US4001674A
Expired / Lapsed
US
⏱️ 0.0 years remaining
Method of testing the voltage withstand ability of a high voltage d-c cable at a voltage higher than its normal operating voltage while carrying current
Abstract A high voltage d-c cable is tested by first disconnecting the normally-grounded sheath of the cable from ground and providing insulation between the sheath and ground. The sheath is then biased to a predetermined bias voltage that is of an opposite polarity with respect to ground as the normal operating voltage of the cable conductor. The conductor is then energized with current and test voltage derived from its normal source. This test voltage is of the same polarity with respect to ground as the normal operating voltage of the cable conductor and of a magnitude approximating said normal operating voltage, whereby the difference between said test voltage and said bias voltage is applied to the cable insulation between the cable conductor and sheath.
A method of testing a high voltage d-c cable at a voltage higher than its normal operating voltage while said cable is carrying current from its normal source of energization, said d-c cable comprising: a conductor for carrying said current that is normally operated at a predetermined voltage and polarity with respect to ground, a metal sheath surrounding said conductor that is normally at ground potential, and dielectric material between said conductor and said sheath that is stressed by the voltage present between said conductor and said sheath, said method comprising the steps of: a. disconnecting said sheath from ground and providing insulation between said sheath and ground, b. electrically biasing said sheath to a predetermined bias voltage with respect to ground, said bias voltage being of an opposite polarity with respect to ground as the normal operating voltage of said source, c. energizing said conductor with current and test voltage derived from said normal source, said test voltage being of the same polarity with respect to ground as said normal operating voltage and of a magnitude approximating that of said normal operating voltage, whereby the difference between said test voltage and said bias voltage is applied to said dielectric material, and d. monitoring the condition of said dielectric material after said conductor has been energized as in (c) and said difference voltage has been applied to said dielectric material so as to determine whether said dielectric material can withstand said difference voltage without a breakdown while said conductor is carrying said current.
Claim 2
Independent Claim
253 words
A method of testing a high voltage d-c cable at a voltage higher than its normal operating voltage while said cable is carrying current from its normal source of energization, said d-c cable comprising: a conductor for carrying said current that is normally operated at a predetermined voltage and polarity with respect to ground, a metal sheath surrounding said conductor that is normally at ground potential, and dielectric material between said conductor and said sheath that is stressed by the voltage present between said conductor and said sheath, said method comprising the steps of: a. disconnecting said sheath from ground and providing insulation between said sheath and ground, b. electrically biasing said sheath to a predetermined bias voltage with respect to ground, said bias voltage being of an opposite polarity with respect to ground as the normal operating voltage of said source, c. energizing said conductor with current and test voltage derived from said normal source, said test voltage being of the same polarity with respect to ground as said normal operating voltage and of a magnitude approximating that of said normal operating voltage, whereby the difference between said test voltage and said bias voltage is applied to said dielectric material, and d. monitoring the condition of said dielectric material after said conductor has been energized as in (c) and said difference voltage has been applied to said dielectric material so as to determine whether said dielectric material can withstand said difference voltage without a breakdown while said conductor is carrying said current.
Claim 3
Dependent Claim
28 words
The method of claim 1 in which said cable is placed in a support mounted on said insulation prior to electrically biasing said sheath to said predetermined voltage.
Claim 4
Dependent Claim
54 words
The method of claim 1 in which said test is performed in a system comprising said source and a load connected in series with said cable, said source and said load being subjected during said test to only said test voltage and not to the difference between said test voltage and said bias voltage.