Claims Analysis
Total Claims: 7
Claim 1
Independent Claim
339 words
A method for the construction of an impermeable concrete wall in the ground, comprising the steps of excavating a first series of slots of predetermined length, width and depth along a predetermined line and of any desired shape, the first series having spaces of predetermined length between each slot, at the same time removing soil from the slots and replacing the soil with a thixotropic fluid, inserting vertical membranes in at least one end of the first series of slots with concrete to form first concrete panels such that approximately half the crosssections of each of the vertical membranes are within the first concrete panels, excavating the soil from the spaces to form a second series of slots, and at the same time replacing the soil with thixotropic fluid, filling the second series of slots with concrete to form second concrete panels such that at least one end of the second concrete panels abuts at least one end of the first concrete panels and the remaining half of the crosssections of each of the flexible membranes are within the second concrete panels, the method being further characterized in that during the pouring of the trixothropic fluid and subsequently the concrete, the membrane is supported by a steel frame bordering the end of the slot, the steel frame engaging the membrane with at least one rigid vertical edge which supports the membrane in a vertical position and slides freely vertically relative thereto so that it supports the membrane where it engages it regardless of its vertical position relative to the membrane, and including the step of removing the steel frame gradually as the concrete starts to harden at its lower end, and at essentially the same vertical rate as the concrete hardens from the bottom upwardly so that the bottom of the steel frame gradually moves above concrete hard enough to be self-supporting but not sufficiently hard to bond to the steel frame, the steel frame moving slidably along and still supporting the vertical membrane as it moves upwardly therealong.
Claim 2
Independent Claim
339 words
A method for the construction of an impermeable concrete wall in the ground, comprising the steps of excavating a first series of slots of predetermined length, width and depth along a predetermined line and of any desired shape, the first series having spaces of predetermined length between each slot, at the same time removing soil from the slots and replacing the soil with a thixotropic fluid, inserting vertical membranes in at least one end of the first series of slots with concrete to form first concrete panels such that approximately half the crosssections of each of the vertical membranes are within the first concrete panels, excavating the soil from the spaces to form a second series of slots, and at the same time replacing the soil with thixotropic fluid, filling the second series of slots with concrete to form second concrete panels such that at least one end of the second concrete panels abuts at least one end of the first concrete panels and the remaining half of the crosssections of each of the flexible membranes are within the second concrete panels, the method being further characterized in that during the pouring of the trixothropic fluid and subsequently the concrete, the membrane is supported by a steel frame bordering the end of the slot, the steel frame engaging the membrane with at least one rigid vertical edge which supports the membrane in a vertical position and slides freely vertically relative thereto so that it supports the membrane where it engages it regardless of its vertical position relative to the membrane, and including the step of removing the steel frame gradually as the concrete starts to harden at its lower end, and at essentially the same vertical rate as the concrete hardens from the bottom upwardly so that the bottom of the steel frame gradually moves above concrete hard enough to be self-supporting but not sufficiently hard to bond to the steel frame, the steel frame moving slidably along and still supporting the vertical membrane as it moves upwardly therealong.
Claim 3
Dependent Claim
50 words
The method according to claim 1 wherein the steel frame comprises a channel with a width extending across the face of the slots and the vertical flexible membranes are attached to one flange of the channel resulting in the membranes being positioned at one side of the first concrete panels.
Claim 4
Dependent Claim
29 words
The method according to claim 1 wherein the steel frames support the flexible membranes so that they are located in the centre of the width of the concrete panels.
Claim 5
Dependent Claim
45 words
The method according to claim 1 wherein the steel frame comprises a shoulder pipe having two lips and an aperture therebetween to support a flexible membrane, the shoulder pipe being inserted into at least one end of the slot with the aperture facing the excavation.
Claim 6
Dependent Claim
28 words
The method according to claim 1 which is further characterized in that said vertical flexible membranes have bulbous opposite side edges which become embedded in the concrete panels.
Claim 7
Dependent Claim
38 words
The method according to claim 1 which is further characterized in that said steel frame is a round pipe provided at one side thereof with a pair of spaced longitudinal lips between which the flexible membrane is received.