← Back to Patent Explorer
US3647414A Expired / Lapsed US ⏱️ 0.0 years remaining

Extraction of iron from titaniferous ores

Assignee: NL Chemicals Inc
•
Filing: 1969-07-31
•
Granted: 1972-03-07
•
Expires: 1989-07-31
📄 Original PDF 🌐 Google Patents 🔄 Sync Now

Abstract

Abstract The present invention relates to the removal of iron values from titaniferous ores so as to produce a titanium concentrate suitable for chlorination and is characterized by leaching the iron values from a metallized titaniferous ore in two stages using, in combination, a dilute solution of a mineral acid and preferably waste sulfuric acid in the first stage and an oxidizing leach solution in the second stage.

Inventors

  • 👤 Arnold E Nilsen

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-11-04 12:57
CPC Classifications
C; C22; C22B; C22B34/00; C22B34/10; C22B34/12; C22B34/1204; C22B34/1213

Claims Analysis

Total Claims: 10
Claim 1
Independent Claim 27 words
Method for leaching the iron from finely divided ilmenite ores to produce a titanium dioxide concentrate according to claim 1 wherein the oxidizing agent is ferric sulfate.
Claim 2
Dependent Claim 27 words
Method for leaching the iron from finely divided ilmenite ores to produce a titanium dioxide concentrate according to claim 1 wherein the oxidiZing agent is ferric chloride.
Claim 3
Dependent Claim 27 words
Method for leaching the iron from finely divided ilmenite ores to produce a titanium dioxide concentrate according to claim 1 wherein the oxidizing agent is nitric acid.
Claim 4
Dependent Claim 38 words
Method for leaching the iron from finely divided ilmenite ores to produce a titanium dioxide concentrate according to claim 1 wherein said oxidizing leach is effected by introducing air or oxygen into the dilute sulfuric acid leach solution.
Claim 5
Dependent Claim 30 words
Method for leaching the iron from ilmenite ores to produce a titanium dioxide concentrate according to claim 5 wherein the oxidizing leach is accelerated by the addition of gaseous SO2.
Claim 6
Dependent Claim 39 words
Method for leaching the iron from finely divided ilmenite ores to produce a titanium dioxide concentrate according to claim 1 wherein the partially leached ore produced by said acid leach is filtered and washed prior to said oxidizing leach.
Claim 7
Dependent Claim 43 words
Method for leaching iron from finely divided titaniferous ores according to claim 1, wherein leaching with said dilute sulfuric acid is carried out for from 5 to 15 minutes and leaching with said oxidizing agent is carried out for 5 to 8 minutes.
Claim 8
Dependent Claim 61 words
Method for leaching the iron from finely divided ilmenite ores according to claim 1 wherein the dilute sulfuric acid is waste sulfuric acid having an acid strength within the range from 3 to 24% H2SO4 and said waste sulfuric acid being used in an amount corresponding to an acid to total iron ratio in the range from 1:1 to about 3:1.
Claim 9
Dependent Claim 40 words
Method for leaching the iron from finely divided ilmenite ores to produce a titanium dioxide concentrate according to claim 1 wherein the finely divided ore is roasted in an oxidizing atmosphere prior to reducing the iron values to metallic iron.
Claim 10
Dependent Claim 203 words
Method for leaching the iron from finely divided ilmenite ores to produce a titanium dioxide concentrate comprising the steps of: upgrading the finely divided ore by removing gangue materials, heating the gangue-free ore under reducing conditions to reduce the iron values in said ore to metallic iron, leaching the metallized ore with waste sulfuric acid at a concentration in the range of from 5 to 15% H2SO4, at an acid pH, and at a temperature from 25*-100* C. for a period of time from 5- 15 minutes to dissolve a major portion of the metallized iron from said ore, said waste sulfuric acid being added in an amount corresponding to an acid to total iron ratio of about 3:1, and thereafter leaching the acid leached ore with an oxidizing leach comprising an aqueous solution of a water-soluble ferric salt, said salt being added to said acid leach solution in an amount corresponding to a ferric salt to total iron ratio of from about 0.25:1 to 1:1, and at a temperature of from 25* to 100* C. for from 5 to 8 minutes to dissolve the remaining metallized iron from said ore, recovering the leached ore by filtration, and then water-washing the leached ore.

References Cited (Backward Citations)

US513490A Cited
CA767560A Cited
US1084600A Cited
US981451A Cited
US1032400A Cited
US1021768A Cited
US2804375A Cited
US2829964A Cited
US3169853A Cited
US3146091A Cited
US3293027A Cited
US3457037A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1975-03-07 1975-09-06 1976-03-07 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1979-03-07 1979-09-06 1980-03-07 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 1983-03-07 1983-09-06 1984-03-07 $7700.00 Window Closed / Lapsed

Assigned Categories & Tags

No categories assigned to this patent yet.

Assign Category Tag