Claim 1
Independent Claim
190 words
An automated customer order promising and confirming method for implementation on a computer, providing for the customer order promising capability based on user production capacity verification to aid a user in making decisions that will improve a customer order promising process, said method comprising the steps of: prompting the user to input to the computer customer information and item requirements; comparing customer item requirements to inventory records stored in said computer; based on said comparing step, determining if inventory is currently available to meet customer requirements; if inventory is not currently available and there is a customer specified date for delivery of the item, determining if inventory will be available in planned production of the item; if inventory will not be available in planned production, using a material requirement planning system, determining net time-phased item requirements against on-hand and on-order inventory; using a capacity requirements planning system, determining whether user production capacity is available to meet a customer specified date; and if the customer specified date can not be met, establishing production availability of the item and determining a best available date for delivery of the item to the customer.
Claim 2
Dependent Claim
190 words
An automated customer order promising and confirming method for implementation on a computer, providing for the customer order promising capability based on user production capacity verification to aid a user in making decisions that will improve a customer order promising process, said method comprising the steps of: prompting the user to input to the computer customer information and item requirements; comparing customer item requirements to inventory records stored in said computer; based on said comparing step, determining if inventory is currently available to meet customer requirements; if inventory is not currently available and there is a customer specified date for delivery of the item, determining if inventory will be available in planned production of the item; if inventory will not be available in planned production, using a material requirement planning system, determining net time-phased item requirements against on-hand and on-order inventory; using a capacity requirements planning system, determining whether user production capacity is available to meet a customer specified date; and if the customer specified date can not be met, establishing production availability of the item and determining a best available date for delivery of the item to the customer.
Claim 3
Dependent Claim
67 words
The automated order promising method as recited in claim 1 wherein the step of using a material requirement planning system and determining net time-phase item requirements comprises the steps of: performing an explosion of customer requirements using item data stored in said computer; offsetting requirements by lead times to obtain time-phased requirements for the item; and netting time-phased requirements against on-hand and on-order inventory of the item.
Claim 4
Dependent Claim
81 words
The automated order promising method as recited in claim 2 wherein if material is available for the item, said step of using a capacity requirements planning system and determining whether user production capacity is available comprises the steps of: determining a load imposed by customer requirements on user production capacity; adding the load from the customer requirements to cumulative load requirements on user production capacity; and then subtracting a load determined by said adding step from a predefined user production capacity.
Claim 5
Dependent Claim
102 words
The automated order promising method as recited in claim 2 wherein if material is not available for the item, then performing the following steps: notifying the user that material is not available; using said time-phased requirements, determining a load imposed by customer requirements on user production capacity; adding the load from the customer requirements to cumulative load requirements on user production capacity; then subtracting a load determined by said adding step from a predefined user production capacity; comparing a difference obtained in said subtracting step with management rules for resource scheduling; and if capacity exists, compiling best available dates for customer requirements.
Claim 6
Dependent Claim
31 words
The automated order promising method as recited in claim 4 further comprising the step of displaying to the user the capability of meeting customer requested dates or system recommended alternate dates.
Claim 7
Dependent Claim
52 words
The automated order promising method as recited in claim 4 wherein if capacity does not exist for a given production period of user production capacity, then performing the following steps: incrementing the production period; and repeating said adding, subtracting and comparing steps to determine if capacity exists for the next production period.