Abstract

Abstract A platform is raised from water level up to the tops of prepositioned template legs by means of jacking units comprising jacking mechanisms and jacking legs mounted near the upper ends of the template legs and extending down to the platform. Bridge beams of open framework construction span the distances between the upper ends of the template legs and these bridge beams provide support for the jacking units as well as reinforcement for the platform when it has been raised.

Inventors

  • 👤 Lindsey J. Phares
  • 👤 George J. Gendron

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-11-08 02:22
CPC Classifications
E; E02; E02B; E02B17/00; E02B17/02; E02B17/025; E02B17/027; E02B2017/0039; E02B2017/0043; E02B2017/0047; E02B2017/0056; E02B2017/0069; E02B2017/0073; E02B2017/0086

Claims Analysis

Total Claims: 6
Claim 1
Independent Claim 110 words
A method of erecting an offshore tower, said method comprising the steps of positioning a template, having at least one vertical template leg, on a sea floor so that said vertical leg extends up above the sea level, said template being provided with jacking mechanism mounting means connected to the upper end of said template leg, moving a platform into position adjacent the template leg; connecting at least one jacking leg to extend down from an associated jacking mechanism on said mounting means and to be connected to said platform and then operating said jacking mechanism to pull said jacking leg upwardly to raise said platform clear of the water.
Claim 2
Independent Claim 110 words
A method of erecting an offshore tower, said method comprising the steps of positioning a template, having at least one vertical template leg, on a sea floor so that said vertical leg extends up above the sea level, said template being provided with jacking mechanism mounting means connected to the upper end of said template leg, moving a platform into position adjacent the template leg; connecting at least one jacking leg to extend down from an associated jacking mechanism on said mounting means and to be connected to said platform and then operating said jacking mechanism to pull said jacking leg upwardly to raise said platform clear of the water.
Claim 3
Dependent Claim 29 words
A method of erecting an offshore tower according to claim 1 wherein said jacking mechanism is provided on said template prior to positioning said template on the sea floor.
Claim 4
Dependent Claim 32 words
A method of erecting an offshore tower according to claim 1 wherein said template is positioned by floating same to a predetermined location in the sea, with said jacking mechanism secured thereto.
Claim 5
Dependent Claim 125 words
An offshore tower construction comprising a template constructed to be anchored to a sea floor, said template including at least one vertical template leg which extends up above the surface of the sea when said template is secured to the sea floor, a mounting member connected to the upper end of at least said one template leg, a platform member constructed to be positioned adjacent said template leg and to be lifted upwardly therealong clear of the water, a jacking mechanism secured to said mounting means on said template leg and a jacking leg extending from said jacking mechanism down to said platform and secured thereto whereby operation of said jacking mechanism pulls up said jacking leg and lifts said platform clear of the water.
Claim 6
Dependent Claim 125 words
An offshore tower construction comprising a template constructed to be anchored to a sea floor, said template including at least one vertical template leg which extends up above the surface of the sea when said template is secured to the sea floor, a mounting member connected to the upper end of at least said one template leg, a platform member constructed to be positioned adjacent said template leg and to be lifted upwardly therealong clear of the water, a jacking mechanism secured to said mounting means on said template leg and a jacking leg extending from said jacking mechanism down to said platform and secured thereto whereby operation of said jacking mechanism pulls up said jacking leg and lifts said platform clear of the water.

References Cited (Backward Citations)

US2941369A Cited
US2857744A Cited
US3874180A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1980-01-11 1980-07-12 1981-01-11 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1984-01-11 1984-07-12 1985-01-11 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 1988-01-11 1988-07-12 1989-01-11 $7700.00 Window Closed / Lapsed