Abstract A shoring system for building site excavating operations utilizing caisson holes drilled in spaced positions outside the building perimeter and receiving flanged pile elements with paired main piles disposed at regulated elevations and spacing and having vertically spaced support sockets adapted to receive fastener components for the support of horizontally disposed cribbing pieces that are placed progressively in inverted order to hold back loose materials as the foundation excavation is deepened. Threaded or wedge-set flange clamps are inserted in slots between adjacent cribbing pieces to engage the flanges of intermediate pile elements to provide additional cribbing support. Deadman anchors are driven outwardly into the surrounding loose materials on earth, and a cable tensioning system interconnects the anchor and waler frames placed inwardly to additionally resist forces tending to collapse the shoring system.

Inventors

  • 👤 J Meredith

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-11-07 21:57
CPC Classifications
E; E02; E02D; E02D17/00; E02D17/02; E02D17/04

Claims Analysis

Total Claims: 14
Claim 1
Independent Claim 230 words
A shoring system and method for excavation operations at building sites where loose materials may be encountered comprising the steps of drilling a plurality of caisson holes of depth greater than the depth of the intended excavation at spaced separated and aligned positions about the site to be excavated, inserting intermixed main and intermediate piles in said caisson holes with the vertical positioning of paired main piles being regulated, establishing footings of consolidated materials placed about the ends of said pile elements at the bottom of said caisson holes for resisting the transversely directed forces exerted by the unexcavated loose materials, initiating excavation operations to progressively reduce the operating level inwardly of said shoring system to expose the in-place pile elements, applying regularly spaced free standing cribbing supports disposed vertically along said main pile elements and extending inwardly therefrom, placing and supporting horizontally oriented cribbing members on and between the cribbing supports of paired main pile elements in an inverted order with the in-place cribbing supports thereby providing slot openings between adjacent cribbing members, extending additional clamping members through said slot openings to engage intermediate piles disposed between the paired main piles for the added support of said cribbing members, and, after excavation operations are completed, removing said cribbing members and supports in a bottom to top order, and subsequently removing said pile elements while leaving said footings in place.
Claim 2
Dependent Claim 230 words
A shoring system and method for excavation operations at building sites where loose materials may be encountered comprising the steps of drilling a plurality of caisson holes of depth greater than the depth of the intended excavation at spaced separated and aligned positions about the site to be excavated, inserting intermixed main and intermediate piles in said caisson holes with the vertical positioning of paired main piles being regulated, establishing footings of consolidated materials placed about the ends of said pile elements at the bottom of said caisson holes for resisting the transversely directed forces exerted by the unexcavated loose materials, initiating excavation operations to progressively reduce the operating level inwardly of said shoring system to expose the in-place pile elements, applying regularly spaced free standing cribbing supports disposed vertically along said main pile elements and extending inwardly therefrom, placing and supporting horizontally oriented cribbing members on and between the cribbing supports of paired main pile elements in an inverted order with the in-place cribbing supports thereby providing slot openings between adjacent cribbing members, extending additional clamping members through said slot openings to engage intermediate piles disposed between the paired main piles for the added support of said cribbing members, and, after excavation operations are completed, removing said cribbing members and supports in a bottom to top order, and subsequently removing said pile elements while leaving said footings in place.
Claim 3
Dependent Claim 28 words
The method as set forth in claim 1 and additionally disposing shield pieces about the lower ends of said pile elements for direct engagement with the established footings.
Claim 4
Dependent Claim 18 words
The method as set forth in claim 2 wherein said shield pieces remain in place with the footings.
Claim 5
Dependent Claim 29 words
The method as set forth in claim 2 and additionally applying a release agent to said shield pieces and wherein said shield pieces are removed with the pile elements.
Claim 6
Dependent Claim 140 words
A shoring system for excavation operations at building sites where loose materials may be encountered comprising flanged main and intermediate piles disposed iN intermixed spaced separated and aligned positions about the periphery of a site to be excavated, cribbing support elements disposed at spaced vertical positions along paired main piles, cribbing fasteners for application to the support elements of paired main piles in top to bottom order providing inwardly standing supports, cribbing members for placement on the standing support elements of said main piles for extension between main pile elements and past intermediate piles with said standing support elements preserving a slot opening between adjacent cribbing members, and auxiliary clamping members for extension through the provided slot openings for engagement with the flanges of intermediate piles disposed between the paired main piles for the added support of said cribbing members.
Claim 7
Dependent Claim 140 words
A shoring system for excavation operations at building sites where loose materials may be encountered comprising flanged main and intermediate piles disposed iN intermixed spaced separated and aligned positions about the periphery of a site to be excavated, cribbing support elements disposed at spaced vertical positions along paired main piles, cribbing fasteners for application to the support elements of paired main piles in top to bottom order providing inwardly standing supports, cribbing members for placement on the standing support elements of said main piles for extension between main pile elements and past intermediate piles with said standing support elements preserving a slot opening between adjacent cribbing members, and auxiliary clamping members for extension through the provided slot openings for engagement with the flanges of intermediate piles disposed between the paired main piles for the added support of said cribbing members.
Claim 8
Dependent Claim 54 words
Structure as set forth in claim 5 wherein said clamping members are flange-clamps having a ''''C'''' shaped body providing a slot for engagement with the flanges of said pile elements, and a body extension rigidly joined to said ''''C'''' shaped body for extension inwardly through said slot openings to an easy access working position.
Claim 9
Dependent Claim 24 words
Structure as set forth in claim 6 wherein said flange-clamp has a threaded body extension passing through the slot openings between adjacent cribbing members.
Claim 10
Dependent Claim 42 words
Structure as set forth in claim 6 wherein the body extension of said flange-clamp extends inwardly through the slot openings between adjacent cribbing members, and further comprising a lock element for engaging said body for the added support of said cribbing members.
Claim 11
Dependent Claim 96 words
Structure as set forth in claim 5 wherein said piles are disposed in caisson holes provided at the building site of depth greater than the depth of the intended excavation at space separated and aligned positions about the site, and further comprising footings of consolidated materials replaced about the ends of said piles at the bottom of said caisson holes for resisting the transversely directed forces exerted by the loose materials, and release means provided intermediate said piles and footings for facilitating the removal of said piles from said footings after excavation operations have been completed.
Claim 12
Dependent Claim 14 words
Structure as set forth in claim 9 wherein said footings are of poured concrete.
Claim 13
Dependent Claim 30 words
Structure as set forth in claim 9 wherein said release means is inclusive of shield pieces about the lower ends of said pile elements for direct engagement with said footings.
Claim 14
Dependent Claim 33 words
Structure as set forth in claim 11 wherein said shield pieces are engaged to said pile elements for removal therewith after excavation operations are completed, and wherein said footings are of poured concrete.

References Cited (Backward Citations)

AT70927B Cited
US2000492A Cited
US2340447A Cited
DE719786C Cited
US3155206A Cited
US3139163A Cited
US3226933A Cited
US3290840A Cited
US3385565A Cited
US3466874A Cited
US3490242A Cited
US3541798A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1976-04-23 1976-10-23 1977-04-24 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1980-04-23 1980-10-23 1981-04-24 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 1984-04-23 1984-10-23 1985-04-24 $7700.00 Window Closed / Lapsed