Abstract

Abstract A combined cycle electric power plant includes gas and steam turbines and steam generators and a digital/analog control system. In the control system, an automatic digital computer control generates position setpoints for the gas turbine fuel valves and the steam turbine inlet valves to control turbine speed and load. A synchronizer system includes an automatic synchronizer subsystem and a manual synchronizer subsystem. The automatic synchronizer subsystem includes a sequencer which is largely embodied in the digital computer and it further includes a synchronizer which is external to the automatic control. The automatic sequencer connects the synchronizer to synchronize the three generators in a sequence which depends on the startup and loading operation of the turbines, the synchronization operation of the synchronizer and the operation of the breakers. The manual synchronizer subsystem responds to operator inputs to generate a speed reference for the synchronization of each turbine. The synchronization system further includes logic structure needed to permit synchronization to occur and to define the synchronization mode. Turbine speed changes are initiated by the speed/load control under synchronizer system control.

Inventors

  • 👤 Robert Uram

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-10-30 02:20
CPC Classifications
F; F01; F01K; F01K23/00; F01K23/02; F01K23/06; F01K23/10; F01K23/103; F01K23/105; F01D; F01D17/00; F01D17/20; F01D17/22; F01D17/24; Y; Y02; Y02E; Y02E20/00; Y02E20/16

