← Back to Patent Explorer
US3686876A Expired / Lapsed US ⏱️ 0.0 years remaining

Removable pier construction

Assignee: Individual
•
Filing: 1971-05-11
•
Granted: 1972-08-29
•
Expires: 1991-05-11
📄 Original PDF 🌐 Google Patents 🔄 Sync Now

Abstract

Abstract A removable pier having at least two sections pivotably joined end to end and extending from a footing on a shore into a body of water. The pier sections are removably supported on permanent footings for stability. Booms having cable guides are removably mounted on leg extensions of the inner pier section. Cables, driven by winches, pass through the cable guides on the boom and engage the outer pier section for its removal from the water by rotation about its pivotable connection with the inner pier section. The booms are transferred to mounts on the shore at the sides of the pier for removal of the inner pier section from the water with the outer pier section in overlying position. The outer pier section is preferably slightly shorter than the inner pier section so that both pier sections can be stored in upright position on the shore ready for repositioning in the water.

Inventors

  • 👤 James E Muschell

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-11-07 21:41
CPC Classifications
E; E02; E02B; E02B3/00; E02B3/04; E02B3/06; E02B3/068

Claims Analysis

Total Claims: 16
Claim 1
Independent Claim 333 words
In a pier construction extending outwardly from a shore into a body of water, said pier construction comprising: a footing on said shore adjacent said body of water; a first elongated pier section having an inner end and an outer end; means hinging said first pier section inner end to said shore footing; means for removably supporting said outer end of said first pier section above the surface of the water; a second elongated pier section having an inner end and an outer end; means for hinging said inner end of said second pier section to said outer end of said first pier section so that said second pier section can rotate on its inner end about said outer end of said first pier section; means for removably supporting said outer end of said second pier section above the surface of water; and means for removing said first and second pier sections from the water, the improvement in said pier section removal means comprising: boom support means extending upwardly from at least one side of said first pier section outer end; cable engaging means on said second pier section spaced outwardly of said second pier section inner end; a winch on said shore footing; a cable wound by said winch and having on its outer end means to engage said cable engaging means; a boom removably supported on said boom support means, said boom being spaced outwardly of the side edges of said first pier section; guide means mounted on said boom for said cable, and said cable extending through said guide means and secured to said cable engaging means on said second pier section; whereby said second pier section can be removed from the water by winding said winch, thereby rotating said second pier section about said hinging means at said inner end of said second pier section until said second pier section is substantially vertical, and by thereafter unwinding said winch until said second pier section overlies said first pier section.
Claim 2
Dependent Claim 333 words
In a pier construction extending outwardly from a shore into a body of water, said pier construction comprising: a footing on said shore adjacent said body of water; a first elongated pier section having an inner end and an outer end; means hinging said first pier section inner end to said shore footing; means for removably supporting said outer end of said first pier section above the surface of the water; a second elongated pier section having an inner end and an outer end; means for hinging said inner end of said second pier section to said outer end of said first pier section so that said second pier section can rotate on its inner end about said outer end of said first pier section; means for removably supporting said outer end of said second pier section above the surface of water; and means for removing said first and second pier sections from the water, the improvement in said pier section removal means comprising: boom support means extending upwardly from at least one side of said first pier section outer end; cable engaging means on said second pier section spaced outwardly of said second pier section inner end; a winch on said shore footing; a cable wound by said winch and having on its outer end means to engage said cable engaging means; a boom removably supported on said boom support means, said boom being spaced outwardly of the side edges of said first pier section; guide means mounted on said boom for said cable, and said cable extending through said guide means and secured to said cable engaging means on said second pier section; whereby said second pier section can be removed from the water by winding said winch, thereby rotating said second pier section about said hinging means at said inner end of said second pier section until said second pier section is substantially vertical, and by thereafter unwinding said winch until said second pier section overlies said first pier section.
Claim 3
Dependent Claim 33 words
A pier construction according to claim 1 wherein said boom support means extends upwardly from said removable support means for said outer end of said first pier section above said first pier section.
Claim 4
Dependent Claim 22 words
A pier construction according to claim 2 wherein said boom has a tubular bottom portion which telescopes over said boom support means.
Claim 5
Dependent Claim 124 words
A pier construction according to claim 2 and further comprising at least one boom support means extending upwardly from said shore footing between said body of water and said winch, and outside of the side edges of said first pier section; cable engaging means on said first pier section spaced outwardly of said inner end thereof; whereby said boom can be removably mounted on said footing boom support means, said cable can be secured to said cable engaging means on said first pier section for removal of said first and second pier sections after said second pier section has been positioned to overlie said first pier section by raising said first section about said hinge means at said inner end of said pier section.
Claim 6
Dependent Claim 98 words
A pier construction according to claim 1 and further comprising at least one boom support means on said shore footing between said body of water and said winch, and outside of the side edges of said first pier section; cable engaging means on said first pier section; whereby said first and second pier sections can be removed from the water with said second pier section overlying said first pier section by securing said cable to said cable engaging means on saId first pier section, placing said boom on said shore footing boom support means and winding said winch.
Claim 7
Dependent Claim 35 words
