is further divided to form a third and fourth recycle streams, said third recycle stream passing to step (a) and the fourth recycle stream being combined with acid to form a leaching agent for a dump leach, producing a pregnant leach liquor.
Claim 11
Dependent Claim 40 words
A process as described in claim 9 wherein the pregnant leach liquor from the dump leach is combined with the pregnant leach liquor of step (a) and the wash waters of step (b) to form the feed to step (c).
Claim 12
Dependent Claim 34 words
A process as described in claim 9 wherein the pregnant leach liquor from the dump leach is added to the leach system of step (a) to produce the pregnant leach liquor of step (a).

References Cited (Backward Citations)

US2831763A Cited
US3655347A Cited
US3777003A Cited
US3697400A Cited
US3863002A Cited
US3853981A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1980-08-01 1981-01-31 1981-08-02 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1984-08-01 1985-01-31 1985-08-02 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 1988-08-01 1989-01-31 1989-08-02 $7700.00 Window Closed / Lapsed