Abstract

Abstract A process for manufacturing helium metal vapor laser tubes having an extended life characteristic. Three main areas of processing are presented which extend the life expectancy of a helium metal vapor laser tube. The first area of processing is directed to a time bake under vacuum of the tube to be used; the second is directed to the melting of the metal in an argon atmosphere; and the third area is directed to a final burn-in procedure of the helium metal vapor laser using the manufactured helium metal vapor tube.

Inventors

  • 👤 William A. Shull

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-10-26 12:13
CPC Classifications
H; H01; H01S; H01S3/00; H01S3/02; H01S3/03; H01S3/031

Claims Analysis

Total Claims: 20
Claim 1
Independent Claim 94 words
A process for manufacturing a helium metal vapor laser comprising the steps of: providing a laser tube having a cathode, Brewster windows and and a metal reservoir intermediate its ends; filling the metal reservoir with metal; evacuating said tube; baking said tube at a temperature of approximately 100°C for at least 10 hours; backfilling said tube with argon; melting the metal in the metal reservoir; backfilling said tube with helium gas; sealing said tube; mounting said tube in a resonator to form a laser; and aligning said tube in said resonator for lasing operation.
Claim 2
Dependent Claim 94 words
A process for manufacturing a helium metal vapor laser comprising the steps of: providing a laser tube having a cathode, Brewster windows and and a metal reservoir intermediate its ends; filling the metal reservoir with metal; evacuating said tube; baking said tube at a temperature of approximately 100°C for at least 10 hours; backfilling said tube with argon; melting the metal in the metal reservoir; backfilling said tube with helium gas; sealing said tube; mounting said tube in a resonator to form a laser; and aligning said tube in said resonator for lasing operation.
Claim 3
Dependent Claim 32 words
A process for manufacturing a helium metal vapor laser as recited in claim 1 wherein during the argon backfilling step the tube is filled to a pressure of at least 12 Torr.
Claim 4
Dependent Claim 107 words
A process for manufacturing a helium metal vapor laser tube comprising the steps of: providing a laser tube having a metal reservoir intermediate its ends; filling the metal reservoir with metal; evacuating the tube; baking said tube at a temperature of approximately 100°C for at least 10 hours; backfilling said tube with argon; melting the metal in the metal reservoir; backfilling said tube with helium gas; sealing said tube; mounting said tube in a resonator to form a laser; aligning said tube in said resonator for lasing operation; and operating said laser within one hour after sealing said tube for a period of 20 to 40 hours.
Claim 5
Dependent Claim 107 words
A process for manufacturing a helium metal vapor laser tube comprising the steps of: providing a laser tube having a metal reservoir intermediate its ends; filling the metal reservoir with metal; evacuating the tube; baking said tube at a temperature of approximately 100°C for at least 10 hours; backfilling said tube with argon; melting the metal in the metal reservoir; backfilling said tube with helium gas; sealing said tube; mounting said tube in a resonator to form a laser; aligning said tube in said resonator for lasing operation; and operating said laser within one hour after sealing said tube for a period of 20 to 40 hours.
Claim 6
Dependent Claim 29 words
A process for manufacturing a helium metal vapor laser tube as recited in claim 3 wherein said argon is at a pressure of 12 Torr after said argon backfilling.
Claim 7
Dependent Claim 33 words
A process for manufacturing a helium metal vapor laser tube as recited in claim 3 wherein said helium 3 gas is at a pressure of approximately 5.5 Torr after said helium 3 backfilling.
Claim 8
Dependent Claim 193 words
A process for manufacturing a helium metal vapor laser tube comprising the steps of: providing a laser tube having a cathode and a metal reservoir intermediate its ends; filling the metal reservoir with metal; cleaning said tube; attaching said tube to a vacuum system; evacuating said tube; baking said tube at a temperature of approximately 100°C for at least 10 hours; evacuating said tube; backfilling said tube with oxygen; heating the cathode to form an active cathode surface; evacuating said tube; backfilling said tube with a mixture of neon and helium 4 ; striking a discharge in said tube to remove water vapor; evacuating said tube; backfilling said tube with argon; melting the metal in the metal reservoir of said tube; evacuating said tube; backfilling said tube with helium 4 ; striking a discharge in said tube; evacuating said tube; backfilling said tube with helium 3 ; sealing said tube to remove said tube from said vacuum system; mounting said tube in a resonator to form a laser; aligning said tube in said resonator for lasing operation; and operating said laser within 1 hour after sealing said tube for 20 to 40 hours.