A pier construction according to claim 5 wherein said shore footing boom support means extends upwardly of said shore footing; and said boom has a tubular bottom portion which telescopes over said boom support means.
Claim 8
Dependent Claim 56 words
A pier construction according to claim 1 wherein said removable supporting means for said first and second pier sections comprises: legs extending downwardly from said first and second pier sections; a permanent footing at the bottom of said body of water beneath said legs; sockets on the top portion of said footing for receiving said legs.
Claim 9
Dependent Claim 26 words
A pier construction according to claim 7 and further comprising fastening means between said legs and said footings for releasably securing said legs in said sockets.
Claim 10
Dependent Claim 20 words
A pier construction according to claim 7 wherein said legs are rigidly fixed to said first and second pier sections.
Claim 11
Dependent Claim 150 words
In a pier construction extending outwardly from a shore into a body of water, said pier construction comprising: an elongated pier section having an inner end and an outer end; means supporting said inner end of said pier section above said body of water for rotation of said pier section about its inner end; means for removably supporting said outer end of said pier section above the surface of water; the improvement in said removably supporting means comprising: legs extending downwardly from said outer end of said pier section; the bottom portion of said legs being open and forming sockets; a permanent footing at the bottom of the water beneath said leg; positioning rods extending up from the top portion of said footing for engaging the open bottom of said legs, and fastening means between said legs and said footing for releasably and rigidly securing said legs to said footings.
Claim 12
Dependent Claim 150 words
In a pier construction extending outwardly from a shore into a body of water, said pier construction comprising: an elongated pier section having an inner end and an outer end; means supporting said inner end of said pier section above said body of water for rotation of said pier section about its inner end; means for removably supporting said outer end of said pier section above the surface of water; the improvement in said removably supporting means comprising: legs extending downwardly from said outer end of said pier section; the bottom portion of said legs being open and forming sockets; a permanent footing at the bottom of the water beneath said leg; positioning rods extending up from the top portion of said footing for engaging the open bottom of said legs, and fastening means between said legs and said footing for releasably and rigidly securing said legs to said footings.
Claim 13
Dependent Claim 21 words
A pier construction according to claim 10 wherein said legs are rigidly fixed to said outer end of said pier section.
Claim 14
Dependent Claim 117 words
A pier construction according to claim 10 and further comprising a second elongated pier section having an inner end and an outer end; means for hinging said inner end of said second pier section to said outer end of said first pier section so that said second pier section can rotate on its inner end about said outer end of said first pier section; a pair of legs fixed to said outer end of said second pier section and extending downwardly to the bottom of the body of water; a second permanent footing beneath said legs of said second pier section; said second footing having sockets engaging bottom portions of said legs of said second pier section.
Claim 15
Dependent Claim 249 words
In a pier construction extending outwardly from a shore into a body of water, said pier construction comprising: an elongated pier section having an inner end and an outer end; means supporting said inner end of said elongated pier section above said body of water for rotation about said inner end; means for supporting said outer end of said pier section above said body of water; and means for removing said first and second pier section from the water, the improvement in said pier section removal means comprising: boom support means fixed to and extending upwardly from at least one side of said support means adjacent to said inner end of said pier section; a winch mounted on said support means; a cable wound by said winch and having on its outer end means to engage an outer portion of said pier section; a boom removably supported on said boom support means, said boom being spaced outwardly of the side edges of said pier section; guide means mounted on said boom for said cable, and said cable extending through said guide means and secured to an outer portion of said pier section; whereby said pier section can be removed from the water by winding said winch, thereby rotating said pier section about said support means at said inner end of said pier section until said pier section is substantially vertical, and by thereafter unwinding said winch until said pier section overlies at least a portion of said support means.
Claim 16
Dependent Claim 249 words
In a pier construction extending outwardly from a shore into a body of water, said pier construction comprising: an elongated pier section having an inner end and an outer end; means supporting said inner end of said elongated pier section above said body of water for rotation about said inner end; means for supporting said outer end of said pier section above said body of water; and means for removing said first and second pier section from the water, the improvement in said pier section removal means comprising: boom support means fixed to and extending upwardly from at least one side of said support means adjacent to said inner end of said pier section; a winch mounted on said support means; a cable wound by said winch and having on its outer end means to engage an outer portion of said pier section; a boom removably supported on said boom support means, said boom being spaced outwardly of the side edges of said pier section; guide means mounted on said boom for said cable, and said cable extending through said guide means and secured to an outer portion of said pier section; whereby said pier section can be removed from the water by winding said winch, thereby rotating said pier section about said support means at said inner end of said pier section until said pier section is substantially vertical, and by thereafter unwinding said winch until said pier section overlies at least a portion of said support means.

References Cited (Backward Citations)

US1358951A Cited
US1704841A Cited
US2592626A Cited
US2618124A Cited
US2948121A Cited
US3043109A Cited
US3543523A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1975-08-29 1976-02-28 1976-08-29 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1979-08-29 1980-02-28 1980-08-29 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 1983-08-29 1984-02-28 1984-08-29 $7700.00 Window Closed / Lapsed

Assigned Categories & Tags

No categories assigned to this patent yet.

Assign Category Tag