Electric power plant having a gas turbine with an improved wide range surge protection system

Assignee: Westinghouse Electric Corp
•
Filing: 1974-08-08
•
Granted: 1976-08-31
•
Expires: 1994-08-08
📄 Original PDF 🌐 Google Patents 🔄 Sync Now

Abstract

Abstract A combined cycle electric power plant includes gas and steam turbines and steam generators and a digital/analog control system. A surge protection system is included as part of the analog portion of the control system, and it functions in both automatic and manual modes of operation. A surge protection signal is generated to limit fuel demand as a function of speed during startup and as a function of combustor shell pressure during higher speed load operation.

Inventors

  • 👤 Jack R. Smith

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-11-04 07:01
CPC Classifications
F; F04; F04D; F04D27/00; F04D27/02; F04D27/0284; F01; F01K; F01K13/00; F01K13/02; F01K23/00; F01K23/02; F01K23/06; F01K23/10; F01K23/103; F01K23/105; Y; Y02; Y02E; Y02E20/00; Y02E20/16

Claims Analysis

Total Claims: 24
Claim 1
Independent Claim 157 words
A gas turbine electric power plant comprising compressor section and a turbine section, a plurality of combustors for energizing the driving gas flow for the turbine section, means for generating electric power under the driving power of the turbine, a gas turbine control system having means for generating an electric fuel reference signal to control the turbine speed and load, at least one throttle valve for said gas turbine, means for controlling the position of said throttle valve to control the flow of fuel to the gas turbine in response to the fuel reference signal from said speed and load controlling means, means for generating an electric signal representative of the turbine speed, means for generating an electric signal representative of combustor shell pressure, and means for generating a surge limit signal in response to said speed and pressure signal generating means to limit the fuel flow and avoid compressor surge in accordance with a predetermined characterization.
Claim 2
Dependent Claim 157 words
A gas turbine electric power plant comprising compressor section and a turbine section, a plurality of combustors for energizing the driving gas flow for the turbine section, means for generating electric power under the driving power of the turbine, a gas turbine control system having means for generating an electric fuel reference signal to control the turbine speed and load, at least one throttle valve for said gas turbine, means for controlling the position of said throttle valve to control the flow of fuel to the gas turbine in response to the fuel reference signal from said speed and load controlling means, means for generating an electric signal representative of the turbine speed, means for generating an electric signal representative of combustor shell pressure, and means for generating a surge limit signal in response to said speed and pressure signal generating means to limit the fuel flow and avoid compressor surge in accordance with a predetermined characterization.
Claim 3
Dependent Claim 58 words
A gas turbine electric power plant as set forth in claim 1 wherein the predetermined characterization is provided by means for generating a surge speed function which is operative from ignition speed to a higher turbine speed value and a pressure surge function which is operative from the higher turbine speed value to the maximum load operating level.
Claim 4
Dependent Claim 28 words
A gas turbine electric power plant as set forth in claim 2 wherein the crossover point of the two functions is at a speed less than synchronous speed.
Claim 5
Dependent Claim 50 words
A gas turbine electric power plant as set forth in claim 2 wherein said function generating means includes a proportional function generator for generating a straight line pressure surge function and a proportional controller for generating a speed surge function having at least two straight line parts with different slopes.
Claim 6
Dependent Claim 50 words
A gas turbine electric power plant as set forth in claim 1 wherein said speed signal generating means includes at least two speed transducers and means are provided for detecting the highest of the two signals generated by said speed transducers for application to said surge limit signal generating means.
Claim 7
Dependent Claim 39 words
A gas turbine electric power plant as set forth in claim 2 wherein means are provided for selecting the highest of the two outputs generated by the pressure surge and speed surge function generators for limiting the fuel flow.
Claim 8
Dependent Claim 76 words
A gas turbine electric power plant as set forth in claim 4 wherein said speed signal generating means includes at least two speed transducers, means are provided for detecting the highest of the two signals generated by said speed transducers for application to said surge limit signal generating means, and means are provided for selecting the highest of the two outputs generated by the pressure surge and speed surge function generators for limiting the fuel flow.
Claim 9
Dependent Claim 186 words
A combined cycle electric power plant comprising at least one gas turbine, means for generating steam in response to heat energy from said gas turbine, a steam turbine driven by steam supply to it from said steam generating means, means for generating electric power under the driving power of said turbines, means for controlling the operation of said turbines and said steam generating means, said controlling means including a gas turbine control system having means for generating an electric fuel reference signal to control the turbine speed and load, at least one throttle valve for said gas turbine, means for controlling the position of said throttle valve to control the flow of fuel to the gas turbine in response to the fuel reference signal from said speed and load controlling means, means for generating an electric signal representative of the turbine speed, means for generating an electric signal representative of combustor shell pressure, and means for generating a surge limit signal in response to said speed and pressure signal generating means to limit the fuel flow and avoid compressor surge in accordance with a predetermined characterization.
Claim 10
Dependent Claim 186 words