Claims Analysis

Total Claims: 16
Claim 1
Independent Claim 294 words
A combined cycle electric power plant comprising at least one gas turbine, means for generating steam in response to heat energy from said gas turbine, a steam turbine driven by steam supplied to it from said steam generating means, an electric generator driven by each of said turbines, means for controlling the operation of said turbines and steam generating means, said controlling means including a speed control for said gas turbine and a speed control for said steam turbine, means for regulating the field voltage of each of said generators during its startup, circuit breaker means for connecting each of said generators to a power system line, means for generating signals representing each generator voltage and frequency and each line voltage and frequency, an operator station having an automatic/manual synchronization selector switch and means for generating speed change and voltage change demand signals for each turbine-generator when it is selected for manual synchronization, means responsive to said voltage and frequency signals for automatically generating voltage change and turbine speed change outputs for implementation by the associated ones of said turbine speed controls and said field voltage regulating means when an automatic synchronization signal is generated by said selector switch and the associated generator is being sychronized, means for automatically generating a breaker close signal for each breaker means during synchronization of the associated generator on voltage and speed matches in the automatic synchronization mode, means for uncoupling the automatic synchronizing control paths and for coupling the speed and voltage change demand signals from said operator station to the selected turbine-generator when a manual synchronization signal is generated by said selector swtich, and means for generating a closing signal from the operator station for the breaker means associated with the generator selected for manual synchronization.
Claim 2
Dependent Claim 294 words
A combined cycle electric power plant comprising at least one gas turbine, means for generating steam in response to heat energy from said gas turbine, a steam turbine driven by steam supplied to it from said steam generating means, an electric generator driven by each of said turbines, means for controlling the operation of said turbines and steam generating means, said controlling means including a speed control for said gas turbine and a speed control for said steam turbine, means for regulating the field voltage of each of said generators during its startup, circuit breaker means for connecting each of said generators to a power system line, means for generating signals representing each generator voltage and frequency and each line voltage and frequency, an operator station having an automatic/manual synchronization selector switch and means for generating speed change and voltage change demand signals for each turbine-generator when it is selected for manual synchronization, means responsive to said voltage and frequency signals for automatically generating voltage change and turbine speed change outputs for implementation by the associated ones of said turbine speed controls and said field voltage regulating means when an automatic synchronization signal is generated by said selector switch and the associated generator is being sychronized, means for automatically generating a breaker close signal for each breaker means during synchronization of the associated generator on voltage and speed matches in the automatic synchronization mode, means for uncoupling the automatic synchronizing control paths and for coupling the speed and voltage change demand signals from said operator station to the selected turbine-generator when a manual synchronization signal is generated by said selector swtich, and means for generating a closing signal from the operator station for the breaker means associated with the generator selected for manual synchronization.
Claim 3
Dependent Claim 47 words
A combined cycle electric power plant as set forth in claim 1 wherein means are provided for sequentially operating said automatic generating means to implement field voltage changes and turbine speed changes for sequential automatic synchronization of the turbine generators for which automatic synchronization has been specified.
Claim 4
Dependent Claim 85 words
A combined cycle electric power plant as set forth in claim 1 wherein a digital computer is included as a part of said controlling means, means are provided for controlling the fuel flow to said gas turbine and the inlet steam flow to said steam turbine, said computer includes said turbine speed controls to generate fuel and steam control signals for said fuel and inlet steam controlling means, and said computer includes means for applying synchronizing speed change signals to said turbine speed controlling means.
Claim 5
Dependent Claim 59 words
A combined cycle electric power plant as set forth in claim 3 wherein said operator station includes a keyboard for entering speed demand changes into said computer, and said computer includes means for disabling operator speed demand changes from application to said speed control during gas or steam turbine-generator synchronization for which automatic synchronization has been specified or selected.
Claim 6
Dependent Claim 72 words
A combined cycle electric power plant as set forth in claim 3 wherein said computer speed controls include means for generating a speed demand, means for generating a speed reference, means for generating a speed error from the speed reference and actual turbine speed, means for applying automatic synchronization speed changes as reference changes, and means for setting the speed demand equal to the speed reference when synchronization speed reference changes occur.
Claim 7
Dependent Claim 48 words
A combined cycle electric power plant as set forth in claim 4 wherein said computer speed control functions automatically during startup and said computer further includes means for disabling operator speed demand changes from application to said speed controls during automatic startup of said turbines to synchronous speed.
Claim 8
Dependent Claim 31 words
A combined cycle electric power plant as set forth in claim 1 wherein predetermined permissive conditions must be satisfied before automatic synchronization is enabled for each turbine-generator selected for automatic synchronization.
Claim 9
Dependent Claim 251 words
A control system for controlling the operation of gas and steam turbine generators in a combined cycle electric power plant comprising a speed control for said gas turbine and a speed control for said steam turbine, means for regulating the field voltage of each of said generators during its startup, circuit breaker means for connecting each of said generators to a power system line, means for generating signals representing each generator voltage and frequency and each line voltage and frequency, an operator station having an automatic/manual synchronization selector switch and means for generating speed change and voltage change demand signals for each turbine-generator when it is selected for manual synchronization, means responsive to said voltage and frequency signals for automatically generating voltage change and turbine speed change outputs for implementation by the associated ones of said turbine speed controls and said field voltage regulating means when an automatic synchronization signal is generated by said selector switch and the associated generator is being synchronized, means for automatically generating a breaker close signal for each breaker means during synchronization of the associated generator on voltage and speed matches in the automatic synchronization mode, means for uncoupling the automatic synchronizing control paths and for coupling the speed and voltage change demand signals from said operator station to the selected turbine-generator when a manual synchronization signal is generated by said selector switch, and means for generating a closing signal from the operator station for the breaker means associated with the generator selected for manual synchronization.
Claim 10
Dependent Claim 251 words
A control system for controlling the operation of gas and steam turbine generators in a combined cycle electric power plant comprising a speed control for said gas turbine and a speed control for said steam turbine, means for regulating the field voltage of each of said generators during its startup, circuit breaker means for connecting each of said generators to a power system line, means for generating signals representing each generator voltage and frequency and each line voltage and frequency, an operator station having an automatic/manual synchronization selector switch and means for generating speed change and voltage change demand signals for each turbine-generator when it is selected for manual synchronization, means responsive to said voltage and frequency signals for automatically generating voltage change and turbine speed change outputs for implementation by the associated ones of said turbine speed controls and said field voltage regulating means when an automatic synchronization signal is generated by said selector switch and the associated generator is being synchronized, means for automatically generating a breaker close signal for each breaker means during synchronization of the associated generator on voltage and speed matches in the automatic synchronization mode, means for uncoupling the automatic synchronizing control paths and for coupling the speed and voltage change demand signals from said operator station to the selected turbine-generator when a manual synchronization signal is generated by said selector switch, and means for generating a closing signal from the operator station for the breaker means associated with the generator selected for manual synchronization.
Claim 11
Dependent Claim 44 words
A control system as set forth in claim 8 wherein means are provided for sequentially operating said automatic generating means to implement field voltage changes and turbine speed changes for sequential automatic synchronization of the turbine generators for which automatic synchronization has been specified.
Claim 12
Dependent Claim 82 words
A control system as set forth in claim 8 wherein a digital computer is included as a part of said controlling means, means are provided for controlling the fuel flow to said gas turbine and the inlet steam flow to said steam turbine, said computer includes said turbine speed controls to generate fuel and steam control signals for said fuel and inlet steam controlling means, and said computer includes means for applying synchronizing speed change signals to said turbine speed controlling means.
Claim 13
Dependent Claim 56 words
A control system as set forth in claim 10 wherein said operator station includes a keyboard for entering speed demand changes into said computer, and said computer includes means for disabling operator speed demand changes from application to said speed control during gas or steam turbine-generator synchronization for which automatic synchronization has been specified or selected.
Claim 14
Dependent Claim 69 words
A control system as set forth in claim 10 wherein said computer speed controls include means for generating a speed demand, means for generating a speed reference, means for generating a speed error from the speed reference and actual turbine speed, means for applying automatic synchronization speed changes as reference changes, and means for setting the speed demand equal to the speed reference when synchronization speed reference changes occur.
Claim 15
Dependent Claim 45 words
A control system as set forth in claim 10 wherein said computer speed control functions automatically during startup and said computer further includes means for disabling operator speed demand changes from application to said speed controls during automatic startup of said turbines to synchronous speed.
Claim 16
Dependent Claim 28 words
A control system as set forth in claim 8 wherein predetermined permissive conditions must be satisfied before automatic synchronization is enabled for each turbine-generator selected for automatic synchronization.

References Cited (Backward Citations)

US3446014A Cited
US3675426A Cited
US3762162A Cited
US3892975A Cited
US3879616A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1980-06-27 1980-12-27 1981-06-28 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1984-06-27 1984-12-27 1985-06-28 $3760.00 Window Closed / Lapsed