Claim 9
Dependent Claim 193 words
A process for manufacturing a helium metal vapor laser tube comprising the steps of: providing a laser tube having a cathode and a metal reservoir intermediate its ends; filling the metal reservoir with metal; cleaning said tube; attaching said tube to a vacuum system; evacuating said tube; baking said tube at a temperature of approximately 100°C for at least 10 hours; evacuating said tube; backfilling said tube with oxygen; heating the cathode to form an active cathode surface; evacuating said tube; backfilling said tube with a mixture of neon and helium 4 ; striking a discharge in said tube to remove water vapor; evacuating said tube; backfilling said tube with argon; melting the metal in the metal reservoir of said tube; evacuating said tube; backfilling said tube with helium 4 ; striking a discharge in said tube; evacuating said tube; backfilling said tube with helium 3 ; sealing said tube to remove said tube from said vacuum system; mounting said tube in a resonator to form a laser; aligning said tube in said resonator for lasing operation; and operating said laser within 1 hour after sealing said tube for 20 to 40 hours.
Claim 10
Dependent Claim 43 words
A process for manufacturing a helium metal vapor laser tube as recited in claim 6 wherein said tube includes Brewster windows, said process further including the step of raising shields within said tube to protect said Brewster windows prior to said baking step.
Claim 11
Dependent Claim 30 words
A process for manufacturing a helium metal vapor laser tube as recited in claim 7 and further comprising the step of: lowering said shields after said sealing of said tube.
Claim 12
Dependent Claim 65 words
A process for manufacturing a helium metal vapor laser tube as recited in claim 6 wherein said tube includes Brewster windows, the metal reservoir includes a filler tube and said filling step includes depositing metal pellets through the filler tube; and thereafter further comprising the steps of: providing shields inside said tube to protect the Brewster windows; and sealing said filler tube near its top.
Claim 13
Dependent Claim 34 words
A process for manufacturing a helium metal vapor laser tube as recited in claim 6 wherein all said evacuation steps evacuate said tube to a pressure of less than 5 × 10.sup. -5 Torr.
Claim 14
Dependent Claim 33 words
A process for manufacturing a helium metal vapor laser tube as recited in claim 6 wherein during the oxygen backfilling step the tube is filled to a pressure of 0.5 Torr of oxygen.
Claim 15
Dependent Claim 42 words
A process for manufacturing a helium metal vapor laser tube as recited in claim 6 wherein said cathode is comprised of barium strontium carbonate and the cathode is heated sufficient to reduce said barium strontium carbonate to barium oxide and strontium oxide.
Claim 16
Dependent Claim 36 words
A process for manufacturing a helium metal vapor laser tube as recited in claim 6 wherein a mixture of 0.3 Torr of neon, and 2.7 Torr of helium 4 is used in the neon/helium backfilling step.
Claim 17
Dependent Claim 33 words
A process for manufacturing a helium metal vapor laser tube as recited in claim 6 wherein during the argon backfilling step the tube is filled to a pressure of 12 Torr of argon.
Claim 18
Dependent Claim 35 words
A process for manufacturing a helium metal vapor laser tube as recited in claim 6 wherein during the helium backfilling step the tube is filled to a pressure of 6 Torr of helium 4 .
Claim 19
Dependent Claim 27 words
A process for manufacturing a helium metal vapor laser tube as recited in claim 6 wherein the said helium 4 discharge is maintained for approximately 3 hours.
Claim 20
Dependent Claim 40 words
A process for manufacturing a helium metal vapor laser tube as recited in claim 6 wherein said step of sealing said tube comprises the sealing of a vacuum port as close to the main body of said tube as possible.

References Cited (Backward Citations)

US2844433A Cited
US3466567A Cited
US3860310A Cited
US3492598A Cited
US3624548A Cited
US3748595A Cited
US3683295A Cited
US3730606A Cited
US3720877A Cited
US3731227A Cited
US3740110A Cited
US3759602A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1979-06-01 1979-12-01 1980-06-01 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1983-06-01 1983-12-01 1984-06-01 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 1987-06-01 1987-12-01 1988-06-01 $7700.00 Window Closed / Lapsed