A combined cycle electric power plant comprising at least one gas turbine, means for generating steam in response to heat energy from said gas turbine, a steam turbine driven by steam supply to it from said steam generating means, means for generating electric power under the driving power of said turbines, means for controlling the operation of said turbines and said steam generating means, said controlling means including a gas turbine control system having means for generating an electric fuel reference signal to control the turbine speed and load, at least one throttle valve for said gas turbine, means for controlling the position of said throttle valve to control the flow of fuel to the gas turbine in response to the fuel reference signal from said speed and load controlling means, means for generating an electric signal representative of the turbine speed, means for generating an electric signal representative of combustor shell pressure, and means for generating a surge limit signal in response to said speed and pressure signal generating means to limit the fuel flow and avoid compressor surge in accordance with a predetermined characterization.
Claim 11
Dependent Claim 58 words
A combined cycle electric power plant as set forth in claim 8 wherein the predetermined characterization is provided by means for generating a surge speed function which is operative from ignition speed to a higher turbine speed value and a pressure surge function which is operative from the higher turbine speed value to the maximum load operating level.
Claim 12
Dependent Claim 28 words
A combined cycle electric power plant as set forth in claim 9 wherein the crossover point of the two functions is at a speed less than synchronous speed.
Claim 13
Dependent Claim 50 words
A combined cycle electric power plant as set forth in claim 9 wherein said function generating means includes a proportional function generator for generating a straight line pressure surge function and a proportional controller for generating a speed surge function having at least two straight line parts with different slopes.
Claim 14
Dependent Claim 50 words
A combined cycle electric power plant as set forth in claim 8 wherein said speed signal generating means includes at least two speed transducers and means are provided for detecting the highest of the two signals generated by said speed transducers for application to said surge limit signal generating means.
Claim 15
Dependent Claim 39 words
A combined cycle electric power plant as set forth in claim 9 wherein means are provided for selecting the highest of the two outputs generated by the pressure surge and speed surge function generators for limiting the fuel flow.
Claim 16
Dependent Claim 76 words
A combined cycle electric power plant as set forth in claim 11 wherein said speed signal generating means includes at least two speed transducers, means are provided for detecting the highest of the two signals generated by said speed transducers for application to said surge limit signal generating means, and means are provided for selecting the highest of the two outputs generated by the pressure surge and speed surge function generators for limiting the fuel flow.
Claim 17
Dependent Claim 108 words
A control system for an electric power plant gas turbine having a throttle valve comprising means for generating an electric fuel reference signal to control the turbine speed and load, means for controlling the position of the turbine throttle valve to control the flow of fuel to said gas turbine in response to the fuel reference signal from said speed and load controlling means, means for generating an electric signal representative of combustor shell pressure, and means for generating a surge limit signal in response to said speed and pressure signal generating means to limit the fuel flow and avoid compressor surge in accordance with a predetermined characterization.
Claim 18
Dependent Claim 108 words
A control system for an electric power plant gas turbine having a throttle valve comprising means for generating an electric fuel reference signal to control the turbine speed and load, means for controlling the position of the turbine throttle valve to control the flow of fuel to said gas turbine in response to the fuel reference signal from said speed and load controlling means, means for generating an electric signal representative of combustor shell pressure, and means for generating a surge limit signal in response to said speed and pressure signal generating means to limit the fuel flow and avoid compressor surge in accordance with a predetermined characterization.
Claim 19
Dependent Claim 55 words
A control system as set forth in claim 15 wherein the predetermined characterization is provided by means for generating a surge speed function which is operative from ignition speed to a higher turbine speed value and a pressure surge function which is operative from the higher turbine speed value to the maximum load operating level.
Claim 20
Dependent Claim 25 words
A control system as set forth in claim 16 wherein the crossover point of the two functions is at a speed less than synchronous speed.
Claim 21
Dependent Claim 47 words
A control system as set forth in claim 16 wherein said function generating means includes a proportional function generator for generating a straight line pressure surge function and a proportional controller for generating a speed surge function having at least two straight line parts with different slopes.
Claim 22
Dependent Claim 48 words
A control system as set forth in claim 15 wherein said speed signal generating means includes at least two speed transducers and a means are provided for detecting the highest of the two signals generated by said speed transducers for application to said surge limit signal generating means.
Claim 23
Dependent Claim 36 words
A control system as set forth in claim 15 wherein means are provided for selecting the highest of the two outputs generated by the pressure surge and speed surge function generators for limiting the fuel flow.
Claim 24
Dependent Claim 73 words
A control system as set forth in claim 18 wherein said speed signal generating means includes at least two speed transducers, means are provided for detecting the highest of the two signals generated by said speed transducers for application to said surge limit signal generating means, and means are provided for selecting the highest of the two outputs generated by the pressure surge and speed surge function generators for limiting the fuel flow.

References Cited (Backward Citations)

US3255586A Cited
US3421317A Cited
US3422800A Cited
US3520133A Cited
US3691759A Cited
US3729929A Cited
US3854287A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1979-08-31 1980-03-01 1980-08-31 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1983-08-31 1984-03-01 1984-08-31 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 1987-08-31 1988-03-01 1988-08-31 $7700.00 Window Closed / Lapsed