Claims Analysis
Total Claims: 13
Claim 1
Independent Claim
103 words
A method of developing and shaping a permeable zone within a subterranean ore deposit so that it will have a lower portion of substantially constant horizontal cross-section below a predetermined level from which it tapers upwardly to an apex to form a cone-shaped upper portion comprising the steps of: a. placing an explosive charge into the deposit adjacent said apex; b. expanding a volume of said deposit underlying said predetermined level to form said lower portion; and c. thereafter detonating said explosive charge to produce cratering of said deposit between said apex and said predetermined level so as to form said upper portion.
Claim 2
Independent Claim
103 words
A method of developing and shaping a permeable zone within a subterranean ore deposit so that it will have a lower portion of substantially constant horizontal cross-section below a predetermined level from which it tapers upwardly to an apex to form a cone-shaped upper portion comprising the steps of: a. placing an explosive charge into the deposit adjacent said apex; b. expanding a volume of said deposit underlying said predetermined level to form said lower portion; and c. thereafter detonating said explosive charge to produce cratering of said deposit between said apex and said predetermined level so as to form said upper portion.
Claim 3
Dependent Claim
24 words
A method as in claim 1 comprising placing said explosive charge within a blasting hole drilled into said deposit in a substantially vertical direction.
Claim 4
Dependent Claim
18 words
A method as in claim 2 wherein said blasting hole extends downwardly from the surface of the earth.
Claim 5
Dependent Claim
17 words
A method as in claim 2 wherein said blasting hole extends downwardly from an upper mining level.
Claim 6
Dependent Claim
19 words
A method as in claim 2 wherein said blasting hole extends upwardly from the bottom of said lower portion.
Claim 7
Dependent Claim
14 words
A method as in claim 1 wherein said ore deposit is a carbonaceous material.
Claim 8
Dependent Claim
13 words
A method as in claim 1 wherein said ore deposit is oil shale.
Claim 9
Independent Claim
146 words
A method of forming an upright retort in a subterranean ore deposit wherein the base of the deposit is partially undercut to form a cavity therebeneath connecting with the surface, a designated block of the overlaying deposit being thereafter expanded to fill said cavity, the improvement comprising the steps of: a. providing a substantially vertically directed blasting hole extending into said block so that said blasting hole lies at least partially above a predetermined level of said block; b. charging said blasting hole with a length of explosive above said intermediate level; c. explosively fragmenting the portion of said designated block below said intermediate level to effect expansion thereof into said cavity; and d. thereafter detonating the explosive in said blasting hole to produce a downwardly widening crater of fragmented material of said designated block extending from the top of said explosive to said intermediate level.
Claim 10
Independent Claim
146 words
A method of forming an upright retort in a subterranean ore deposit wherein the base of the deposit is partially undercut to form a cavity therebeneath connecting with the surface, a designated block of the overlaying deposit being thereafter expanded to fill said cavity, the improvement comprising the steps of: a. providing a substantially vertically directed blasting hole extending into said block so that said blasting hole lies at least partially above a predetermined level of said block; b. charging said blasting hole with a length of explosive above said intermediate level; c. explosively fragmenting the portion of said designated block below said intermediate level to effect expansion thereof into said cavity; and d. thereafter detonating the explosive in said blasting hole to produce a downwardly widening crater of fragmented material of said designated block extending from the top of said explosive to said intermediate level.
Claim 11
Dependent Claim
21 words
A method as in claim 8 wherein said blasting hole is approximately centered within the cross-sectional dimensions of said designated block.
Claim 12
Dependent Claim
28 words
A method as in claim 8 wherein said at least one blasting hole is connected to a source of air and fuel adapted to ignite said fragmented ore.
Claim 13
Dependent Claim
47 words
A method as in claim 8 wherein said ore deposit comprises an upper low quality layer lying above and contiguous with A lower high quality layer and wherein said intermediate level of said detonated block is situated at the interface between said low and high quality layers.