US4018671A
Expired / Lapsed
US
⏱️ 0.0 years remaining
Intermittent catalyst addition system
Assignee: Marathon Oil Co
•
Filing: 1975-01-14
•
Granted: 1977-04-19
•
Expires: 1995-01-14
Abstract
Abstract Catalyst, e.g., for a fluid catalytic cracker, is added automatically by a system consisting of an addition hopper which is periodically fed by gravity from a storage hopper, sealed off from the supply, and then pressurized with air to discharge its contents to the carrier gas line feeding the hydrocarbon conversion unit, e.g., the regenerator section of a Fluid Catalytic Cracking Unit. Sequencing can be by electronic timer-solenoid (or pneumatic) valve system.
Inventors
- 👤 Nicholaki A. Andon
- 👤 Robert I. Fleece
Bibliographic Details
Application Number
—
Jurisdiction
US
Data Source
google_patents
Last Synchronized
2026-10-26 22:05
CPC Classifications
B; B01; B01J; B01J8/00; B01J8/0015; B01J8/0035; C; C10; C10G; C10G11/00; C10G11/14; C10G11/18; C10G11/187; B01J2208/00; B01J2208/00743; B01J2208/00752
Claims Analysis
Total Claims: 7
Claim 1
Independent Claim
264 words
In the catalytic conversion of feed materials by contacting said feed materials in a converter system with catalyst in a fluidized state, some of which catalyst is lost from said catalytic cracking process through reduced activity and/or entrainment in the effluent from said process, the improvement comprising: a. storing said catalyst in a storage tank maintained at a first internal pressure and having a conduit communicating through a storage valve with an addition hopper; b. maintaining said addition hopper at a pressure corresponding substantially to said first pressure of said storage tank by operation of a venting means and opening said storage valve to admit said catalyst to a predetermined level in said addition hopper, said addition hopper communicating through an addition valve to a carrier gas line leading to said converter; c. closing said venting means and pressurizing said addition hopper to a second addition pressure; d. thereafter opening said addition valve and permitting said addition hopper to empty into said carrier gas line; e. after emptying of said addition hopper, closing said addition valve, opening said venting means to reduce the pressure in said addition hopper to said first pressure, and opening said storage valve to admit additional catalyst to fill said addition hopper to a predetermined level determined by the volume of said addition hopper; f. thereafter closing said venting means, closing said storage valve and admitting additional gases to raise the pressure of said addition hopper to said addition pressure; g. thereafter opening said addition valve to admit additional catalyst to said carrier gas line and repeating the above cycle.
Claim 2
Dependent Claim
264 words
In the catalytic conversion of feed materials by contacting said feed materials in a converter system with catalyst in a fluidized state, some of which catalyst is lost from said catalytic cracking process through reduced activity and/or entrainment in the effluent from said process, the improvement comprising: a. storing said catalyst in a storage tank maintained at a first internal pressure and having a conduit communicating through a storage valve with an addition hopper; b. maintaining said addition hopper at a pressure corresponding substantially to said first pressure of said storage tank by operation of a venting means and opening said storage valve to admit said catalyst to a predetermined level in said addition hopper, said addition hopper communicating through an addition valve to a carrier gas line leading to said converter; c. closing said venting means and pressurizing said addition hopper to a second addition pressure; d. thereafter opening said addition valve and permitting said addition hopper to empty into said carrier gas line; e. after emptying of said addition hopper, closing said addition valve, opening said venting means to reduce the pressure in said addition hopper to said first pressure, and opening said storage valve to admit additional catalyst to fill said addition hopper to a predetermined level determined by the volume of said addition hopper; f. thereafter closing said venting means, closing said storage valve and admitting additional gases to raise the pressure of said addition hopper to said addition pressure; g. thereafter opening said addition valve to admit additional catalyst to said carrier gas line and repeating the above cycle.
Claim 3
Dependent Claim
21 words
A process according to claim 1 wherein the duration of opening of each of said valves is controlled by timing means.
Claim 4
Dependent Claim
21 words
A process according to claim 2 wherein the position of each of said valves is controlled by a sequencing control center.
Claim 5
Dependent Claim
59 words
A process according to claim 1 wherein said addition valve is closed substantially whenever said storage valve is open and wherein said storage valve is closed substantially whenever said addition valve is open, and wherein said venting means is open whenever said storage valve is open and wherein said storage valve is closed whenever said venting means is closed.
Claim 6
Dependent Claim
20 words
A process according to claim 4 wherein said venting means communicates with an upper portion of said catalyst storage tank.
Claim 7
Dependent Claim
18 words
A process according to claim 1 wherein said storage tank has a first pressure of approximately atmospheric pressure.
References Cited (Backward Citations)
US1535991A
Cited
US2786800A
Cited
US2892773A
Cited
US3090593A
Cited
US3156537A
Cited
US3479093A
Cited
US3850582A
Cited
USPTO Annuity & Maintenance Windows
| Annuity Stage | Window Opens | Payment Deadline | Surcharge Period Until | Estimated Fee | Status |
|---|---|---|---|---|---|
| 3.5 Years (Year 4) | 1980-04-18 | 1980-10-18 | 1981-04-19 | $2000.00 | Window Closed / Lapsed |
| 7.5 Years (Year 8) | 1984-04-18 | 1984-10-18 | 1985-04-19 | $3760.00 | Window Closed / Lapsed |
| 11.5 Years (Year 12) | 1988-04-18 | 1988-10-18 | 1989-04-19 | $7700.00 | Window Closed / Lapsed |