← Back to Patent Explorer
US4030307A Expired / Lapsed US ⏱️ 0.0 years remaining

Impermeable ecological barrier and process of making same from reconstituted shale

Assignee: Individual
•
Filing: 1976-06-14
•
Granted: 1977-06-21
•
Expires: 1996-06-14
📄 Original PDF 🌐 Google Patents 🔄 Sync Now

Abstract

Abstract An ecologically acceptable liquid-impermeable geologic barrier is made from shale. In the process described, the preferred shale is Brainard Shale, the upper shale formation in the Maquoketa Group, which is excavated to expose solid, unweathered shale in its original sedimentary state. The Brainard shale is removed by a suitable mining operaton and crushed into an aggregate which can be readily compacted. Water is added and the shale aggregate is thoroughly mixed to uniformly disperse the water. It is immediately spread in a layer of uniform thickness along a wall to be sealed and worked and further mixed in place and compacted solid by multiple passes of a sheepsfoot roller. This is repeated in multiple lifts until the barrier reaches a desired total compacted thickness and width.

Inventors

  • 👤 Armen G. Avedisian

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-10-27 19:23
CPC Classifications
E; E02; E02D; E02D31/00; E02B; E02B3/00; E02B3/04; E02B3/12

Claims Analysis

Total Claims: 15
Claim 1
Independent Claim 111 words
A process for reconstituting shale to make an ecologically impermeable geologic barrier along a wall comprising the steps of: a. primarily crushing solid, as-mined shale selected from the group consisting of Maquoketa Group shale, a shale identified by the presence of Cornulite fossils in the upper part thereof, and shale which is high in illite mineral content, to produce a readily compactible aggregate having a progressive gradation of sizes; b. mixing water with said shale to provide a wetted aggregate; c. spreading said wetted aggregate along said wall; and d. secondarily crushing and mixing said wetted aggregate in place against said wall to compact it to a substantially solid, impermeable state.
Claim 2
Dependent Claim 111 words
A process for reconstituting shale to make an ecologically impermeable geologic barrier along a wall comprising the steps of: a. primarily crushing solid, as-mined shale selected from the group consisting of Maquoketa Group shale, a shale identified by the presence of Cornulite fossils in the upper part thereof, and shale which is high in illite mineral content, to produce a readily compactible aggregate having a progressive gradation of sizes; b. mixing water with said shale to provide a wetted aggregate; c. spreading said wetted aggregate along said wall; and d. secondarily crushing and mixing said wetted aggregate in place against said wall to compact it to a substantially solid, impermeable state.
Claim 3
Dependent Claim 27 words
A process according to claim 1 in which said barrier is compacted to a coefficient of permeability of less than 5 × 10.sup. -8 centimeters per second.
Claim 4
Dependent Claim 25 words
A process according to claim 1 in which said aggregate has a gradation of sizes progressively varying from plus 3/4 inch to minus 200 mesh.
Claim 5
Dependent Claim 20 words
A process according to claim 1 in which the largest size of said aggregate passes through a 1 -inch screen.
Claim 6
Dependent Claim 62 words
An ecologically impermeable geologic barrier for a ground cavity including bottom and side walls comprising compacted reconstituted shale disposed along at least the side walls of said cavity, said shale selected from the group consisting of Maguoketa Group shale, a shale identified by the presence of Cornulite fossils in the upper part thereof, and shale which is high in illite mineral content.
Claim 7
Dependent Claim 62 words
An ecologically impermeable geologic barrier for a ground cavity including bottom and side walls comprising compacted reconstituted shale disposed along at least the side walls of said cavity, said shale selected from the group consisting of Maguoketa Group shale, a shale identified by the presence of Cornulite fossils in the upper part thereof, and shale which is high in illite mineral content.
Claim 8
Dependent Claim 44 words
An ecologically impermeable geologic barrier according to claim 5 wherein the bottom wall of said ground cavity is comprised of said shale in its natural solid state, said shale having a coefficient of permeability of less than 5 × 10.sup. -8 centimeters per second.
Claim 9
Dependent Claim 91 words
A process for reconstituting shale to make an ecologically impermeable geologic barrier along a wall comprising the steps of: a. primarily crushing solid, as-mined shale identified by the presence of Cornulite fossils in the upper part thereof, to produce a readily compactible aggregate having a progressive gradation of sizes; b. mixing water with said shale to provide a wetted aggregate; c. spreading said wetted aggregate along said wall; and d. secondarily crushing and mixing said wetted aggregate in place against said wall to compact it to a substantially solid, impermeable state.
Claim 10
Dependent Claim 91 words
A process for reconstituting shale to make an ecologically impermeable geologic barrier along a wall comprising the steps of: a. primarily crushing solid, as-mined shale identified by the presence of Cornulite fossils in the upper part thereof, to produce a readily compactible aggregate having a progressive gradation of sizes; b. mixing water with said shale to provide a wetted aggregate; c. spreading said wetted aggregate along said wall; and d. secondarily crushing and mixing said wetted aggregate in place against said wall to compact it to a substantially solid, impermeable state.
Claim 11
Dependent Claim 84 words
A process for reconstituting shale to make an ecologically impermeable geologic barrier along a wall comprising the steps of: a. primarily crushing solid, as-mined shale high in illite mineral content, to produce a readily compactible aggregate having a progressive gradation of sizes; b. mixing water with said shale to provide a wetted aggregate; c. spreading said wetted aggregate along said wall; and d. secondarily crushing and mixing said wetted aggregate in place against said wall to compact it to a substantially solid, impermeable state.
Claim 12
Dependent Claim 84 words
A process for reconstituting shale to make an ecologically impermeable geologic barrier along a wall comprising the steps of: a. primarily crushing solid, as-mined shale high in illite mineral content, to produce a readily compactible aggregate having a progressive gradation of sizes; b. mixing water with said shale to provide a wetted aggregate; c. spreading said wetted aggregate along said wall; and d. secondarily crushing and mixing said wetted aggregate in place against said wall to compact it to a substantially solid, impermeable state.
Claim 13
Dependent Claim 81 words
A process for reconstituting shale to make an ecologically impermeable geologic barrier along a wall comprising the steps of: a. primarily crushing solid, as-mined Maquoketa Group shale, to produce a readily compactible aggregate having a progressive gradation of sizes; b. mixing water with said shale to provide a wetted aggregate; c. spreading said wetted aggregate along said wall; and d. secondarily crushing and mixing said wetted aggregate in place against said wall to compact it to a substantially solid, impermeable state.
Claim 14
Dependent Claim 81 words
A process for reconstituting shale to make an ecologically impermeable geologic barrier along a wall comprising the steps of: a. primarily crushing solid, as-mined Maquoketa Group shale, to produce a readily compactible aggregate having a progressive gradation of sizes; b. mixing water with said shale to provide a wetted aggregate; c. spreading said wetted aggregate along said wall; and d. secondarily crushing and mixing said wetted aggregate in place against said wall to compact it to a substantially solid, impermeable state.
Claim 15
Dependent Claim 19 words
A process according to claim 9 in which said shale is from the Brainard Formation of the Maquoketa Group.

References Cited (Backward Citations)

US2929219A Cited
US3614867A Cited
US3898844A Cited
US3732697A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1980-06-20 1980-12-20 1981-06-21 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1984-06-20 1984-12-20 1985-06-21 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 1988-06-20 1988-12-20 1989-06-21 $7700.00 Window Closed / Lapsed

Assigned Categories & Tags

No categories assigned to this patent yet.

Assign Category Tag